Commercial Building Permit in Coalville, Utah

Required for new commercial construction in Coalville, regulated by the statewide-adopted 2024 IBC (Utah Code § 15A-2-103(1)(a), effective 2026-07-01). Building Valuation is per the IBC occupancy/construction type (ICC Building Valuation Data Sheet) or actual contractor-reported cost, whichever is higher, run through the same valuation-based Building Permit Fee table used for residential structures (Resolution 2025-1). Plan Review is billed at 65% of the Building Permit Fee, the same rate applied to residential structures.

Verified 2026-07-19 · Source

When you need this permit

  • New commercial construction regulated by the statewide-adopted 2024 IBC
  • Planning and Zoning, Public Works, and North Summit Fire District sign-offs obtained prior to building permit issuance
  • Scaled site plan (minimum 1" = 20') showing property lines, easements, rights of way, setbacks, driveway dimensions/paving, water/sewer tie-ins, grading, and structure height — per Coalville's Building Permit Application Review Procedures, which explicitly states 'new residential or commercial construction plans cannot be hand drawn'
  • Three complete sets of legible plans (two physical sets min. 18"x24", one electronic set emailed to cityhall@coalvillecity.org), including a Building Code Analysis cover page listing occupancy, building type, square footage, structure height, and fire suppression/fire-resistance ratings where required, structural plans, elevations, floor plans, footing/foundation drawings, roofing/truss layout, electrical layout, plumbing plan, and mechanical heat-loss (Manual J/D) calculations, stamped and signed by the engineer or architect of record

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 3 required documents checked.

This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29

Fee schedule

Building Permit Fee (valuation-based, Resolution 2025-1, effective 05/27/2025)Coalville City Fee Schedule (Resolution 2025-1, effective 05/27/2025), 'BUILDING PERMIT FEES' section, item 2: 'Building Permit Fees ... b. Non-Agricultural: i. Commercial structures built per the IBC ... Fees in accordance with Coalville City Building Permit Fees' — this is the same valuation-based fee table used for residential structures (item 2's table is not split by structure type). Building Valuation (item 1(b)(i)) for commercial structures is 'per the International Building Code (IBC)' — the higher of actual contractor-reported construction cost, or the ICC Building Valuation Data Sheet (Building Safety Journal, updated biannually) rate for the applicable occupancy/construction type. A 1% Utah State surcharge (UCA § 58-54-9-3, as amended) applies to all permits in addition to these fees.
Less than $2,000: $24 for the first $500 plus $3.50 per additional $100 (or fraction) to $2,000. $2,001–$25,000: $76.50 for the first $2,000 plus $16.50 per additional $1,000 (or fraction) to $25,000. $25,001–$50,000: $456 for the first $25,000 plus $10.10 per additional $1,000. $50,001–$100,000: $756 for the first $50,000 plus $8.50 per additional $1,000. $100,001–$500,000: $1,181 for the first $100,000 plus $6.50 per additional $1,000. $500,001–$1,000,000: $3,781 for the first $500,000 plus $5.50 per additional $1,000. $1,000,001 and up: $6,531 for the first $1,000,000 plus $4.50 per additional $1,000.
Plan Review Fee (commercial)Coalville City Fee Schedule, 'BUILDING PERMIT FEES' section, item 3(b): 'Commercial Structures: 65% of building permit fee.' Identical rate to residential structures (item 3(c)); the reduced 15% rate under item 3(d) applies only to detached garages with no living space, decks/porches for existing structures, and accessory buildings — not general commercial construction.
65% of the Building Permit Fee

Review timeline

Plan review
Not published — contact the department

How long did your Commercial Building Permit permit actually take in Coalville?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    Footing/Foundation

    Required inspection of footing and foundation work prior to backfill, per standard IBC inspection sequencing referenced in Coalville's Building Permit Application Review Procedures. Schedule with the Building Official (Greg White, 435-640-1799) with a minimum 24-hour notice, per the Building Permit Application form.

  2. 2

    Framing

    Framing and rough electrical/plumbing/mechanical inspection prior to insulation and drywall. Minimum 24-hour notice required for scheduling, per the Building Permit Application form.

  3. 3

    Final Building Inspection

    Final inspection by the Building Official, coordinated with Public Works and North Summit Fire District sign-offs (both listed as approval blocks on the Building Permit Application form), required prior to occupancy.

See the full Coalville inspection guide — scheduling & re-inspection fees →

Tips

  • Coalville's Building Permit Application Review Procedures document applies the same plan-submittal checklist to both residential and commercial construction, explicitly stating 'new residential or commercial construction plans cannot be hand drawn' — there is no separate, shorter commercial-only checklist published.
  • Plan review for commercial structures is billed at the same 65% rate as residential structures (Fee Schedule item 3(b)/(c)) — Coalville does not use a lower commercial plan-review rate the way some larger Wasatch Front cities do.
  • Building valuation for commercial structures is the higher of actual contractor-reported construction cost, or the ICC Building Valuation Data Sheet rate for the applicable IBC occupancy/construction type (published biannually in the Building Safety Journal).
  • A 1% Utah State surcharge applies to all building permits per Utah Code § 58-54-9-3, in addition to Coalville's own fee schedule.
  • Coalville is an independent municipal building department (Building Official Greg White, 435-640-1799) — it is not contracted to Summit County's building department.

