Required to demolish all or part of a structure in Clinton. Clinton City Code Title 5, Chapter 6 imposes detailed utility-disconnection requirements. Residential demolition carries a discrete flat fee plus a bond; commercial and relocation are charged per inspection plus a bond.

Verified 2026-07-03 · Source

When you need this permit

  • Complete or partial demolition of any structure — requires a building permit from the Community Development Department (Clinton City Code § 5-6-1)
  • Utility disconnects (sewer, culinary water, secondary water, land drains, power, telephone/cable) completed per Clinton City Code § 5-6-3 specifications
  • Site restoration and grading after demolition (Clinton City Code § 5-6-4)

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 2 required documents checked.

This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29

Fee schedule

Demolition — ResidentialClinton City Consolidated Fee Schedule, FY 2026-27, Other Inspection Fees, item 7
$117.60 + Bond
Demolition — CommercialClinton City Consolidated Fee Schedule, FY 2026-27, Other Inspection Fees, item 7
Per Inspection + Bond
Relocation Residential or CommercialClinton City Consolidated Fee Schedule, FY 2026-27, Other Inspection Fees, item 7
Per Inspection + Bond

Review timeline

Plan review
Not published — contact the department

How long did your Demolition Permit permit actually take in Clinton?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    Utility Disconnect Verification

    Sewer, water, secondary water, land drain, power, and telephone/cable laterals disconnected per Clinton City Code § 5-6-3

  2. 2

    Final / Site Restoration

    Site cleared of debris, graded for natural drainage, per Clinton City Code § 5-6-4

See the full Clinton inspection guide — scheduling & re-inspection fees →

Tips

  • Clinton City Code § 5-6-3 specifies exact utility-disconnection methods: laterals meeting current city standards are cut back to a point 10 feet inside the property line, plugged, and marked with a 2x4 treated-lumber marker extending to within 1 foot of final grade; laterals not meeting current standards must be removed back to the main.
  • A relocation permit (separate from a demolition permit) is required for any structure being moved into or within Clinton, per Chapter 5 of Title 5 — this includes a relocation bond or cash deposit and a foundation-completion requirement before the structure is moved.

Frequently asked questions

Clinton requires a demolition permit for: Complete or partial demolition of any structure — requires a building permit from the Community Development Department (Clinton City Code § 5-6-1); Utility disconnects (sewer, culinary water, secondary water, land drains, power, telephone/cable) completed per Clinton City Code § 5-6-3 specifications; Site restoration and grading after demolition (Clinton City Code § 5-6-4). If your project isn't listed, confirm with Clinton City Community Development Department — Building Division at (801) 614-0740 before starting work.

Residential demolition is a flat $117.60 plus a bond. Commercial demolition and building relocation are charged per inspection plus a bond. Source: Clinton City Consolidated Fee Schedule, FY 2026-27.

Clinton does not publish a plan-review timeline for this permit. Contact Clinton City Community Development Department — Building Division at (801) 614-0740 for current turnaround.

You'll need: Demolition Application (Building Permit); Utility Disconnect Confirmation. See the required-documents checklist on this page for details on each.

Clinton requires 2 inspection(s) for a demolition permit, in order: Utility Disconnect Verification, Final / Site Restoration. Schedule each through Clinton City Community Development Department — Building Division ((801) 614-0740).

Apply through Clinton City Community Development Department — Building Division at 2267 North 1500 West, Clinton, UT 84015. Phone: (801) 614-0740. Office hours: Monday–Friday, 8:00 AM – 5:00 PM. Official information: https://www.clintoncity.net/2164/Building-Division.

