Automatic Fire Extinguishing (Sprinkler) and Alarm System Permit in Clinton, Utah

Required in Clinton City for installation of automatic fire sprinkler (extinguishing) systems and fire alarm systems. Per the Clinton City Consolidated Fee Schedule (FY 2026-27, effective 7/1/2026), all Automatic Extinguishing and Alarm Systems are third-party reviewed and must be reviewed by a Utah-licensed Fire Protection Engineer or a State-recognized equivalent; occupancies classified Educational 'E' or Institutional 'I' must instead be reviewed by the Utah State Fire Marshal's Office. Fees are tiered by square footage and by whether the submittal is a new installation, an existing-system remodel, or a re-review of corrected/rejected plans, with separate (lower) tiers for single-family, two-family, and manufactured homes.

Verified 2026-07-20 · Source

When you need this permit

  • All Automatic Extinguishing (sprinkler) and Alarm Systems must be reviewed by a Utah-licensed Fire Protection Engineer or a State-recognized equivalent, per the Clinton City Consolidated Fee Schedule, FY 2026-27
  • Educational (E) or Institutional (I) occupancies must be reviewed by the Utah State Fire Marshal's Office instead of a third-party reviewer
  • Compliance with Clinton City Code of Ordinances Title 10, Chapter 8 (Fire Code) and the adopted International Fire Code
  • Fees for this Title are set by the Clinton City Council by resolution and published in the Consolidated Fee Schedule, per Clinton City Code § 10-5-4

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 1 required documents checked.

This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29

Fee schedule

New Installation — All buildings except single-family, two-family, and manufactured homes (0-3,000 sq ft)Clinton City Consolidated Fee Schedule, FY 2026-27 (effective 7/1/2026), 'Automatic Fire Extinguishing System Fee and Plan Review Fee' (est. 2017), 'Original/initial submittal for new installations': '0 – 3,000 square feet — $300.00 per plan.'
$300.00 per plan
New Installation — All buildings except single-family, two-family, and manufactured homes (3,001-10,000 sq ft)Clinton City Consolidated Fee Schedule, FY 2026-27: '3,001 – 10,000 square feet — $400.00 per plan.'
$400.00 per plan
New Installation — All buildings except single-family, two-family, and manufactured homes (10,001+ sq ft)Clinton City Consolidated Fee Schedule, FY 2026-27: '10,001 square feet and greater — $400.00 + $0.07 per square foot over 10,000.'
$400.00 + $0.07 per square foot over 10,000
New Installation — Single-family, two-family, and manufactured homes (0-3,000 sq ft)Clinton City Consolidated Fee Schedule, FY 2026-27, 'Single family, two family and manufactured homes' new-installation tier: '0 – 3,000 square feet — $200.00 per plan.'
$200.00 per plan
New Installation — Single-family, two-family, and manufactured homes (3,001-7,000 sq ft)Clinton City Consolidated Fee Schedule, FY 2026-27: '3,001 – 7,000 square feet — $250.00 per plan.'
$250.00 per plan
New Installation — Single-family, two-family, and manufactured homes (7,001+ sq ft)Clinton City Consolidated Fee Schedule, FY 2026-27: '7,001 square feet and greater — $250.00 + $0.07 per square foot over 7,000.'
$250.00 + $0.07 per square foot over 7,000
Existing System Remodel — All buildings except single-family, two-family, and manufactured homes (0-3,000 sq ft)Clinton City Consolidated Fee Schedule, FY 2026-27, 'Original/initial submittal for existing system remodels': '0 – 3,000 square feet — $150.00 per plan' (scaling to $200.00 per plan for 3,001–10,000 sq ft, and $200.00 + $0.07/sq ft over 10,000 sq ft beyond that).
$150.00 per plan
Existing System Remodel — Single-family, two-family, and manufactured homes (0-3,000 sq ft)Clinton City Consolidated Fee Schedule, FY 2026-27: '0 – 3,000 square feet — $125.00 per plan' (scaling to $175.00 per plan for 3,001–7,000 sq ft, and $175.00 + $0.07/sq ft over 7,000 sq ft beyond that).
$125.00 per plan
Re-review of Corrected or Rejected Plans — All buildings except single-family, two-family, and manufactured homes (0-3,000 sq ft)Clinton City Consolidated Fee Schedule, FY 2026-27, 'Re-review of corrected or rejected plans' (est. 2010): '0 – 3,000 square feet — $150.00 per plan' (scaling to $200.00 per plan for 3,001–10,000 sq ft, and $200.00 + $0.07/sq ft over 10,000 sq ft beyond that).
$150.00 per plan
Re-review of Corrected or Rejected Plans — Single-family, two-family, and manufactured homes (0-3,000 sq ft)Clinton City Consolidated Fee Schedule, FY 2026-27: '0 – 3,000 square feet — $125.00 per plan' (scaling to $175.00 per plan for 3,001–7,000 sq ft, and $175.00 + $0.07/sq ft over 7,000 sq ft beyond that).
$125.00 per plan
Automatic Fire Sprinklers/Alarm System/Fire/Smoke/Heat/CO Detection System Plan Review — Original/Initial ReviewClinton City Consolidated Fee Schedule, FY 2026-27, 'Uniform Cost Recovery / Standby Services' section (est. 2008): 'Automatic Fire Sprinklers/Alarm System/Fire/Smoke/Heat/CO Detection System Plan Review: Original/initial review fee — $350.00 per plan.' This is a second, separately dated (2008) fee line item published alongside the 2017 'Automatic Fire Extinguishing System Fee and Plan Review Fee' schedule above; both appear in the same current fee schedule and are reported here exactly as published rather than reconciled.
$350.00 per plan
Automatic Fire Sprinklers/Alarm System/Fire/Smoke/Heat/CO Detection System Plan Review — Re-reviewClinton City Consolidated Fee Schedule, FY 2026-27, 'Uniform Cost Recovery / Standby Services' section: 'Re-review of corrected/rejected plans — $225.00 per plan.'
$225.00 per plan

