Clearfield building inspections

Verified

Inspection sequence, scheduling, and re-inspection fees for building permits in Clearfield, Utah.

Verified 2026-07-03 · Source

How to schedule

Inspections are requested through the building department below.

Address
55 South State Street, Clearfield, UT 84015
Phone
(801) 525-2701
Office hours
Mon–Fri 8:00 AM – 5:00 PM

Inspection sequence

Applies to: Commercial Building Permit

  1. 1

    Foundation / Footing

    Before concrete pour — verify excavation, forms, rebar, and anchor bolts, per 2024 IBC.

  2. 2

    Framing / Structural

    After framing, sheathing, and structural steel/concrete work — before insulation or wall cover.

  3. 3

    MEP Rough-In

    Electrical, plumbing, and mechanical rough-in inspected before walls closed.

  4. 4

    Fire Sprinkler / Fire Alarm

    Fire Department review and approval of the two required complete sets of fire sprinkler plans, per the Commercial Plans Submittal Checklist.

  5. 5

    Final

    All work complete, handicap accessibility features verified per current IBC and ANSI A-117.1, before occupancy.

Applies to: Basement Finish Permit

  1. 1

    Framing

    Wall framing, fire blocking, egress window openings

  2. 2

    MEP Rough-In

    Electrical, plumbing, and HVAC rough-ins before walls closed

  3. 3

    Insulation

    Insulation on exterior walls, vapor barrier placement

  4. 4

    Final

    Drywall, fixtures, smoke/CO detectors, and all finishes complete

Applies to: Commercial Tenant Improvement / Tenant Finish Permit

  1. 1

    Framing / Structural (if applicable)

    Interior wall framing and structural connections verified before close-in, where the scope includes structural work or wall additions/removals.

  2. 2

    MEP Rough-In

    Electrical, plumbing, and mechanical rough-in for the tenant space, inspected before walls closed.

  3. 3

    Fire Sprinkler / Fire Alarm (if applicable)

    Fire Department review and approval where sprinkler/alarm systems are modified as part of the tenant finish.

  4. 4

    Final

    All tenant-finish work complete, accessible route of travel to the improved area verified, before occupancy.

Applies to: Residential Building Permit

  1. 1

    Foundation / Footing

    Before concrete pour — verify excavation, forms, rebar, and anchor bolts

  2. 2

    Framing

    After framing, sheathing, and rough-in MEP — before insulation or wall cover

  3. 3

    Insulation

    After insulation installed, before drywall

  4. 4

    Final

    All work complete — certificate of occupancy issued upon passing

Applies to: Deck Permit

  1. 1

    Footings

    Verify footing depth (minimum 30 inches below grade per Clearfield frost depth), diameter, and rebar before concrete pour

  2. 2

    Framing

    Posts, beams, joists, ledger connection, and hardware

  3. 3

    Final

    Decking, stairs, guards, and railings complete

Applies to: Electrical Permit

  1. 1

    Rough-In

    After wiring installed, before walls closed — verify box placement, wire sizing, proper support

  2. 2

    Service / Panel

    Panel installation, grounding electrode system, service entrance conductors

  3. 3

    Final

    All devices installed, GFCI/AFCI protection verified, panel labeled

Applies to: Fire Sprinkler System Permit

  1. 1

    Flow Test

    One of 3 inspections included in the $300 permit fee.

  2. 2

    Hydrostatic Test

    One of 3 inspections included in the $300 permit fee.

  3. 3

    Final

    Final of the 3 inspections included in the $300 permit fee.

Applies to: Plumbing Permit

  1. 1

    Underground / Slab

    Before concrete pour — verify pipe slope, materials, and cleanouts

  2. 2

    Rough-In

    After pipes installed, before walls closed — pressure test required

  3. 3

    Final

    All fixtures connected, water flowing, no leaks, proper venting verified

Applies to: Solar / Solar PV Installation Permit

  1. 1

    Structural / Roof Attachment

    Verify racking attachment points, flashing, and roof load path before panels are energized (roof-mounted arrays only)

  2. 2

    Electrical

    Inverter, disconnect, grounding, and interconnection point — same standard as other electrical permit inspections

  3. 3

    Final

    System complete and operational; all work verified against approved plans

Applies to: Demolition Permit

  1. 1

    Pre-Demolition

    Verify utility disconnects are complete before work begins

  2. 2

    Final / Site Clear

    Site cleared, foundation removed or capped per plan

Applies to: Fire Alarm System Permit

  1. 1

    First Inspection

    Included in the $200 permit fee; NDFD fire alarm permits include 2 inspections total.

  2. 2

    Final Inspection

    Second of the 2 inspections included in the permit fee.

Applies to: Mechanical / HVAC Permit

  1. 1

    Rough-In

    Ductwork and gas piping installed, before walls closed — verify clearances and support

  2. 2

    Final

    Equipment operational, combustion air verified, gas pressure tested

Applies to: Roofing Permit

  1. 1

    Deck / Substrate

    After tear-off — verify sheathing condition before proceeding

  2. 2

    Final

    Completed roof — verify ice barrier, flashing, drip edge, and nailing pattern

Applies to: Street Cut / Excavation Permit

  1. 1

    Pre-Excavation

    Verify utility locates (call 811) and traffic control plan before cutting

  2. 2

    Final

    Verify patch/repair meets city standards

Re-inspection fees

Residential Building PermitRe-inspection Fee · Clearfield City Consolidated Fee Schedule, Chapter 5 (Ordinance 2025-16, adopted 6-24-2025)
$47 per hour (minimum charge 0.5 hours for inspections with no fee specifically indicated: $25 each)
Electrical PermitRe-inspection Fee · Clearfield City Consolidated Fee Schedule, Chapter 5 (Ordinance 2025-16, adopted 6-24-2025)
$47 per hour (minimum 0.5 hour / $25 for unspecified inspections)
Plumbing PermitRe-inspection Fee · Clearfield City Consolidated Fee Schedule, Chapter 5 (Ordinance 2025-16, adopted 6-24-2025)
$47 per hour (minimum 0.5 hour / $25 for unspecified inspections)
Mechanical / HVAC PermitRe-inspection Fee · Clearfield City Consolidated Fee Schedule, Chapter 5 (Ordinance 2025-16, adopted 6-24-2025)
$47 per hour (minimum 0.5 hour / $25 for unspecified inspections)
Solar / Solar PV Installation PermitRe-inspection Fee · Clearfield City Consolidated Fee Schedule, Chapter 5 (Ordinance 2025-16, adopted 6-24-2025)
$47 per hour (minimum charge 0.5 hours for inspections with no fee specifically indicated: $25 each)

Sources & verification

Verified against official sources. Last reviewed 2026-07-03.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Clearfield building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.

Clearfield building permits

Get alerts for Clearfield

We'll email you when Clearfield's fees, documents, or codes change — not often.

We only use your email to send permit updates. No spam, unsubscribe anytime. Privacy.