Solar PV / Solar Panel Installation Permit in Pleasant View, Utah

Pleasant View has no separate solar or solar-PV permit type and no solar fee line. The 19-page Consolidated Fee Schedule (as of July 1, 2026) contains no mention of solar, photovoltaic, PV, or renewable energy, and neither the city's Permits page nor its Building & Construction Applications page (which lists City Inspect, Business License, Dog License, Subdivisions/Zone Changes, and Utility Services) offers a solar-specific application. Residential rooftop and ground-mount solar PV is billed as a standard Building Permit for the structural and mounting scope — the valuation-based Table for Permit Fees, Appendix L, with project valuation taken from the most recent ICC Building Valuation Data — plus the flat $75.00 Electrical Inspection fee for the electrical interconnection.

Verified 2026-07-21 · Source

When you need this permit

  • Rooftop-mounted or ground-mount solar PV system installation, regulated by the statewide-adopted IBC/IRC for the structural/mounting scope and by the statewide-adopted 2023 National Electrical Code (Utah Code § 15A-2-103(1)(g)) for the electrical interconnection scope
  • Building Permit Application submitted electronically through the City Inspect online portal (utah.cityinspect.com), with required attachments uploaded
  • Project valuation established per the city's 'ICC Building Valuation Data (most recent data available)' for computing the Building Permit Fee, since Pleasant View does not publish a solar-specific valuation formula

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 1 required documents checked.

This checker covers one permit. A full project usually triggers several — our checklist will assemble all of them, free →

Fee schedule

Building Permit Fee — valuation-based Table for Permit Fees (Appendix L, per Pleasant View Consolidated Fee Schedule, as of July 1, 2026)
Pleasant View City Consolidated Fee Schedule (as of July 1, 2026), page 18, 'Table for Permit Fees, Appendix L' — the same general table used for all other Building Permits here. Show full citationPleasant View City Consolidated Fee Schedule (as of July 1, 2026), page 18, 'Table for Permit Fees, Appendix L' — the same general table used for all other Building Permits here. The schedule publishes no separate solar-specific valuation table, so project valuation is established per the schedule's general 'ICC Building Valuation Data (most recent data available)' line on page 3.
$1–$500: $24 flat. $501–$2,000: $24 for the first $500, plus $3 per additional $100 (or fraction). $2,001–$40,000: $69 for the first $2,000, plus $11 per additional $1,000 (or fraction). $40,001–$100,000: $487 for the first $40,000, plus $9 per additional $1,000. $100,001–$500,000: $1,027 for the first $100,000, plus $7 per additional $1,000. $500,001–$1,000,000: $3,827 for the first $500,000, plus $5 per additional $1,000. $1,000,001–$5,000,000: $6,327 for the first $1,000,000, plus $3 per additional $1,000. $5,000,001 and over: $18,327 for the first $5,000,000, plus $1 per additional $1,000.
Electrical Inspection Fee (interconnection/electrical scope)
Pleasant View City Consolidated Fee Schedule (as of July 1, 2026), page 3: 'Electrical Inspection.................................................................................................................... Show full citationPleasant View City Consolidated Fee Schedule (as of July 1, 2026), page 3: 'Electrical Inspection.................................................................................................................... $75.00.' Solar PV electrical work is billed under this same flat fee, as set out in the Electrical Permit entry.
$75.00
Plan Check Fee
Pleasant View City Consolidated Fee Schedule (as of July 1, 2026), page 3: 'Plan Check Fee... Show full citationPleasant View City Consolidated Fee Schedule (as of July 1, 2026), page 3: 'Plan Check Fee... (50% of building fee for residential, 65% for commercial).' Applies to solar installations billed under the general valuation-based Building Permit Fee, same as any other building permit.
50% of building fee (residential); 65% of building fee (commercial)
State Fee (surcharge)Pleasant View City Consolidated Fee Schedule (as of July 1, 2026), page 5: 'State Fee... 1% of building fee.' Statewide Uniform Building Code Commission surcharge collected by all Utah municipalities.
1% of building fee
Database & Support FeePleasant View City Consolidated Fee Schedule (as of July 1, 2026), page 3.
$40.00

Review timeline

Plan reviewTypical estimate — confirm current times with the Pleasant View building department
~7–10 business days

How long did your Solar PV / Solar Panel Installation Permit permit actually take in Pleasant View?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    Building / Structural (racking and roof or ground-mount attachment)

    Verifies the solar array's mounting/racking structural attachment; scheduled via City Inspect (pleasantview.cityinspect.com) or Sunrise Engineering (1-800-560-6151), per Pleasant View's official Inspections page.

  2. 2

    Electrical

    Verifies the solar interconnection wiring and equipment; flat $75.00 inspection fee per the Consolidated Fee Schedule.

  3. 3

    Final

    Approved building plans must be on the job site at time of each and every inspection, per Pleasant View's official Permits page.