Review timeline

Plan review
Not published — contact the department

How long did your Automatic Fire Extinguishing (Sprinkler) and Alarm System Permit permit actually take in Clinton?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    Fire System Inspection

    Inspection of the installed automatic extinguishing/alarm system; a Private Fire Hydrant Inspection fee ($150.00, est. 2013) applies separately where a private fire hydrant is involved, per the Consolidated Fee Schedule.

See the full Clinton inspection guide — scheduling & re-inspection fees →

Tips

  • Clinton's fee schedule publishes two different dollar figures for sprinkler/alarm plan review — a detailed square-footage-tiered 'Automatic Fire Extinguishing System Fee and Plan Review Fee' (est. 2017, e.g. $300/$400 for non-residential new installations) and a flat 'Automatic Fire Sprinklers/Alarm System ... Plan Review' fee (est. 2008, $350 original review / $225 re-review) under the Uniform Cost Recovery section — confirm with the Building/Fire Division at (801) 614-0740 which fee actually applies to your project before budgeting, since the source document does not reconcile the two.
  • Educational (E) and Institutional (I) occupancies must have their automatic extinguishing/alarm system plans reviewed by the Utah State Fire Marshal's Office rather than a third-party Fire Protection Engineer.
  • Both new-installation and remodel/re-review fee tiers give a substantial discount to single-family, two-family, and manufactured homes compared to all other building types.

Frequently asked questions

Clinton requires an automatic fire extinguishing (sprinkler) and alarm system permit for: All Automatic Extinguishing (sprinkler) and Alarm Systems must be reviewed by a Utah-licensed Fire Protection Engineer or a State-recognized equivalent, per the Clinton City Consolidated Fee Schedule, FY 2026-27; Educational (E) or Institutional (I) occupancies must be reviewed by the Utah State Fire Marshal's Office instead of a third-party reviewer; Compliance with Clinton City Code of Ordinances Title 10, Chapter 8 (Fire Code) and the adopted International Fire Code; Fees for this Title are set by the Clinton City Council by resolution and published in the Consolidated Fee Schedule, per Clinton City Code § 10-5-4. If your project isn't listed, confirm with Clinton City Community Development Department — Building Division at (801) 614-0740 before starting work.

Per Clinton City's Consolidated Fee Schedule (FY 2026-27, effective 7/1/2026), a new automatic fire extinguishing (sprinkler) system installation in a non-residential building up to 3,000 sq ft costs $300.00 per plan for third-party plan review (rising to $400.00 for 3,001-10,000 sq ft, and $400.00 plus $0.07/sq ft above 10,000 sq ft). Single-family, two-family, and manufactured homes pay a lower tier starting at $200.00 per plan.

Clinton does not publish a plan-review timeline for this permit. Contact Clinton City Community Development Department — Building Division at (801) 614-0740 for current turnaround.

You'll need: Fire Sprinkler/Alarm System Plans. See the required-documents checklist on this page for details on each.

Clinton requires 1 inspection(s) for an automatic fire extinguishing (sprinkler) and alarm system permit, in order: Fire System Inspection. Schedule each through Clinton City Community Development Department — Building Division ((801) 614-0740).

Apply through Clinton City Community Development Department — Building Division at 2267 North 1500 West, Clinton, UT 84015. Phone: (801) 614-0740. Office hours: Monday–Friday, 8:00 AM – 5:00 PM. Official information: https://www.clintoncity.net/2164/Building-Division.

