Skip to main content
PermitBase

Residential Building Permit in Pleasant View, Utah

Required for new single-family and two-family residential construction and any work regulated by the statewide-adopted IRC/IBC. Pleasant View uses its own valuation-based 'Table for Permit Fees' (Consolidated Fee Schedule, as of July 1, 2026) plus a locally published Residential One- and Two-Family Valuation per-square-foot table for computing project valuation.

Verified 2026-07-08 · Source

When you need this permit

  • New single-family or two-family residential construction
  • Any work regulated by the statewide-adopted IRC
  • Structural modifications regulated by the statewide-adopted IBC/IRC
  • Building Permit Application submitted electronically through the City Inspect online portal (utah.cityinspect.com), with required attachments uploaded

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 2 required documents checked.

This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29

Fee schedule

Building Permit Fee — valuation-based Table for Permit Fees (Appendix L, per Pleasant View Consolidated Fee Schedule, as of July 1, 2026)Pleasant View City Consolidated Fee Schedule (as of July 1, 2026), page 18, 'Table for Permit Fees, Appendix L.' Valuation computed using the city's own Residential One- and Two-Family Valuation per-square-foot table (same document, page 19): Main floor $112.90/sq ft, Upper floor $75.26/sq ft (2/3 of main), Unfinished basement $15.00/sq ft, Finished basement $26.90/sq ft, Attached garage $23.68/sq ft, Unattached garage/accessory building $37.33/sq ft, Pole building $25.00/sq ft.
$1–$500: $24 flat. $501–$2,000: $24 for the first $500, plus $3 per additional $100 (or fraction). $2,001–$40,000: $69 for the first $2,000, plus $11 per additional $1,000 (or fraction). $40,001–$100,000: $487 for the first $40,000, plus $9 per additional $1,000. $100,001–$500,000: $1,027 for the first $100,000, plus $7 per additional $1,000. $500,001–$1,000,000: $3,827 for the first $500,000, plus $5 per additional $1,000. $1,000,001–$5,000,000: $6,327 for the first $1,000,000, plus $3 per additional $1,000. $5,000,001 and over: $18,327 for the first $5,000,000, plus $1 per additional $1,000.
Plan Check FeePleasant View City Consolidated Fee Schedule (as of July 1, 2026), page 2: 'Plan Check Fee ... (50% of building fee for residential, 65% for commercial)' and 'Plan Check Fee (for exact plans) ... 35% of building fee for residential.'
50% of building fee (residential, standard plans); 35% of building fee (residential, for exact/duplicate plans)
State Fee (surcharge)Pleasant View City Consolidated Fee Schedule (as of July 1, 2026), page 5: 'State Fee ... 1% of building fee.' This is the statewide Uniform Building Code Commission surcharge collected by all Utah municipalities.
1% of building fee
Database & Support FeePleasant View City Consolidated Fee Schedule (as of July 1, 2026), page 2.
$40.00
Re-inspection FeePleasant View City Consolidated Fee Schedule (as of July 1, 2026), page 7.
$150.00

Review timeline

Plan reviewPleasant View’s published plan-review target
7–10 business days

How long did your Residential Building Permit permit actually take in Pleasant View?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    Building

    Physical inspections are contracted to Sunrise Engineering; schedule via the City Inspect portal (pleasantview.cityinspect.com) or by calling Sunrise Engineering at 1-800-560-6151, per Pleasant View's official Permits and Inspections pages.

  2. 2

    Electrical

    Electrical inspection performed as part of the combined building inspection process; flat $75.00 inspection fee per the Consolidated Fee Schedule.

  3. 3

    Plumbing

    Plumbing inspection; flat $75.00 inspection fee per the Consolidated Fee Schedule. Water and sewer lateral inspections are scheduled directly with the City Office (801-782-8529), not through Sunrise Engineering.

  4. 4

    Mechanical/Gas

    Mechanical/Gas Administration inspection; flat $75.00 fee per the Consolidated Fee Schedule.

  5. 5

    Final

    Approved building plans must be on the job site at time of each and every inspection, per Pleasant View's official Permits page. Work must commence within 6 months of permit issuance, and the permit remains open only as long as inspections and work continue at least every 6 months.

