Coalville building inspections

Verified

Inspection sequence, scheduling, and re-inspection fees for building permits in Coalville, Utah.

Verified 2026-07-08 · Source

How to schedule

Inspections are requested through the building department below.

Address
10 North Main Street, P.O. Box 188, Coalville, UT 84017
Phone
(435) 336-5981
Office hours
Monday - Thursday 8:00 AM - 5:00 PM

Published scheduling rules

  • A minimum 24-hour notice is required on all inspection requests, per the official Building Permit Application form. Schedule inspections by calling (435) 336-5981. (Residential Building Permit)
  • Building Official Greg White can be reached directly at (435) 640-1799; the general Building Department line (435-336-5981) is used specifically to schedule inspections. (Residential Building Permit)
  • A minimum 24-hour notice is required for all inspection requests, scheduled via the Building Department's main line (435-336-5981). (General)

Inspection sequence

Applies to: Commercial Building Permit

  1. 1

    Footing/Foundation

    Required inspection of footing and foundation work prior to backfill, per standard IBC inspection sequencing referenced in Coalville's Building Permit Application Review Procedures. Schedule with the Building Official (Greg White, 435-640-1799) with a minimum 24-hour notice, per the Building Permit Application form.

  2. 2

    Framing

    Framing and rough electrical/plumbing/mechanical inspection prior to insulation and drywall. Minimum 24-hour notice required for scheduling, per the Building Permit Application form.

  3. 3

    Final Building Inspection

    Final inspection by the Building Official, coordinated with Public Works and North Summit Fire District sign-offs (both listed as approval blocks on the Building Permit Application form), required prior to occupancy.

Applies to: Residential Building Permit

  1. 1

    Footing/Foundation

    Required inspection of footing and foundation work prior to backfill, per standard IRC/IBC inspection sequencing referenced in Coalville's Building Permit Application Review Procedures. Schedule with the Building Official (Greg White, 435-640-1799) with a minimum 24-hour notice, per the Building Permit Application form.

  2. 2

    Framing

    Framing, sheathing, and rough electrical/plumbing/mechanical inspection prior to insulation and drywall. Minimum 24-hour notice required for scheduling, per the Building Permit Application form.

  3. 3

    Final Building Inspection

    Final inspection by the Building Official, coordinated with Public Works and North Summit Fire District sign-offs (both listed as approval blocks on the Building Permit Application form), required prior to occupancy.

Applies to: Commercial Tenant Improvement / Tenant Finish Permit

  1. 1

    Rough-In (Electrical/Plumbing/Mechanical)

    Rough-in inspection of any electrical, plumbing, or mechanical work altered as part of the tenant finish, prior to closing walls/ceilings. Minimum 24-hour notice required; schedule at (435) 336-5981.

  2. 2

    Final Building Inspection

    Final inspection by the Building Official, coordinated with Public Works and North Summit Fire District sign-offs, required prior to occupancy of the improved tenant space.

Applies to: Electrical Permit

  1. 1

    Rough Electrical

    Rough-in wiring inspection prior to closing walls/ceilings. Minimum 24-hour notice required; schedule at (435) 336-5981.

  2. 2

    Final Electrical

    Final electrical inspection, coordinated with the overall Final Building Inspection.

Applies to: Fire Sprinkler & Fire Alarm System Permit

  1. 1

    Fire District Plan Review

    Performed by North Summit Fire District (not Coalville City's Building Department) after the online application, fee payment, and required plans/stamps are submitted.

  2. 2

    Sprinkler/Alarm Field Inspection

    Scheduled directly with North Summit Fire District, separate from Coalville's own Building Official inspections. NSFD's fee schedule lists distinct 'Sprinkler Inspection' and 'Alarm Inspection' line items at $165.00 each, plus a Re-inspection fee (same as the initial inspection fee) if a scheduled inspection is not passed.

Applies to: Mechanical / HVAC Permit

  1. 1

    Rough Mechanical

    Rough-in ductwork and equipment inspection prior to closing walls/ceilings. Minimum 24-hour notice required; schedule at (435) 336-5981.

  2. 2

    Final Mechanical

    Final mechanical inspection, coordinated with the overall Final Building Inspection.

Applies to: Plumbing Permit

  1. 1

    Rough Plumbing

    Rough-in plumbing inspection prior to closing walls/floors. Minimum 24-hour notice required; schedule at (435) 336-5981.

  2. 2

    Final Plumbing

    Final plumbing inspection, coordinated with the overall Final Building Inspection.

Sources & verification

Verified against official sources. Last reviewed 2026-07-08.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Coalville building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.

Coalville building permits