Clinton, Utah has adopted: 2024 International Building Code (Appendices C & J) — governing edition per Utah Code § 15A-2-103(1)(a), effective 2026-07-01, superseded the 2021 edition; NOTE (2026-07-16): Clinton City's own Design Criteria document (rev. 07/03/2023) still lists 2021 and has not been confirmed updated to reflect this statewide transition — the statute governs regardless of the city document's lag; 2021 International Residential Code (Appendix AQ) — Clinton City Design Criteria, rev. 07/03/2023; one- and two-family dwellings and townhomes; unaffected by the 7/1/2026 statute revision (Utah Code § 15A-2-103(1)(b)/(c)) — Clinton's Design Criteria is current on this point; 2015 IRC Chapter 11, Energy Efficiency (residential) — Clinton City Design Criteria, rev. 07/03/2023; 2024 International Plumbing Code (IPC) — governing edition per Utah Code § 15A-2-103(1)(d), effective 2026-07-01, superseded the 2021 edition; NOTE (2026-07-16): Clinton City's own Design Criteria document (rev. 07/03/2023) still lists 2021 and has not been confirmed updated; 2024 International Mechanical Code (IMC) — governing edition per Utah Code § 15A-2-103(1)(e), effective 2026-07-01, superseded the 2021 edition; NOTE (2026-07-16): Clinton City's own Design Criteria document (rev. 07/03/2023) still lists 2021 and has not been confirmed updated; 2024 International Fuel Gas Code (IFGC) — governing edition per Utah Code § 15A-2-103(1)(f), effective 2026-07-01, superseded the 2021 edition; NOTE (2026-07-16): Clinton City's own Design Criteria document (rev. 07/03/2023) still lists 2021 and has not been confirmed updated; 2021 International Fire Code (IFC) — Clinton City Design Criteria, rev. 07/03/2023; 2020 National Electrical Code (NEC) — Clinton City Design Criteria, rev. 07/03/2023; this is one edition behind the 2023 NEC baseline confirmed in other Davis County cities (e.g., Kaysville) under Utah Code § 15A-2-103(1)(g) — Clinton's own published Design Criteria document is the only NEC-edition source found for this city and had not been superseded by a newer published revision as of verification; the 2023 NEC baseline itself was unaffected by the 7/1/2026 statute revision, so this gap predates and is unrelated to that transition; 2015 International Energy Conservation Code (residential provisions) — Clinton City Design Criteria, rev. 07/03/2023; 2024 International Energy Conservation Code (commercial provisions) — governing edition per Utah Code § 15A-2-103(1)(h), effective 2026-07-01, superseded the 2021 edition; NOTE (2026-07-16): Clinton City's own Design Criteria document (rev. 07/03/2023) still lists 2021 and has not been confirmed updated; 2024 International Existing Building Code (IEBC) — governing edition per Utah Code § 15A-2-103(1)(i), effective 2026-07-01, superseded the 2021 edition; NOTE (2026-07-16): Clinton City's own Design Criteria document (rev. 07/03/2023) still lists 2021 and has not been confirmed updated; Accessibility Code — 2021 IBC (ICC/ANSI A117.1-2017) — Clinton City Design Criteria, rev. 07/03/2023; 1997 ICBO Uniform Administrative Code (UAC), Chapter 3 and Table 1-A (as modified) — governs the Building Permit Fee valuation-fee-schedule methodology per Clinton City Consolidated Fee Schedule, FY 2026-27; 1997 Uniform Code for the Abatement of Dangerous Buildings — adopted by Clinton City Code § 5-3-2(2), with local exceptions (references to 'health officer' mean the Davis County Environmental Health and Laboratory Division; recovered funds return to the general fund rather than a repair/demolition fund); GOVERNANCE NOTE: Clinton City Code § 5-3-2(1) adopts 'the current editions of the technical/model codes as adopted by the State of Utah and as published by the International Code Council' as its baseline — i.e., Clinton does not independently select code editions the way some sibling cities' own Design Criteria documents do; it defers to the statewide code suite under Utah Code Title 15A. Because Clinton's own code text defers to the state, and the statute (Utah Code § 15A-2-103) is the ultimate authority here, the 2024 editions of IBC/IPC/IMC/IFGC/IECC(commercial)/IEBC that took effect 2026-07-01 govern in Clinton even though the city's own Design Criteria PDF (rev. 07/03/2023) has not been confirmed updated to show them. Clinton's Design Criteria remains the authoritative source for items the statute revision did not change (IRC, 2015 IRC Ch.11, NEC, IFC, accessibility code) and for local specifics not covered by the statute.; NOTE: Effective July 1, 2026 (now in force) — 2024 editions of IBC, IPC, IMC, IFGC, and IECC (commercial) replaced the 2021 editions statewide per Utah Code § 15A-2-103 (version effective 7/1/2026, superseded 1/1/2027; text independently re-verified live at le.utah.gov 2026-07-16). Clinton's Design Criteria document (last revised 07/03/2023) had not been confirmed updated to reflect this transition as of 2026-07-16 — confirm current adopted edition with the Building Division at (801) 614-0740. The 2021 IRC and 2020 NEC listed in Clinton's Design Criteria were unaffected by this statute revision (Utah's statewide NEC baseline is 2023; Clinton's Design Criteria was already one edition behind that baseline for an unrelated reason, per the NEC line above).. Local amendments apply — see the Clinton overview page for the full list.

All Automatic Extinguishing and Alarm Systems must be reviewed by a Utah-licensed Fire Protection Engineer or a State-recognized equivalent, except Educational (E) or Institutional (I) occupancies, which must be reviewed by the Utah State Fire Marshal's Office, per Clinton City's Consolidated Fee Schedule.

Sources & verification

Verified against official sources. Last reviewed 2026-07-20.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Clinton building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.