Clinton, Utah has adopted: 2024 International Building Code (Appendices C & J) — governing edition per Utah Code § 15A-2-103(1)(a), effective 2026-07-01, superseded the 2021 edition; NOTE (2026-07-16): Clinton City's own Design Criteria document (rev. 07/03/2023) still lists 2021 and has not been confirmed updated to reflect this statewide transition — the statute governs regardless of the city document's lag; 2021 International Residential Code (Appendix AQ) — Clinton City Design Criteria, rev. 07/03/2023; one- and two-family dwellings and townhomes; unaffected by the 7/1/2026 statute revision (Utah Code § 15A-2-103(1)(b)/(c)) — Clinton's Design Criteria is current on this point; 2015 IRC Chapter 11, Energy Efficiency (residential) — Clinton City Design Criteria, rev. 07/03/2023; 2024 International Plumbing Code (IPC) — governing edition per Utah Code § 15A-2-103(1)(d), effective 2026-07-01, superseded the 2021 edition; NOTE (2026-07-16): Clinton City's own Design Criteria document (rev. 07/03/2023) still lists 2021 and has not been confirmed updated; 2024 International Mechanical Code (IMC) — governing edition per Utah Code § 15A-2-103(1)(e), effective 2026-07-01, superseded the 2021 edition; NOTE (2026-07-16): Clinton City's own Design Criteria document (rev. 07/03/2023) still lists 2021 and has not been confirmed updated; 2024 International Fuel Gas Code (IFGC) — governing edition per Utah Code § 15A-2-103(1)(f), effective 2026-07-01, superseded the 2021 edition; NOTE (2026-07-16): Clinton City's own Design Criteria document (rev. 07/03/2023) still lists 2021 and has not been confirmed updated; 2021 International Fire Code (IFC) — Clinton City Design Criteria, rev. 07/03/2023; 2020 National Electrical Code (NEC) — Clinton City Design Criteria, rev. 07/03/2023; this is one edition behind the 2023 NEC baseline confirmed in other Davis County cities (e.g., Kaysville) under Utah Code § 15A-2-103(1)(g) — Clinton's own published Design Criteria document is the only NEC-edition source found for this city and had not been superseded by a newer published revision as of verification; the 2023 NEC baseline itself was unaffected by the 7/1/2026 statute revision, so this gap predates and is unrelated to that transition; 2015 International Energy Conservation Code (residential provisions) — Clinton City Design Criteria, rev. 07/03/2023; 2024 International Energy Conservation Code (commercial provisions) — governing edition per Utah Code § 15A-2-103(1)(h), effective 2026-07-01, superseded the 2021 edition; NOTE (2026-07-16): Clinton City's own Design Criteria document (rev. 07/03/2023) still lists 2021 and has not been confirmed updated; 2024 International Existing Building Code (IEBC) — governing edition per Utah Code § 15A-2-103(1)(i), effective 2026-07-01, superseded the 2021 edition; NOTE (2026-07-16): Clinton City's own Design Criteria document (rev. 07/03/2023) still lists 2021 and has not been confirmed updated; Accessibility Code — 2021 IBC (ICC/ANSI A117.1-2017) — Clinton City Design Criteria, rev. 07/03/2023; 1997 ICBO Uniform Administrative Code (UAC), Chapter 3 and Table 1-A (as modified) — governs the Building Permit Fee valuation-fee-schedule methodology per Clinton City Consolidated Fee Schedule, FY 2026-27; 1997 Uniform Code for the Abatement of Dangerous Buildings — adopted by Clinton City Code § 5-3-2(2), with local exceptions (references to 'health officer' mean the Davis County Environmental Health and Laboratory Division; recovered funds return to the general fund rather than a repair/demolition fund); GOVERNANCE NOTE: Clinton City Code § 5-3-2(1) adopts 'the current editions of the technical/model codes as adopted by the State of Utah and as published by the International Code Council' as its baseline — i.e., Clinton does not independently select code editions the way some sibling cities' own Design Criteria documents do; it defers to the statewide code suite under Utah Code Title 15A. Because Clinton's own code text defers to the state, and the statute (Utah Code § 15A-2-103) is the ultimate authority here, the 2024 editions of IBC/IPC/IMC/IFGC/IECC(commercial)/IEBC that took effect 2026-07-01 govern in Clinton even though the city's own Design Criteria PDF (rev. 07/03/2023) has not been confirmed updated to show them. Clinton's Design Criteria remains the authoritative source for items the statute revision did not change (IRC, 2015 IRC Ch.11, NEC, IFC, accessibility code) and for local specifics not covered by the statute.; NOTE: Effective July 1, 2026 (now in force) — 2024 editions of IBC, IPC, IMC, IFGC, and IECC (commercial) replaced the 2021 editions statewide per Utah Code § 15A-2-103 (version effective 7/1/2026, superseded 1/1/2027; text independently re-verified live at le.utah.gov 2026-07-16). Clinton's Design Criteria document (last revised 07/03/2023) had not been confirmed updated to reflect this transition as of 2026-07-16 — confirm current adopted edition with the Building Division at (801) 614-0740. The 2021 IRC and 2020 NEC listed in Clinton's Design Criteria were unaffected by this statute revision (Utah's statewide NEC baseline is 2023; Clinton's Design Criteria was already one edition behind that baseline for an unrelated reason, per the NEC line above).. Local amendments apply — see the Clinton overview page for the full list.

Sources & verification

Verified against official sources. Last reviewed 2026-07-03.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Clinton building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.