Electrical Permit in Centerville, Utah
Required for power service upgrades, power to panel work, temporary power pedestals, EV charging stations, or meter-mounted transfer switches (solar/generator) in Centerville, per the city's official Electrical Permit Application. 'EV Charging Station' is its own explicit checkbox on the application (confirmed by direct PDF review 2026-07-19), but Centerville does not bill it as a distinct fee — it is billed at the same standard $70.70 permit fee as the other checkbox categories, unless the installation also requires Power to Panel work ($141.40) or a service upgrade.
Verified 2026-07-07 · Source
When you need this permit
- Power service upgrade (amperage and work order number specified)
- Power to panel — outside service box, inside panel, or both (higher fee for both)
- Temporary power pedestal
- EV charging station
- Meter-mounted transfer switch (solar or generator) — must be inspected prior to meter set
- Licensed Contractor Declaration or Owner-Builder Declaration Owner-builderContractor
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 1 required documents checked.
This checker covers one permit. A full project usually triggers several — our checklist will assemble all of them, free →
Fee schedule
Review timeline
Inspection process
- 1
Meter-Set Inspection (transfer switch installations only)
A meter-mounted transfer switch for solar or generator use must be inspected prior to the meter being set, per the official Electrical Permit Application.
See the full Centerville inspection guide — scheduling & re-inspection fees →
Tips
- Power-to-panel work is billed at $70.70 for outside-service-box-only or inside-panel-only work, but jumps to $141.40 if both the outside service box and inside panel are involved.
- Centerville explicitly names 'EV Charging Station' as a permit-type checkbox on its Electrical Permit Application, so there is no ambiguity about how to file — but it carries the same standard $70.70 fee as other electrical work rather than a separate EV-specific charge.
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-07-07.
Applications & forms
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Centerville building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Centerville's permit history isn't searchable here yet
This page covers what the permit requires. What we don't have for Centerville yet is the record of permits actually issued — the history you'd search by street address. That is a gap in our coverage, not a statement about any particular property.
Your email, and the place — never an address. We only use it to tell you when Centerville lands. Privacy.
Other permits in Centerville
Electrical Permit in other cities
Compare electrical permit fees across Utah →
Look up this fee in a different city →
Related guides
Now live
Build your Centerville project checklist
Describe your project once and get every permit, document, and fee it triggers in Centerville — in one checklist. Free, for any city and any number of projects.
Get started →