Commercial Tenant Improvement / Tenant Finish Permit — Centerville, Utah · Requirements sheet
Verified 2026-07-19 · Source: https://centerville.municipalcodeonline.com/book?type=fees
PermitBase is an independent reference and is not affiliated with any government agency. Requirements change and vary by project — confirm current details with the building department before you submit.
Commercial Tenant Improvement / Tenant Finish Permit in Centerville, Utah
Required for interior tenant-finish and tenant-improvement work within an existing commercial, industrial, or multi-family building in Centerville. Centerville's Building Permit Application groups 'Large Tenant Finish' projects with 'New' Commercial Build for plan-submittal purposes (both require 2 sets of 24x36 plans), and both are billed under the same Fee Schedule § 4.010 valuation chart and § 4.040 Commercial/Industrial/Multi-Family plan review rate — the fee schedule does not publish a separate, lower tenant-improvement fee table.
Verified 2026-07-19 · Source
When you need this permit
- Interior tenant-finish or tenant-improvement work within an existing commercial, industrial, or multi-family building
- 'Large Tenant Finish' projects require (2) sets of 24x36 plans for review, per the official Building Permit Application (grouped with 'New' Commercial Build in this requirement)
- Estimated permit valuation must be provided at time of application, per CMC § 10.04.120
- Licensed Contractor Declaration required on the application Contractor
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 2 required documents checked.
This checker covers one permit. A full project usually triggers several — our checklist will assemble all of them, free →
Fee schedule
Centerville City Fee Schedule § 4.010, 'Total Building Valuation Chart,' adopted by Res. Show full citationHide
Centerville City Fee Schedule § 4.010, 'Total Building Valuation Chart,' adopted by Res. 2017-18 on 8/15/2017; Centerville's fee schedule does not publish a separate, lower valuation table for tenant-improvement/remodel work versus new construction — the same chart and the same total-project-valuation methodology governs both.Centerville City Fee Schedule § 4.040: 'Commercial, Industrial, Multi-Family Building Plan Review (excluding single-family dwellings, private garages, carports, sheds, and agricultural buildings) —… Show full citationHide
Centerville City Fee Schedule § 4.040: 'Commercial, Industrial, Multi-Family Building Plan Review (excluding single-family dwellings, private garages, carports, sheds, and agricultural buildings) — 65% of Building Permit Fee.' This is the same line item and rate that applies to new commercial construction — the fee schedule does not carve out a discounted plan-review percentage for tenant-improvement projects.Review timeline
Inspection process
- 1
Scheduled Inspections (Building/Electrical/Mechanical/Plumbing)
Provided by Sunrise Engineering under contract to the City; scheduled by calling 1-800-560-6151, with 24-hour advance notice required, per the official Building and Renovating page.
See the full Centerville inspection guide — scheduling & re-inspection fees →
Tips
- Centerville's Building Permit Application explicitly groups 'Large Tenant Finish' with 'New' Commercial Build for the 2-sets-of-24x36-plans submittal requirement — don't assume tenant-finish work gets a lighter submittal standard.
- The fee schedule does not publish a discounted valuation chart or plan-review percentage for tenant-improvement work — it is billed identically to new commercial construction (65% of Building Permit Fee for plan review, same valuation-based base fee).
- The $140 Commercial/Industrial/Multi-Family cardfile plan check may apply if the tenant-finish layout is identical to a previously-approved plan on file — ask the Building and Renovating Division whether your scope qualifies for a lower fee than full plan review.
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-07-19.
Fee schedules
Applications & forms
Department & other records
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Centerville building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
This one’s complicated · Get an expediter
Tell us about your project and we’ll connect you with a permit expediter who works in Centerville.
PermitBase may receive a referral fee from the expediter. This is a service introduction, not verified permit data or legal advice.
Centerville's permit history isn't searchable here yet
This page covers what the permit requires. What we don't have for Centerville yet is the record of permits actually issued — the history you'd search by street address. That is a gap in our coverage, not a statement about any particular property.
Your email, and the place — never an address. We only use it to tell you when Centerville lands. Privacy.
Other permits in Centerville
Commercial Tenant Improvement / Tenant Finish Permit in other cities
Compare commercial tenant improvement / tenant finish permit fees across Utah →
Look up this fee in a different city →