Commercial Tenant Improvement / Tenant Finish Permit in Pleasant View, Utah

Required for tenant improvement and interior remodel work in existing commercial buildings in Pleasant View. Uses the same valuation-based Table for Permit Fees (Appendix L) and 65% commercial Plan Check Fee as new commercial construction — tenant improvement is not one of the enumerated categories in the city's flat-fee 'Misc. permits' bucket (which covers only demolition, fence, mechanical-only, plumbing-only, and 2nd/3rd-layer re-roof), so it is billed on the general valuation-based schedule.

Verified 2026-07-19 · Source

When you need this permit

  • Tenant improvement / interior remodel work in an existing commercial building, regulated by the statewide-adopted IBC
  • Building Permit Application submitted through the City Inspect online portal
  • Not eligible for the city's flat $100.00-minimum 'Misc. permits' fee category, which per the Consolidated Fee Schedule is limited to demolition, fence, mechanical-only, plumbing-only, and 2nd/3rd-layer re-roof work

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 1 required documents checked.

This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29

Fee schedule

Building Permit Fee — valuation-based Table for Permit Fees (Appendix L)Pleasant View City Consolidated Fee Schedule (as of July 1, 2026), page 18 — same table used for new commercial and residential construction; Pleasant View does not publish a distinct tenant-improvement valuation table.
$1–$500: $24 flat. $501–$2,000: $24 for the first $500, plus $3 per additional $100 (or fraction). $2,001–$40,000: $69 for the first $2,000, plus $11 per additional $1,000 (or fraction). $40,001–$100,000: $487 for the first $40,000, plus $9 per additional $1,000. $100,001–$500,000: $1,027 for the first $100,000, plus $7 per additional $1,000. $500,001–$1,000,000: $3,827 for the first $500,000, plus $5 per additional $1,000. $1,000,001–$5,000,000: $6,327 for the first $1,000,000, plus $3 per additional $1,000. $5,000,001 and over: $18,327 for the first $5,000,000, plus $1 per additional $1,000.
Plan Check Fee (commercial)Pleasant View City Consolidated Fee Schedule (as of July 1, 2026), page 2: 'Plan Check Fee ... (50% of building fee for residential, 65% for commercial).' Same rate applies to tenant improvement as to new commercial construction.
65% of building fee
State Fee (surcharge)Pleasant View City Consolidated Fee Schedule (as of July 1, 2026), page 5.
1% of building fee
Database & Support FeePleasant View City Consolidated Fee Schedule (as of July 1, 2026), page 2.
$40.00
Re-inspection FeePleasant View City Consolidated Fee Schedule (as of July 1, 2026), page 7.
$150.00

Review timeline

Plan reviewTypical estimate — confirm current times with the Pleasant View building department
~7–10 business days

How long did your Commercial Tenant Improvement / Tenant Finish Permit permit actually take in Pleasant View?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    Framing / Fire-Rated Assembly

    Wall construction and any fire-rated/occupancy separation assemblies verified before close-in; scheduled via City Inspect (pleasantview.cityinspect.com) or Sunrise Engineering (1-800-560-6151).

  2. 2

    MEP Rough-In

    Electrical, mechanical/gas, and plumbing rough-in verified against submitted plans; flat $75.00 inspection fee per trade per the Consolidated Fee Schedule.

  3. 3

    Final

    Approved building plans must be on-site at time of every inspection, per Pleasant View's official Permits page.

See the full Pleasant View inspection guide — scheduling & re-inspection fees →

Tips

  • Tenant improvement work does not qualify for Pleasant View's $100 flat 'Misc. permits' minimum — that bucket only covers demolition, fence, mechanical-only, plumbing-only, and 2nd/3rd-layer re-roof work.
  • The same 65% commercial Plan Check Fee applies to tenant improvement as to new commercial construction — there is no discounted TI-specific rate.

