Electrical Permit — Coalville, Utah · Requirements sheet
Verified 2026-07-08 · Source: https://www.coalvillecity.gov/media/11
PermitBase is an independent reference and is not affiliated with any government agency. Requirements change and vary by project — confirm current details with the building department before you submit.
Electrical Permit in Coalville, Utah
Required for electrical work in Coalville, including service upgrades. Fee is a $10 issuance charge plus a per-square-foot system fee, per the city's official fee schedule. EV charger/EVSE installation is electrical work and falls under this general Electrical Permit; the Fee Schedule (Resolution 2025-1) does not publish an EV-specific line item — a charger circuit would be billed under the same $10 issuance fee plus per-square-foot/service-upgrade structure as other electrical work.
Verified 2026-07-08 · Source
When you need this permit
- New electrical circuits, wiring installations, or service upgrades regulated by the statewide-adopted NEC
- Electrical panel or service entrance changes
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 1 required documents checked.
This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29 →
Fee schedule
Review timeline
Inspection process
- 1
Rough Electrical
Rough-in wiring inspection prior to closing walls/ceilings. Minimum 24-hour notice required; schedule at (435) 336-5981.
- 2
Final Electrical
Final electrical inspection, coordinated with the overall Final Building Inspection.
See the full Coalville inspection guide — scheduling & re-inspection fees →
Tips
- The Fee Schedule's residential electrical system-fee line item text ('$0.035 per square foot plus $10') appears to double-count the $10 issuance fee already listed separately in item 6(a) — confirm the total charge with the Building Official (435-640-1799) before budgeting for a standalone electrical permit.
- Coalville has no distinct EV charger/EVSE permit or fee — a home charging circuit is billed under the standard electrical permit fee structure.
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-07-08.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Coalville building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Other permits in Coalville
Electrical Permit in other cities
Compare electrical permit fees across Utah →
Look up this fee in a different city →