Frequently asked questions

Coalville requires a commercial building permit for: New commercial construction regulated by the statewide-adopted 2024 IBC; Planning and Zoning, Public Works, and North Summit Fire District sign-offs obtained prior to building permit issuance; Scaled site plan (minimum 1" = 20') showing property lines, easements, rights of way, setbacks, driveway dimensions/paving, water/sewer tie-ins, grading, and structure height — per Coalville's Building Permit Application Review Procedures, which explicitly states 'new residential or commercial construction plans cannot be hand drawn'; Three complete sets of legible plans (two physical sets min. 18"x24", one electronic set emailed to cityhall@coalvillecity.org), including a Building Code Analysis cover page listing occupancy, building type, square footage, structure height, and fire suppression/fire-resistance ratings where required, structural plans, elevations, floor plans, footing/foundation drawings, roofing/truss layout, electrical layout, plumbing plan, and mechanical heat-loss (Manual J/D) calculations, stamped and signed by the engineer or architect of record. If your project isn't listed, confirm with Coalville City Building Department at (435) 336-5981 before starting work.

Per Coalville City's Fee Schedule (Resolution 2025-1, effective 05/27/2025), commercial building permit fees use the same valuation-based table as residential permits: e.g., a project valued $100,001–$500,000 costs $1,181 plus $6.50 per additional $1,000 of valuation. Commercial valuation is the higher of actual contractor-reported cost or the ICC Building Valuation Data Sheet rate for the applicable IBC occupancy/construction type, plus a 65% plan review fee and a 1% Utah state surcharge.

Coalville has not published a commercial-specific plan-review turnaround time. Utah Code § 10-20-909's 14-business-day statutory floor (17 business days including completeness screening) is scoped by statute to one- and two-family dwelling and townhome permits only and does not apply to commercial structures.

You'll need: Coalville City Building Permit Application; Building Permit Application Review Procedures; Engineering Standards and Construction Specifications. See the required-documents checklist on this page for details on each.

Coalville requires 3 inspection(s) for a commercial building permit, in order: Footing/Foundation, Framing, Final Building Inspection. Schedule each through Coalville City Building Department ((435) 336-5981).

Apply through Coalville City Building Department at 10 North Main Street, P.O. Box 188, Coalville, UT 84017. Phone: (435) 336-5981, email: cityhall@coalvillecity.org. Office hours: Monday - Thursday 8:00 AM - 5:00 PM. Official information: https://www.coalvillecity.gov/building-department.

Coalville, Utah has adopted: 2024 International Building Code (IBC) — current statewide-adopted edition per Utah Code § 15A-2-103(1)(a) (Utah Uniform Building Standard Act), effective 2026-07-01, superseded the 2021 edition (which was itself effective July 1, 2023). Coalville's Building Permit Fees resolution (Res. 2025-1) references the IBC directly for commercial structures and does not codify a separate local building-code chapter, consistent with the statewide adoption model.; 2021 International Residential Code (IRC) — current statewide-adopted edition per Utah Code § 15A-2-103(1)(b); unaffected by the 7/1/2026 statute revision, continues in force. Coalville's Fee Schedule (Res. 2025-1, Building Permit Fees section) references the IRC directly for residential structures.; 2024 International Plumbing Code (IPC) — current statewide-adopted edition per Utah Code § 15A-2-103(1)(d), effective 2026-07-01, superseded the 2021 edition. Coalville's Fee Schedule references the IPC for commercial plumbing permit fee calculation.; 2024 International Mechanical Code (IMC) — current statewide-adopted edition per Utah Code § 15A-2-103(1)(e), effective 2026-07-01, superseded the 2021 edition. Coalville's Fee Schedule references the IMC for commercial mechanical permit fee calculation.; 2023 National Electrical Code (NEC) — current statewide-adopted edition per Utah Code § 15A-2-103(1)(g); unaffected by the 7/1/2026 statute revision, continues in force. Coalville's Fee Schedule references the NEC for commercial electrical permit fee calculation.; 2024 International Energy Conservation Code (IECC) with Utah amendments — current statewide-adopted edition per Utah Code § 15A-2-103(1)(h), effective 2026-07-01, superseded the 2021 edition.; NOTE: Effective July 1, 2026 (now in force), the 2024 editions of IBC, IPC, IMC, and IECC replaced the 2021 editions statewide per Utah Code § 15A-2-103 (version effective 7/1/2026, superseded 1/1/2027; text independently re-verified live at le.utah.gov 2026-07-16). The 2021 IRC and 2023 NEC were unaffected and remain in force. This file's codesAdopted list does not carry separate line items for the International Fuel Gas Code, International Existing Building Code, or International Swimming Pool and Spa Code (residential provisions) — all three are also statewide-adopted per Utah Code § 15A-2-103(1)(f)/(i)/(n) at the 2024 edition effective 2026-07-01, but no Coalville-specific citation for them was located this session; this is a pre-existing completeness gap in this file, not addressed further here.. Local amendments apply — see the Coalville overview page for the full list.

This one’s complicated · Get an expediter

Tell us about your project and we’ll connect you with a permit expediter who works in Coalville.

PermitBase may receive a referral fee from the expediter. This is a service introduction, not verified permit data or legal advice.