Fire Sprinkler & Fire Alarm System Permit — Coalville, Utah · Requirements sheet
Verified 2026-07-21 · Source: https://www.northsummitfireut.gov/district-fee-schedule
PermitBase is an independent reference and is not affiliated with any government agency. Requirements change and vary by project — confirm current details with the building department before you submit.
Fire Sprinkler & Fire Alarm System Permit in Coalville, Utah
Coalville City itself does not operate a fire marshal's office and its own Fee Schedule (Resolution 2025-1, full text reviewed) contains no fire sprinkler or fire alarm line item. Instead, per Coalville's own Building Permit Application Review Procedures and Building Permit Application (which lists a North Summit Fire District sign-off block), fire sprinkler (NFPA 13/13R/13D) and fire alarm (NFPA 72) system plan review and permitting is handled entirely by the North Summit Fire District (NSFD) -- the independent joint fire authority covering Coalville, per NSFD's own Building Regulations page: 'Summit County requires a district representative's signature on building and lot permits.' NSFD prices and reviews this work under its own Fee Schedule (Resolution 2026-02, adopted 3/13/2026, effective 3/14/2026), separate from and in addition to Coalville's own building permit fees.
Verified 2026-07-21 · Source
When you need this permit
- New installation, alteration, or extension of a fire sprinkler system or fire alarm system at a Coalville property
- Plan review and permitting for the fire protection system is performed by North Summit Fire District (NSFD), not Coalville City's Building Department -- NSFD sign-off is required before Coalville issues the underlying building permit, per the Building Permit Application's Fire District approval block
- Residential sprinkler systems: NSFD's Residential Sprinkler System Review Form requires 'Information/plans shall be uploaded by a professional sprinkler engineer with a NICET 3 level stamp of approval,' and 'A Utah licensed sprinkler contractor shall include the original drawings or readable copy'
- Commercial sprinkler/alarm work: NSFD's Commercial Building Permit Plan Review Application requires a site plan showing the nearest fire hydrant location (measured by fire-access-road travel distance, not straight-line) and fire access road dimensions, and asks 'Are Fire Sprinklers being installed' as a required field
- Review does not begin until NSFD's fees are paid: 'After all fee's are paid by the applicant is when the review process begins,' per the Residential Sprinkler System Review Form page
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 3 required documents checked.
This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29 →
Fee schedule
Review timeline
Inspection process
- 1
Fire District Plan Review
Performed by North Summit Fire District (not Coalville City's Building Department) after the online application, fee payment, and required plans/stamps are submitted.
- 2
Sprinkler/Alarm Field Inspection
Scheduled directly with North Summit Fire District, separate from Coalville's own Building Official inspections. NSFD's fee schedule lists distinct 'Sprinkler Inspection' and 'Alarm Inspection' line items at $165.00 each, plus a Re-inspection fee (same as the initial inspection fee) if a scheduled inspection is not passed.
See the full Coalville inspection guide — scheduling & re-inspection fees →
Tips
- Fire sprinkler and fire alarm permitting for a Coalville property is NOT handled by Coalville City's Building Department -- it is a separate process run entirely by North Summit Fire District, with its own online application, plan review, fees, and inspections, that must be completed (with an Approval Letter) before Coalville issues its own building permit.
- Per NSFD's own Building Regulations page: 'In July of 2010, Utah HB 0308 took effect. It gives fire districts the authority to require a residential sprinkler system under specific conditions... The district can not require sprinklers in areas outside of the designated Urban Wildland Interface.'
- Coalville City's own Fee Schedule (Resolution 2025-1), reviewed in full for this entry, contains no fire sprinkler or fire alarm fee line item of any kind -- confirming this is entirely a North Summit Fire District process and fee structure, not a Coalville City one.
- Contact North Summit Fire District at (435) 336-2221 (general) or the NS Fire Marshal directly at (435) 350-3474 for process questions.
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-07-21.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Coalville building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Other permits in Coalville
Fire Sprinkler & Fire Alarm System Permit in other cities
Compare fire sprinkler & fire alarm system permit fees across Utah →
Look up this fee in a different city →
Now live
Build your Coalville project checklist
Describe your project once and get every permit, document, and fee it triggers in Coalville — in one checklist. Sign up and pay once to generate it, or go unlimited with Pro.
Get started →