Mechanical / HVAC Permit — Clearfield, Utah · Requirements sheet
Verified 2026-07-03 · Source: https://clearfield.city/business-development/
PermitBase is an independent reference and is not affiliated with any government agency. Requirements change and vary by project — confirm current details with the building department before you submit.
Mechanical / HVAC Permit in Clearfield, Utah
Required for heating, ventilation, and air conditioning installations, replacements, and gas fireplace/log installations in Clearfield. Governed by the 2024 IMC and 2024 IFGC, current statewide as of 7/1/2026 per Utah Code § 15A-2-103(1)(e)/(f); Clearfield's Design Criteria and Adopted Codes document (rev. 9/29/2023) still lists the 2021 editions (live-checked 2026-07-16), but the statute controls. Charged under the same building valuation fee table.
Verified 2026-07-03 · Source
When you need this permit
- Heating and air conditioning installations or replacements
- Boiler installation or replacement
- Gas log or gas line installation
- Fireplace installation (wood, pellet, or gas)
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 1 required documents checked.
This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29 →
Fee schedule
Review timeline
Inspection process
- 1
Rough-In
Ductwork and gas piping installed, before walls closed — verify clearances and support
- 2
Final
Equipment operational, combustion air verified, gas pressure tested
See the full Clearfield inspection guide — scheduling & re-inspection fees →
Tips
- Heating and air conditioning installations or replacements are explicitly listed as requiring a permit in Clearfield's 'When Do I Need a Building Permit?' handout, with no like-for-like exemption stated.
- Gas logs, gas lines, and fireplaces (wood, pellet, or gas) all require permits per the same handout.
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-07-03.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Clearfield building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Other permits in Clearfield
Mechanical / HVAC Permit in other cities
Compare mechanical / hvac permit fees across Utah →
Look up this fee in a different city →