Mechanical / HVAC Permit — Bountiful, Utah · Requirements sheet
Verified 2026-07-01 · Source: https://www.bountifulutah.gov/Building
PermitBase is an independent reference and is not affiliated with any government agency. Requirements change and vary by project — confirm current details with the building department before you submit.
Mechanical / HVAC Permit in Bountiful, Utah
Required for heating, ventilation, and air conditioning installations, replacements, and ductwork modifications in Bountiful. Governed by the 2024 IMC (Utah Code § 15A-2-103(1)(e)), effective July 1, 2026 (superseded the 2021 edition). Apply through Cityinspect.
Verified 2026-07-01 · Source
When you need this permit
- Furnace or boiler installation or replacement
- Air conditioning system installation or replacement
- Ductwork installation or major modification
- Evaporative cooler installation
- Fireplace or wood-burning stove installation
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 1 required documents checked.
This checker covers one permit. A full project usually triggers several — our checklist will assemble all of them, free →
Fee schedule
Review timeline
Inspection process
- 1
Rough-In
Ductwork and gas piping installed, before walls closed — verify clearances and support
- 2
Final
Equipment operational, combustion air verified, gas pressure tested, thermostat functional
See the full Bountiful inspection guide — scheduling & re-inspection fees →
Tips
- Like-for-like furnace and AC replacements in Bountiful still require a mechanical permit.
- Bountiful follows the 2024 IMC (Utah Code § 15A-2-103(1)(e)), effective July 1, 2026 (superseded the 2021 edition).
- High-efficiency furnaces require condensate drain lines — plan routing before installation.
- Bountiful does not publish a BTU-tier fee schedule — the $75 Single Inspection Permit covers most residential mechanical replacements.
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-07-01.
Fee schedules
Department & other records
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Bountiful building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Bountiful's permit history isn't searchable here yet
This page covers what the permit requires. What we don't have for Bountiful yet is the record of permits actually issued — the history you'd search by street address. That is a gap in our coverage, not a statement about any particular property.
Your email, and the place — never an address. We only use it to tell you when Bountiful lands. Privacy.
Other permits in Bountiful
Mechanical / HVAC Permit in other cities
Compare mechanical / hvac permit fees across Utah →
Look up this fee in a different city →