See the full Pleasant View inspection guide — scheduling & re-inspection fees →

Tips

  • Pleasant View's Building Department office hours are Mon–Thu 8:00 AM–5:00 PM and Fri 8:00 AM–12:00 PM (half-day Friday), unlike some neighboring Weber County cities that close entirely on Friday.
  • Physical building inspections are contracted to Sunrise Engineering (schedule at 1-800-560-6151), while water/sewer lateral inspections are scheduled directly with the City Office (801-782-8529) — two different contacts depending on inspection type.
  • All Building Permits are submitted electronically through the City Inspect portal — there is no paper/in-person application process described on the city's official Permits page.
  • Permits stay open only if inspections and work occur at least every 6 months; work must commence within 6 months of issuance or the permit lapses, per the city's official Permits page.
  • The city's Consolidated Fee Schedule labels its valuation fee table 'Appendix L, 2015 IRC' even though Utah's statewide code has since moved to the 2021 I-Code cycle — this is stale labeling on a still-current fee table, not evidence of an outdated adopted code.

Frequently asked questions

Pleasant View requires a residential building permit for: New single-family or two-family residential construction; Any work regulated by the statewide-adopted IRC; Structural modifications regulated by the statewide-adopted IBC/IRC; Building Permit Application submitted electronically through the City Inspect online portal (utah.cityinspect.com), with required attachments uploaded. If your project isn't listed, confirm with Pleasant View City Planning, Zoning & Building Department at (801) 782-8529 before starting work.

Per the city's Consolidated Fee Schedule (as of July 1, 2026), fees are valuation-based using the Table for Permit Fees (Appendix L): e.g., a project valued $100,001–$500,000 costs $1,027 plus $7 per additional $1,000 of valuation. Valuation is computed using the city's own per-square-foot table (main floor $112.90/sq ft, upper floor $75.26/sq ft). A 50% Plan Check Fee (residential) and a 1% State Fee surcharge also apply on top of the base building fee.

Per Pleasant View's official Permits page, inspector review of a submitted building permit application takes an average of 7 to 10 business days.

You'll need: Building Permit Application (City Inspect); Site Plan. See the required-documents checklist on this page for details on each.

Pleasant View requires 5 inspection(s) for a residential building permit, in order: Building, Electrical, Plumbing, Mechanical/Gas, Final. Schedule each through Pleasant View City Planning, Zoning & Building Department ((801) 782-8529).

Apply through Pleasant View City Planning, Zoning & Building Department at 520 W Elberta Dr, Pleasant View, UT 84414. Phone: (801) 782-8529. Office hours: Mon–Thu 8:00 AM – 5:00 PM; Fri 8:00 AM – 12:00 PM. Official information: https://www.pleasantviewut.gov/168/Planning-Zoning-Building.

Pleasant View, Utah has adopted: 2024 International Building Code (IBC), including Appendices C and J — current statewide code per Utah Code § 15A-2-103(1)(a), in force since July 1, 2026, under the statewide preemption mandate of § 15A-1-204 (State Construction and Fire Codes Act); Pleasant View's own codified Title 15.04 text still references the 2000 IBC (Ord. 2002-10), but that codification is stale and superseded by the mandatory statewide cycle.; 2021 International Residential Code (IRC) — current statewide code per Utah Code § 15A-2-103(1)(b) (unchanged by the July 1, 2026 code cycle flip); Pleasant View's Consolidated Fee Schedule (as of July 1, 2026) still labels its Table for Permit Fees 'Appendix L, 2015 IRC,' which is stale fee-table boilerplate, not evidence the city enforces an outdated code edition — plan review and inspections apply the current statewide IRC per § 15A-1-204.; 2024 International Plumbing Code (IPC) — current statewide code per Utah Code § 15A-2-103(1)(d); Pleasant View's codified Title 15.16.010 references the 2000 IPC (stale codification), superseded by § 15A-1-204.; 2024 International Mechanical Code (IMC) / International Fuel Gas Code (IFGC) — current statewide code per Utah Code § 15A-2-103(1)(e)/(f); Pleasant View's codified Title 15.12.010 references the 2000 IMC (stale codification), superseded by § 15A-1-204.; 2024 International Energy Conservation Code (IECC) with Utah amendments — current statewide code per Utah Code § 15A-2-103(1)(h) (a single edition applies statewide, no separate residential/commercial split); Pleasant View's codified Title 15.28.010 references the 2000 IECC (stale codification), superseded by § 15A-1-204.; 2023 National Electrical Code (NEC) — current statewide code per Utah Code § 15A-2-103(1)(g) (unchanged by the July 1, 2026 code cycle flip); Pleasant View's codified Title 15.20.010 references the 1999 NEC (stale codification), superseded by § 15A-1-204.. Local amendments apply — see the Pleasant View overview page for the full list.

Sources & verification

Verified against official sources. Last reviewed 2026-07-08.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Pleasant View building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.