Solar Panel (PV) Permit — Centerville, Utah · Requirements sheet
Verified 2026-07-07 · Source: https://www.centervilleutah.gov/media/gdlhce31/pritable-solar-array-permit-permit-requirements.pdf
PermitBase is an independent reference and is not affiliated with any government agency. Requirements change and vary by project — confirm current details with the building department before you submit.
Solar Panel (PV) Permit in Centerville, Utah
Required for solar panel installations, battery backup for solar systems, and meter-mounted transfer switches for solar systems in Centerville, per the city's official Solar Permit Application and Solar Array Permit Requirements document. This is the only Centerville permit type with a city-published numeric review-timeline commitment.
Verified 2026-07-07 · Source
When you need this permit
- Structural engineer's letter confirming existing trusses support solar panel loads, indicating wind loads of 140 MPH
- Complete set of construction drawings and one-line electrical diagram(s)
- Roof layout and panel locations meeting clearance-to-peak/hips/valleys/pathways requirements per the adopted International Fire Code (IFC)
- Complete manufacturer specifications for micro-inverters, modules/panels, disconnect switches, any new AC panelboards, and the supporting racking system
- Any detached structure on the property receiving panels must be shown
- Plans must be submitted to South Davis Metro Fire Agency (sdmetrofire.gov, Plan Review) for a separate fire plan review, with a $100 fee for the first hour of review, paid before review begins
- After fire approval, email the Centerville City Solar Permit Application plus the fire-approved (stamped and dated) plans/specifications to donna.wilkinson@centervilleutah.gov
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 2 required documents checked.
This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29 →
Fee schedule
Review timeline
Inspection process
See the full Centerville inspection guide — scheduling & re-inspection fees →
Tips
- Solar is the one Centerville permit type with a real published review-timeline figure: 'Reviews will be completed, in most cases, within 3 business days of submittal, pending no revision of the plans are necessary,' per the official Solar Array Permit Requirements document.
- A separate South Davis Metro Fire Agency plan review and $100/hour fee is required BEFORE the City will review the solar application — plan for this as a distinct upstream step, not a parallel one.
- After the City's review, a project clearance letter is emailed to the solar installation company rather than issuing a traditional in-hand permit document.
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-07-07.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Centerville building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Other permits in Centerville
Solar Panel (PV) Permit in other cities
Compare solar panel (pv) permit fees across Utah →
Look up this fee in a different city →
Now live
Build your Centerville project checklist
Describe your project once and get every permit, document, and fee it triggers in Centerville — in one checklist. Sign up and pay once to generate it, or go unlimited with Pro.
Get started →