EV Charger / EVSE Permit in Coalville, Utah

Coalville City does not publish a distinct "EV Charger" or "EVSE" fee line item. Its Fee Schedule (Resolution 2025-1) prices electrical permits by structure type and square footage rather than by equipment: a flat $10 Permit Issuance Fee plus a System Fee of $0.035 per square foot for residential structures (per the IRC), or the same rate for commercial structures (per the National Electric Code). A full-text search of the current fee schedule found no mention of "EV," "EVSE," "electric vehicle," or "charging station." Because the published System Fee is scaled to overall structure square footage rather than scope of electrical work, it is not confirmed how a single added EV-charger circuit would be billed relative to a full-structure electrical permit; the $10 flat Permit Issuance Fee is the only clearly applicable minimum figure.

Reviewed 2026-07-20 · Source

When you need this permit

  • Installation of a Level 2 or DC fast EV charger (EVSE) at a residential or commercial property within Coalville City
  • Dedicated 240V circuit and/or panel capacity installed by a licensed electrician Contractor
  • Electrical permit filed with Coalville City for the added circuit

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 1 required documents checked.

This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29

Fee schedule

Electrical Permit Fee — Permit Issuance Fee (base fee; no distinct EV charger line item)Coalville City Fee Schedule (Resolution 2025-1), 'ELECTRICAL PERMIT FEES' section, item 6a: 'Permit Issuance Fee: $10.'
$10
Electrical Permit Fee — System Fee (residential structures per IRC; scaled to structure square footage, not itemized per circuit/EV charger)Coalville City Fee Schedule (Resolution 2025-1), 'ELECTRICAL PERMIT FEES' section, item 6(b)(iii): 'Residential Structures per the IRC: $0.035 per square foot plus $10.' No EV/EVSE line item or added-circuit-only rate is published; how this square-footage-based fee applies to a standalone charger circuit (versus a whole-structure electrical permit) is not explicitly confirmed.
$0.035 per square foot (does not include the $10 issuance fee)

Review timeline

Plan review
Not published — contact the department

How long did your EV Charger / EVSE Permit permit actually take in Coalville?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    Electrical Inspection

    Inspection of the new circuit/equipment by Coalville City as part of the standard electrical permit process.

See the full Coalville inspection guide — scheduling & re-inspection fees →

Tips

  • Coalville's electrical fee is scaled to structure square footage rather than scope of work and does not name EV chargers — confirm with the Coalville City Building Department (435-336-5981) how a single added charger circuit will be billed before applying.

Frequently asked questions

Coalville requires an ev charger / evse permit for: Installation of a Level 2 or DC fast EV charger (EVSE) at a residential or commercial property within Coalville City; Dedicated 240V circuit and/or panel capacity installed by a licensed electrician; Electrical permit filed with Coalville City for the added circuit. If your project isn't listed, confirm with Coalville City Building Department at (435) 336-5981 before starting work.

No. Coalville City's Fee Schedule (Resolution 2025-1) has no EV/EVSE line item. Electrical permits are billed as a $10 flat issuance fee plus a $0.035-per-square-foot system fee based on structure size, not itemized by equipment type.

Coalville does not publish a plan-review timeline for this permit. Contact Coalville City Building Department at (435) 336-5981 for current turnaround.

You'll need: Electrical Permit Application. See the required-documents checklist on this page for details on each.

Coalville requires 1 inspection(s) for an ev charger / evse permit, in order: Electrical Inspection. Schedule each through Coalville City Building Department ((435) 336-5981).

Apply through Coalville City Building Department at 10 North Main Street, P.O. Box 188, Coalville, UT 84017. Phone: (435) 336-5981, email: cityhall@coalvillecity.org. Office hours: Monday - Thursday 8:00 AM - 5:00 PM. Official information: https://www.coalvillecity.gov/building-department.

Coalville, Utah has adopted: 2024 International Building Code (IBC) — current statewide-adopted edition per Utah Code § 15A-2-103(1)(a) (Utah Uniform Building Standard Act), effective 2026-07-01, superseded the 2021 edition (which was itself effective July 1, 2023). Coalville's Building Permit Fees resolution (Res. 2025-1) references the IBC directly for commercial structures and does not codify a separate local building-code chapter, consistent with the statewide adoption model.; 2021 International Residential Code (IRC) — current statewide-adopted edition per Utah Code § 15A-2-103(1)(b); unaffected by the 7/1/2026 statute revision, continues in force. Coalville's Fee Schedule (Res. 2025-1, Building Permit Fees section) references the IRC directly for residential structures.; 2024 International Plumbing Code (IPC) — current statewide-adopted edition per Utah Code § 15A-2-103(1)(d), effective 2026-07-01, superseded the 2021 edition. Coalville's Fee Schedule references the IPC for commercial plumbing permit fee calculation.; 2024 International Mechanical Code (IMC) — current statewide-adopted edition per Utah Code § 15A-2-103(1)(e), effective 2026-07-01, superseded the 2021 edition. Coalville's Fee Schedule references the IMC for commercial mechanical permit fee calculation.; 2023 National Electrical Code (NEC) — current statewide-adopted edition per Utah Code § 15A-2-103(1)(g); unaffected by the 7/1/2026 statute revision, continues in force. Coalville's Fee Schedule references the NEC for commercial electrical permit fee calculation.; 2024 International Energy Conservation Code (IECC) with Utah amendments — current statewide-adopted edition per Utah Code § 15A-2-103(1)(h), effective 2026-07-01, superseded the 2021 edition.; NOTE: Effective July 1, 2026 (now in force), the 2024 editions of IBC, IPC, IMC, and IECC replaced the 2021 editions statewide per Utah Code § 15A-2-103 (version effective 7/1/2026, superseded 1/1/2027; text independently re-verified live at le.utah.gov 2026-07-16). The 2021 IRC and 2023 NEC were unaffected and remain in force. This file's codesAdopted list does not carry separate line items for the International Fuel Gas Code, International Existing Building Code, or International Swimming Pool and Spa Code (residential provisions) — all three are also statewide-adopted per Utah Code § 15A-2-103(1)(f)/(i)/(n) at the 2024 edition effective 2026-07-01, but no Coalville-specific citation for them was located this session; this is a pre-existing completeness gap in this file, not addressed further here.. Local amendments apply — see the Coalville overview page for the full list.

Sources & verification

Key facts verified against official sources. Last reviewed 2026-07-20.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Coalville building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.