See the full Pleasant View inspection guide — scheduling & re-inspection fees →

Tips

  • Solar PV installations have no dedicated permit type or fee tier in Pleasant View. The project is billed under the general valuation-based Building Permit Fee (Table for Permit Fees, Appendix L) plus the flat $75.00 Electrical Inspection fee for the electrical scope, exactly as set out in the Electrical Permit entry.
  • A full page-by-page read of the entire 19-page Consolidated Fee Schedule (as of July 1, 2026) — covering Subdivisions, Building Permits, Signs, Planning & Zoning, Utilities, Animal Impound, Other Fees, and Business License Fees — found no 'solar,' 'photovoltaic,' 'PV,' or 'renewable energy' line item anywhere in the document.
  • Confirm current solar-specific submittal expectations (e.g., structural engineering letter for the racking system, single-line electrical diagram) directly with the Building Department, (801) 782-8529, before applying, since Pleasant View does not publish a standalone solar checklist the way some other Utah jurisdictions do.
  • Physical inspections are contracted to Sunrise Engineering (schedule at 1-800-560-6151); the City Office (801-782-8529) does not perform building or electrical inspections directly.

Frequently asked questions

Pleasant View requires a solar pv / solar panel installation permit for: Rooftop-mounted or ground-mount solar PV system installation, regulated by the statewide-adopted IBC/IRC for the structural/mounting scope and by the statewide-adopted 2023 National Electrical Code (Utah Code § 15A-2-103(1)(g)) for the electrical interconnection scope; Building Permit Application submitted electronically through the City Inspect online portal (utah.cityinspect.com), with required attachments uploaded; Project valuation established per the city's 'ICC Building Valuation Data (most recent data available)' for computing the Building Permit Fee, since Pleasant View does not publish a solar-specific valuation formula. If your project isn't listed, confirm with Pleasant View City Planning, Zoning & Building Department at (801) 782-8529 before starting work.

There is no solar-specific fee. The project pays the general valuation-based Building Permit Fee (Table for Permit Fees, Appendix L) plus a 50% (residential) or 65% (commercial) Plan Check Fee, a 1% State Fee surcharge, a $40.00 Database & Support Fee, and a flat $75.00 Electrical Inspection fee for the interconnection wiring, per the Consolidated Fee Schedule (as of July 1, 2026).

Plan review for a solar pv / solar panel installation permit in Pleasant View typically runs 7–10 business days. This is an estimate, not a published figure — confirm current review times with Pleasant View City Planning, Zoning & Building Department at (801) 782-8529.

You'll need: Building Permit Application (City Inspect). See the required-documents checklist on this page for details on each.

Pleasant View requires 3 inspection(s) for a solar pv / solar panel installation permit, in order: Building / Structural (racking and roof or ground-mount attachment), Electrical, Final. Schedule each through Pleasant View City Planning, Zoning & Building Department ((801) 782-8529).

Apply through Pleasant View City Planning, Zoning & Building Department at 520 W Elberta Dr, Pleasant View, UT 84414. Phone: (801) 782-8529. Office hours: Mon–Thu 8:00 AM – 5:00 PM; Fri 8:00 AM – 12:00 PM. Official information: https://www.pleasantviewut.gov/168/Planning-Zoning-Building.

Pleasant View, Utah has adopted: 2024 International Building Code (IBC), including Appendices C and J — current statewide code per Utah Code § 15A-2-103(1)(a), in force since July 1, 2026, under the statewide preemption mandate of § 15A-1-204 (State Construction and Fire Codes Act); Pleasant View's own codified Title 15.04 text still references the 2000 IBC (Ord. 2002-10), but that codification is stale and superseded by the mandatory statewide cycle.; 2021 International Residential Code (IRC) — current statewide code per Utah Code § 15A-2-103(1)(b) (unchanged by the July 1, 2026 code cycle flip); Pleasant View's Consolidated Fee Schedule (as of July 1, 2026) still labels its Table for Permit Fees 'Appendix L, 2015 IRC,' which is stale fee-table boilerplate, not evidence the city enforces an outdated code edition — plan review and inspections apply the current statewide IRC per § 15A-1-204.; 2024 International Plumbing Code (IPC) — current statewide code per Utah Code § 15A-2-103(1)(d); Pleasant View's codified Title 15.16.010 references the 2000 IPC (stale codification), superseded by § 15A-1-204.; 2024 International Mechanical Code (IMC) / International Fuel Gas Code (IFGC) — current statewide code per Utah Code § 15A-2-103(1)(e)/(f); Pleasant View's codified Title 15.12.010 references the 2000 IMC (stale codification), superseded by § 15A-1-204.; 2024 International Energy Conservation Code (IECC) with Utah amendments — current statewide code per Utah Code § 15A-2-103(1)(h) (a single edition applies statewide, no separate residential/commercial split); Pleasant View's codified Title 15.28.010 references the 2000 IECC (stale codification), superseded by § 15A-1-204.; 2023 National Electrical Code (NEC) — current statewide code per Utah Code § 15A-2-103(1)(g) (unchanged by the July 1, 2026 code cycle flip); Pleasant View's codified Title 15.20.010 references the 1999 NEC (stale codification), superseded by § 15A-1-204.. Local amendments apply — see the Pleasant View overview page for the full list.

No. Pleasant View publishes no distinct solar or solar-PV permit type or fee. Under the city's Consolidated Fee Schedule (as of July 1, 2026), a solar PV installation is billed as a standard Building Permit for the structural and mounting work (valuation-based Table for Permit Fees, Appendix L), plus the flat $75.00 Electrical Inspection fee for the electrical interconnection scope.

Sources & verification

Verified against official sources. Last reviewed 2026-07-21.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Pleasant View building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.

Pleasant View's permit history isn't searchable here yet