Frequently asked questions

Pleasant View requires a commercial tenant improvement / tenant finish permit for: Tenant improvement / interior remodel work in an existing commercial building, regulated by the statewide-adopted IBC; Building Permit Application submitted through the City Inspect online portal; Not eligible for the city's flat $100.00-minimum 'Misc. permits' fee category, which per the Consolidated Fee Schedule is limited to demolition, fence, mechanical-only, plumbing-only, and 2nd/3rd-layer re-roof work. If your project isn't listed, confirm with Pleasant View City Planning, Zoning & Building Department at (801) 782-8529 before starting work.

No. The $100.00 'Misc. permits' minimum only covers demolition, fence, mechanical-only, plumbing-only, and 2nd/3rd-layer re-roof work, per the Consolidated Fee Schedule. A commercial tenant improvement is billed on the full valuation-based Table for Permit Fees (Appendix L) with the 65% commercial Plan Check Fee.

Plan review for a commercial tenant improvement / tenant finish permit in Pleasant View typically runs 7–10 business days. This is an estimate, not a published figure — confirm current review times with Pleasant View City Planning, Zoning & Building Department at (801) 782-8529.

You'll need: Building Permit Application (City Inspect). See the required-documents checklist on this page for details on each.

Pleasant View requires 3 inspection(s) for a commercial tenant improvement / tenant finish permit, in order: Framing / Fire-Rated Assembly, MEP Rough-In, Final. Schedule each through Pleasant View City Planning, Zoning & Building Department ((801) 782-8529).

Apply through Pleasant View City Planning, Zoning & Building Department at 520 W Elberta Dr, Pleasant View, UT 84414. Phone: (801) 782-8529. Office hours: Mon–Thu 8:00 AM – 5:00 PM; Fri 8:00 AM – 12:00 PM. Official information: https://www.pleasantviewut.gov/168/Planning-Zoning-Building.

Pleasant View, Utah has adopted: 2024 International Building Code (IBC), including Appendices C and J — current statewide code per Utah Code § 15A-2-103(1)(a), in force since July 1, 2026, under the statewide preemption mandate of § 15A-1-204 (State Construction and Fire Codes Act); Pleasant View's own codified Title 15.04 text still references the 2000 IBC (Ord. 2002-10), but that codification is stale and superseded by the mandatory statewide cycle.; 2021 International Residential Code (IRC) — current statewide code per Utah Code § 15A-2-103(1)(b) (unchanged by the July 1, 2026 code cycle flip); Pleasant View's Consolidated Fee Schedule (as of July 1, 2026) still labels its Table for Permit Fees 'Appendix L, 2015 IRC,' which is stale fee-table boilerplate, not evidence the city enforces an outdated code edition — plan review and inspections apply the current statewide IRC per § 15A-1-204.; 2024 International Plumbing Code (IPC) — current statewide code per Utah Code § 15A-2-103(1)(d); Pleasant View's codified Title 15.16.010 references the 2000 IPC (stale codification), superseded by § 15A-1-204.; 2024 International Mechanical Code (IMC) / International Fuel Gas Code (IFGC) — current statewide code per Utah Code § 15A-2-103(1)(e)/(f); Pleasant View's codified Title 15.12.010 references the 2000 IMC (stale codification), superseded by § 15A-1-204.; 2024 International Energy Conservation Code (IECC) with Utah amendments — current statewide code per Utah Code § 15A-2-103(1)(h) (a single edition applies statewide, no separate residential/commercial split); Pleasant View's codified Title 15.28.010 references the 2000 IECC (stale codification), superseded by § 15A-1-204.; 2023 National Electrical Code (NEC) — current statewide code per Utah Code § 15A-2-103(1)(g) (unchanged by the July 1, 2026 code cycle flip); Pleasant View's codified Title 15.20.010 references the 1999 NEC (stale codification), superseded by § 15A-1-204.. Local amendments apply — see the Pleasant View overview page for the full list.

Sources & verification

Verified against official sources. Last reviewed 2026-07-19.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Pleasant View building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.

This one’s complicated · Get an expediter

Tell us about your project and we’ll connect you with a permit expediter who works in Pleasant View.

PermitBase may receive a referral fee from the expediter. This is a service introduction, not verified permit data or legal advice.