Change of Use / Change of Occupancy in Kaysville, Utah
Kaysville does not publish a distinct 'Change of Use' or 'Change of Occupancy' permit or fee line item. Confirmed by direct review of the Business Licensing page, Business License Fees page, Building Permits page, and the FY2027 Consolidated Fee Schedule (Resolution 26-06-06, adopted 6/18/2026, effective 7/1/2026) — no standalone application or fee exists. Where a change of use involves no construction, a new occupant simply obtains a standard Commercial business license (Zoning Administrator site approval, Fire Department business inspection, Business Licensing Office). Where construction accompanies the change of use, occupancy classification is determined as part of Kaysville's existing Commercial Building Permit or Commercial Tenant Improvement / Tenant Finish Permit process, governed by the 2024 IBC and IEBC (statewide-mandatory per Utah Code § 15A-2-103(1)(a) and (1)(i), effective 7/1/2026).
Verified 2026-07-21 · Source
When you need this permit
- No standalone change-of-use or change-of-occupancy application exists in Kaysville — the applicable process depends on whether construction accompanies the use change
- If no construction is involved: the new occupant/business obtains a standard Commercial business license through Kaysville Business Licensing, subject to Zoning Administrator site approval and a Fire Department business inspection before the license can be issued
- If construction is involved: file under Kaysville's existing Commercial Building Permit or Commercial Tenant Improvement / Tenant Finish Permit process, which determines the Occupancy Group under the 2024 IBC/IEBC
- Governed by the 2024 International Existing Building Code (IEBC), statewide-mandatory per Utah Code § 15A-2-103(1)(i) as of 7/1/2026, which addresses change-of-occupancy classification
Required documents
Check off what you have — your progress is saved on this device.
Fee schedule
Review timeline
Inspection process
- 1
Fire Department Business Inspection (if no construction)
Required before a new commercial business license is issued for a space, per Kaysville's published business-licensing guidance; billed as the $100 Business Inspection fee newly adopted in the FY2027 Consolidated Fee Schedule.
- 2
Building Permit inspections (if construction accompanies the change of use)
See this file's Commercial Building Permit / Commercial Tenant Improvement Permit inspection sequences.
See the full Kaysville inspection guide — scheduling & re-inspection fees →
Tips
- Kaysville does not publish a standalone 'Change of Use' or 'Change of Occupancy' permit or fee — confirmed by direct review of the Business Licensing page, Business License Fees page, Building Permits page, and the FY2027 Consolidated Fee Schedule (Resolution 26-06-06, adopted 6/18/2026, effective 7/1/2026).
- If the new use requires no construction, the new occupant applies for a standard Commercial business license ($120 license fee plus a one-time $15 Set Up Fee) through Business Licensing (801-546-1241) — a Fire Department business inspection ($100) of the space is required before the license can be issued.
- If only the details of an existing license are changing (e.g., ownership or minor modification) rather than a genuinely new occupant/use, the $10 Transfer/Modify Fee applies instead of the full new-license fee.
- If the new use also involves structural, MEP, or life-safety work (e.g., retail converting to a restaurant), it is processed through Kaysville's Commercial Building Permit or Commercial Tenant Improvement / Tenant Finish Permit, whose plan review determines Occupancy Group under the 2024 IBC/IEBC (Utah Code § 15A-2-103(1)(a), (1)(i)).
- Kaysville is served by its own city Fire Department (kaysville.gov/236/Fire), not North Davis Fire District (NDFD) — NDFD's own published service area covers West Point, Clearfield, Sunset, and unincorporated Davis County, not Kaysville. This matches this file's fire-sprinkler-alarm-permit entry, which documents that Kaysville's own Building Department (not any fire agency) handles fire sprinkler/alarm permitting.
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-07-21.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Kaysville building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Other permits in Kaysville
Change of Use / Change of Occupancy in other cities
Compare change of use / change of occupancy fees across Utah →