Coalville building inspections
VerifiedInspection sequence, scheduling, and re-inspection fees for building permits in Coalville, Utah.
Verified 2026-07-08 · Source
How to schedule
Inspections are requested through the building department below.
- Address
- 10 North Main Street, P.O. Box 188, Coalville, UT 84017
- Phone
- (435) 336-5981
- Office hours
- Monday - Thursday 8:00 AM - 5:00 PM
- Website
- Official site
Published scheduling rules
- A minimum 24-hour notice is required on all inspection requests, per the official Building Permit Application form. Schedule inspections by calling (435) 336-5981. (Residential Building Permit)
- Building Official Greg White can be reached directly at (435) 640-1799; the general Building Department line (435-336-5981) is used specifically to schedule inspections. (Residential Building Permit)
- A minimum 24-hour notice is required for all inspection requests, scheduled via the Building Department's main line (435-336-5981). (General)
Inspection sequence
Applies to: Commercial Building Permit
- 1
Footing/Foundation
Required inspection of footing and foundation work prior to backfill, per standard IBC inspection sequencing referenced in Coalville's Building Permit Application Review Procedures. Schedule with the Building Official (Greg White, 435-640-1799) with a minimum 24-hour notice, per the Building Permit Application form.
- 2
Framing
Framing and rough electrical/plumbing/mechanical inspection prior to insulation and drywall. Minimum 24-hour notice required for scheduling, per the Building Permit Application form.
- 3
Final Building Inspection
Final inspection by the Building Official, coordinated with Public Works and North Summit Fire District sign-offs (both listed as approval blocks on the Building Permit Application form), required prior to occupancy.
Applies to: Residential Building Permit
- 1
Footing/Foundation
Required inspection of footing and foundation work prior to backfill, per standard IRC/IBC inspection sequencing referenced in Coalville's Building Permit Application Review Procedures. Schedule with the Building Official (Greg White, 435-640-1799) with a minimum 24-hour notice, per the Building Permit Application form.
- 2
Framing
Framing, sheathing, and rough electrical/plumbing/mechanical inspection prior to insulation and drywall. Minimum 24-hour notice required for scheduling, per the Building Permit Application form.
- 3
Final Building Inspection
Final inspection by the Building Official, coordinated with Public Works and North Summit Fire District sign-offs (both listed as approval blocks on the Building Permit Application form), required prior to occupancy.
Applies to: Commercial Tenant Improvement / Tenant Finish Permit
- 1
Rough-In (Electrical/Plumbing/Mechanical)
Rough-in inspection of any electrical, plumbing, or mechanical work altered as part of the tenant finish, prior to closing walls/ceilings. Minimum 24-hour notice required; schedule at (435) 336-5981.
- 2
Final Building Inspection
Final inspection by the Building Official, coordinated with Public Works and North Summit Fire District sign-offs, required prior to occupancy of the improved tenant space.
Applies to: Electrical Permit
- 1
Rough Electrical
Rough-in wiring inspection prior to closing walls/ceilings. Minimum 24-hour notice required; schedule at (435) 336-5981.
- 2
Final Electrical
Final electrical inspection, coordinated with the overall Final Building Inspection.
Applies to: Fire Sprinkler & Fire Alarm System Permit
- 1
Fire District Plan Review
Performed by North Summit Fire District (not Coalville City's Building Department) after the online application, fee payment, and required plans/stamps are submitted.
- 2
Sprinkler/Alarm Field Inspection
Scheduled directly with North Summit Fire District, separate from Coalville's own Building Official inspections. NSFD's fee schedule lists distinct 'Sprinkler Inspection' and 'Alarm Inspection' line items at $165.00 each, plus a Re-inspection fee (same as the initial inspection fee) if a scheduled inspection is not passed.
Applies to: Mechanical / HVAC Permit
- 1
Rough Mechanical
Rough-in ductwork and equipment inspection prior to closing walls/ceilings. Minimum 24-hour notice required; schedule at (435) 336-5981.
- 2
Final Mechanical
Final mechanical inspection, coordinated with the overall Final Building Inspection.
Applies to: Plumbing Permit
- 1
Rough Plumbing
Rough-in plumbing inspection prior to closing walls/floors. Minimum 24-hour notice required; schedule at (435) 336-5981.
- 2
Final Plumbing
Final plumbing inspection, coordinated with the overall Final Building Inspection.
Final inspection only: Demolition Permit, EV Charger / EVSE Permit, Solar / Alternative Energy Permit
Sources & verification
Verified against official sources. Last reviewed 2026-07-08.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Coalville building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Coalville building permits
Get alerts for Coalville
We'll email you when Coalville's fees, documents, or codes change — not often.
We only use your email to send permit updates. No spam, unsubscribe anytime. Privacy.