Clearfield building inspections
VerifiedInspection sequence, scheduling, and re-inspection fees for building permits in Clearfield, Utah.
Verified 2026-07-03 · Source
How to schedule
Inspections are requested through the building department below.
- Address
- 55 South State Street, Clearfield, UT 84015
- Phone
- (801) 525-2701
- Office hours
- Mon–Fri 8:00 AM – 5:00 PM
- Website
- Official site
Inspection sequence
Applies to: Commercial Building Permit
- 1
Foundation / Footing
Before concrete pour — verify excavation, forms, rebar, and anchor bolts, per 2024 IBC.
- 2
Framing / Structural
After framing, sheathing, and structural steel/concrete work — before insulation or wall cover.
- 3
MEP Rough-In
Electrical, plumbing, and mechanical rough-in inspected before walls closed.
- 4
Fire Sprinkler / Fire Alarm
Fire Department review and approval of the two required complete sets of fire sprinkler plans, per the Commercial Plans Submittal Checklist.
- 5
Final
All work complete, handicap accessibility features verified per current IBC and ANSI A-117.1, before occupancy.
Applies to: Basement Finish Permit
- 1
Framing
Wall framing, fire blocking, egress window openings
- 2
MEP Rough-In
Electrical, plumbing, and HVAC rough-ins before walls closed
- 3
Insulation
Insulation on exterior walls, vapor barrier placement
- 4
Final
Drywall, fixtures, smoke/CO detectors, and all finishes complete
Applies to: Commercial Tenant Improvement / Tenant Finish Permit
- 1
Framing / Structural (if applicable)
Interior wall framing and structural connections verified before close-in, where the scope includes structural work or wall additions/removals.
- 2
MEP Rough-In
Electrical, plumbing, and mechanical rough-in for the tenant space, inspected before walls closed.
- 3
Fire Sprinkler / Fire Alarm (if applicable)
Fire Department review and approval where sprinkler/alarm systems are modified as part of the tenant finish.
- 4
Final
All tenant-finish work complete, accessible route of travel to the improved area verified, before occupancy.
Applies to: Residential Building Permit
- 1
Foundation / Footing
Before concrete pour — verify excavation, forms, rebar, and anchor bolts
- 2
Framing
After framing, sheathing, and rough-in MEP — before insulation or wall cover
- 3
Insulation
After insulation installed, before drywall
- 4
Final
All work complete — certificate of occupancy issued upon passing
Applies to: Deck Permit
- 1
Footings
Verify footing depth (minimum 30 inches below grade per Clearfield frost depth), diameter, and rebar before concrete pour
- 2
Framing
Posts, beams, joists, ledger connection, and hardware
- 3
Final
Decking, stairs, guards, and railings complete
Applies to: Electrical Permit
- 1
Rough-In
After wiring installed, before walls closed — verify box placement, wire sizing, proper support
- 2
Service / Panel
Panel installation, grounding electrode system, service entrance conductors
- 3
Final
All devices installed, GFCI/AFCI protection verified, panel labeled
Applies to: Fire Sprinkler System Permit
- 1
Flow Test
One of 3 inspections included in the $300 permit fee.
- 2
Hydrostatic Test
One of 3 inspections included in the $300 permit fee.
- 3
Final
Final of the 3 inspections included in the $300 permit fee.
Applies to: Plumbing Permit
- 1
Underground / Slab
Before concrete pour — verify pipe slope, materials, and cleanouts
- 2
Rough-In
After pipes installed, before walls closed — pressure test required
- 3
Final
All fixtures connected, water flowing, no leaks, proper venting verified
Applies to: Solar / Solar PV Installation Permit
- 1
Structural / Roof Attachment
Verify racking attachment points, flashing, and roof load path before panels are energized (roof-mounted arrays only)
- 2
Electrical
Inverter, disconnect, grounding, and interconnection point — same standard as other electrical permit inspections
- 3
Final
System complete and operational; all work verified against approved plans
Applies to: Demolition Permit
- 1
Pre-Demolition
Verify utility disconnects are complete before work begins
- 2
Final / Site Clear
Site cleared, foundation removed or capped per plan
Applies to: Fire Alarm System Permit
- 1
First Inspection
Included in the $200 permit fee; NDFD fire alarm permits include 2 inspections total.
- 2
Final Inspection
Second of the 2 inspections included in the permit fee.
Applies to: Mechanical / HVAC Permit
- 1
Rough-In
Ductwork and gas piping installed, before walls closed — verify clearances and support
- 2
Final
Equipment operational, combustion air verified, gas pressure tested
Applies to: Roofing Permit
- 1
Deck / Substrate
After tear-off — verify sheathing condition before proceeding
- 2
Final
Completed roof — verify ice barrier, flashing, drip edge, and nailing pattern
Applies to: Street Cut / Excavation Permit
- 1
Pre-Excavation
Verify utility locates (call 811) and traffic control plan before cutting
- 2
Final
Verify patch/repair meets city standards
Final inspection only: Change of Use / Change of Occupancy, EV Charger / EVSE Permit, Fence Permit, Sign Permit
Re-inspection fees
Sources & verification
Verified against official sources. Last reviewed 2026-07-03.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Clearfield building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Clearfield building permits
Get alerts for Clearfield
We'll email you when Clearfield's fees, documents, or codes change — not often.
We only use your email to send permit updates. No spam, unsubscribe anytime. Privacy.