Demolition Permit — Kaysville, Utah · Requirements sheet
Reviewed 2026-07-23 · Source: https://www.kaysville.gov/DocumentCenter/View/5224/Demo-Checklist
PermitBase is an independent reference and is not affiliated with any government agency. Requirements change and vary by project — confirm current details with the building department before you submit.
Demolition Permit in Kaysville, Utah
Required to demolish all or part of a structure in Kaysville. Includes a Historic Preservation Commission review window, mandatory utility disconnects, and an asbestos removal report requirement. Kaysville publishes a dedicated Demolition Checklist.
Reviewed 2026-07-23 · Source
When you need this permit
- Complete or partial demolition of any structure
- Utility disconnects (natural gas, secondary water, power, water) completed PRIOR to demolition
- Asbestos Removal Report from a State-approved asbestos removal company
- Demolition notification permit from the Utah Division of Air Quality (DAQ)
- Historic Preservation Society approval/documentation window for applicable structures
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 5 required documents checked.
This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29 →
Fee schedule
Review timeline
Inspection process
- 1
Power Meter Disconnect
Kaysville City Power meter disconnect, scheduled after permit is paid
- 2
Water Meter Disconnect
Kaysville City Water meter disconnect, scheduled after permit is paid
- 3
Sewer Cap
Sewer line capped per code
- 4
Final
Site cleared, backfilled if foundation/basement removed, erosion/water-accumulation control in place
- 5
Bond Release
Performance deposit ($200) released after passing Final inspection
See the full Kaysville inspection guide — scheduling & re-inspection fees →
Tips
- Allow 10 business days for standard demolition permit review; for single-family dwellings, the Historic Preservation Society review can take up to 30 days. Power and water meter disconnect work orders can take 3-5 business days. (Demo Checklist, kaysville.gov/DocumentCenter/View/5224/Demo-Checklist)
- ALL utilities (natural gas via Dominion Energy at 801-324-5111, secondary water if applicable, Kaysville City Power, Kaysville City Water) must be shut off/disconnected PRIOR to demolition work beginning.
- An Asbestos Removal Report from a State-approved company is required, along with a demolition notification permit from the Utah Division of Air Quality (801-536-4000).
- If the foundation or basement is not removed, the property owner is responsible for securing the site (fence or other approved method); if removed, backfill is required.
- A performance deposit (amount unconfirmed as of 2026-07-23 — see fees section) is forfeited to the City's General Fund if work is not commenced within 180 days or is suspended/abandoned for 180 days.
Frequently asked questions
Sources & verification
Key facts verified against official sources. Last reviewed 2026-07-23.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Kaysville building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Other permits in Kaysville
Demolition Permit in other cities
Compare demolition permit fees across Utah →
Look up this fee in a different city →
Now live
Build your Kaysville project checklist
Describe your project once and get every permit, document, and fee it triggers in Kaysville — in one checklist. Sign up and pay once to generate it, or go unlimited with Pro.
Get started →