Change of Use / Certificate of Occupancy Compliance in Bountiful, Utah
Bountiful City has no separately named or separately priced 'Change of Use Permit' product. Instead, Bountiful City Land Use Code § 14-1-106 ('Certificate of Occupancy and Use Compliance') makes it unlawful to occupy any building with a greater intensity of use or different occupancy than specifically provided for in its Certificate of Occupancy, and requires a new Certificate any time occupancy changes to a more intensive use. Separately, § 14-1-106.F ('Illegal Change of Use') makes it a class C misdemeanor to change the use of a structure or property to a use not permitted by current City ordinances without first obtaining required re-zoning, variance, or other use approvals. Where a use change does require such approval, it is priced through Bountiful's existing Planning Fees (Conditional Use Permit, Variance, Zoning Map Amendment, or Determination of Non-Compliance/Non-Conformance) rather than a distinct change-of-use fee.
Verified 2026-07-21 · Source
When you need this permit
- It is unlawful to use or occupy, or to permit the use or occupancy of, any building or premises prior to issuance of a Certificate of Occupancy by the City (§ 14-1-106.A)
- It is unlawful to occupy, or allow to be occupied, any building with a greater intensity of use or different occupancy than specifically provided for in the Certificate of Occupancy (§ 14-1-106.A)
- A new Certificate of Occupancy is required any time the occupancy of a building changes to a more intensive use (§ 14-1-106.B)
- No building permit shall be granted for a change of use in any land, building, or structure if such change would violate any provision of the Land Use Code (§ 14-1-105.B)
- Any person who changes the use of a structure or property to a use not permitted by current City ordinances, without first obtaining required re-zoning, variance, or other use approvals, is guilty of a class C misdemeanor ('Illegal Change of Use,' § 14-1-106.F)
- Where the new use requires a Conditional Use Permit, Variance, or Zoning Map Amendment, that Planning Department approval process (and its fee) applies before the Certificate of Occupancy can be reissued
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 1 required documents checked.
This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29 →
Fee schedule
Review timeline
Inspection process
- 1
Final Inspection (New Certificate of Occupancy)
Required whenever the occupancy of a building changes to a more intensive use; a new Certificate of Occupancy is issued by the Engineering and Building Department only after this inspection (§ 14-1-106.B).
See the full Bountiful inspection guide — scheduling & re-inspection fees →
Tips
- Bountiful has no single, distinctly-named 'Change of Use Permit,' but City Code § 14-1-106 ('Certificate of Occupancy and Use Compliance') requires a new Certificate of Occupancy any time a building's occupancy changes to a more intensive use, and separately makes an unpermitted 'Illegal Change of Use' a class C misdemeanor (§ 14-1-106.F).
- Occupying a building with a greater intensity of use or different occupancy than its existing Certificate of Occupancy authorizes is itself declared a nuisance subject to abatement (§ 14-1-106.D), independent of the misdemeanor penalty.
- If the new use isn't already permitted outright in the property's zone, expect to go through Bountiful's standard Planning Department approval track first — Conditional Use Permit ($950), Variance ($1,150), or Zoning Map Amendment ($2,000) — before a new Certificate of Occupancy can be issued.
- For a formal written opinion on whether a specific existing or proposed use complies with current zoning, Bountiful's Planning Fees table lists a 'Determination of Non-Compliance/Non-Conformance' fee ($450) — the closest analog to a standalone use-verification product.
- Any seller, lessor, or their agent must disclose the property's current official zoning classification on listings/promotional materials (§ 14-1-106.H), and misrepresenting a property's lawful use is itself a separate class C misdemeanor ('False Representation,' § 14-1-106.G).
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-07-21.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Bountiful building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Other permits in Bountiful
Change of Use / Certificate of Occupancy Compliance in other cities
Compare change of use / certificate of occupancy compliance fees across Utah →
Look up this fee in a different city →