Bountiful building inspections
VerifiedInspection sequence, scheduling, and re-inspection fees for building permits in Bountiful, Utah.
Verified 2026-06-30 · Source
How to schedule
Inspections are requested through the building department below.
- Address
- 795 South Main Street, Bountiful, UT 84010
- Phone
- (801) 298-6125
- Office hours
- Mon–Thu 7:00 AM – 6:00 PM (permits issued until 5:30 PM); closed Fri–Sun
- Website
- Official site
Inspection sequence
Applies to: Accessory Dwelling Unit (ADU)
- 1
Foundation
Footings, forms, rebar — before concrete pour
- 2
Framing
Structure, fire separation between units, egress windows
- 3
MEP Rough-In
Mechanical, electrical, plumbing rough-ins before walls closed
- 4
Insulation
Insulation and vapor barrier before drywall
- 5
Final
All work complete, smoke/CO detectors, address posted, ready for occupancy
Applies to: Commercial Building Permit
- 1
Foundation / Footing
Before concrete pour — verify excavation, forms, rebar, and anchor bolts, per 2024 IBC.
- 2
Framing / Structural
After framing, sheathing, and structural steel/concrete work — before insulation or wall cover.
- 3
MEP Rough-In
Electrical, plumbing, and mechanical rough-in inspected before walls closed.
- 4
Fire / Life Safety
Fire sprinkler and/or fire alarm rough-in and final, where required by the adopted IBC/IFC — coordinated with South Davis Metro Fire Agency.
- 5
Final
All work complete before certificate of occupancy is issued.
Applies to: Basement Finish Permit
- 1
Framing
Wall framing, fire blocking, egress window openings
- 2
MEP Rough-In
Electrical, plumbing, and HVAC rough-ins before walls closed
- 3
Insulation
Insulation on exterior walls, vapor barrier placement
- 4
Final
Drywall, fixtures, smoke/CO detectors, and all finishes complete
Applies to: Commercial Tenant Improvement / Tenant Finish Permit
- 1
Framing / Structural (if applicable)
Interior wall framing, rebar, and structural connections verified before close-in, where the scope includes structural work.
- 2
MEP Rough-In
Electrical, plumbing, and mechanical rough-in for the tenant space, inspected before walls closed.
- 3
Fire / Life Safety (if applicable)
Fire sprinkler/alarm modifications inspected where required by the adopted IBC/IFC — coordinated with South Davis Metro Fire Agency.
- 4
Final
All tenant-finish work complete before occupancy/certificate of occupancy.
Applies to: Residential Building Permit
- 1
Foundation / Footing
Before concrete pour — verify excavation, forms, rebar, and anchor bolts
- 2
Framing
After framing, sheathing, and rough-in MEP — before insulation or wall cover
- 3
Insulation
After insulation installed, before drywall
- 4
Final
All work complete — certificate of occupancy issued upon passing
Applies to: Deck Permit
- 1
Footings
Verify footing depth (minimum 30 inches below grade per Bountiful frost depth), diameter, and rebar before concrete pour
- 2
Framing
Posts, beams, joists, ledger connection, and hardware
- 3
Final
Decking, stairs, guards, and railings complete
Applies to: Electrical Permit
- 1
Rough-In
After wiring installed, before walls closed — verify box placement, wire sizing, proper support
- 2
Service / Panel
Panel installation, grounding electrode system, service entrance conductors, overhead clearances verified per Change of Service policy
- 3
Final
All devices installed, GFCI/AFCI protection verified, panel labeled
Applies to: Fire Sprinkler System Permit
- 1
Inspection 1 of 3
SDMF Fee Ordinance (04/2024) lists the $300 Fire Sprinkler System Permit as covering '(3 Inspections)' without naming each stage individually; contact SDMF for the specific inspection stages on a given project.
- 2
Inspection 2 of 3
Second of the 3 inspections included in the $300 permit fee, per the SDMF Fee Ordinance.
- 3
Inspection 3 of 3 (Final)
Third of the 3 inspections included in the $300 permit fee. Final inspections will not be scheduled until SDMF's pre-check list is complete.
Applies to: Plumbing Permit
- 1
Underground / Slab
Before concrete pour — verify pipe slope, materials, and cleanouts
- 2
Rough-In
After pipes installed, before walls closed — pressure test required
- 3
Final
All fixtures connected, water flowing, no leaks, proper venting verified
Applies to: Demolition Permit
- 1
Pre-Demolition
Verify utility disconnects are complete and any required asbestos clearance is obtained before work begins
- 2
Final / Site Clear
Site cleared, foundation removed or capped per plan, erosion control in place
Applies to: Fire Alarm System Permit
- 1
First Inspection
Included in the $200 permit fee; SDMF fire alarm permits include 2 inspections total.
- 2
Final Inspection
Second of the 2 inspections included in the permit fee.
Applies to: Mechanical / HVAC Permit
- 1
Rough-In
Ductwork and gas piping installed, before walls closed — verify clearances and support
- 2
Final
Equipment operational, combustion air verified, gas pressure tested, thermostat functional
Applies to: Roofing Permit
- 1
Deck / Substrate
After tear-off — verify sheathing condition; structurally unsound decking must be repaired before new roofing. Bountiful (Seismic Zone D2): spaced lumber sheathing must be covered with 7/16" min plywood/OSB overlay.
- 2
Final
Completed roof — verify ice barrier at valleys/eaves, drip edge, flashing, and nailing per manufacturer instructions
Applies to: Sign Permit
- 1
Initial Inspection After Construction
The Planning Director or Building Official may make an initial inspection upon completion of construction, erection, re-erection, or remodeling of a permitted sign, when an inspection request is made; includes inspection of temporary signs using an electrical connection (§ 14-19-105.E.2.a).
- 2
Re-Inspection (when necessary)
The Planning Director or an authorized representative may re-inspect any sign for which a permit was issued but which did not pass a previous inspection (§ 14-19-105.E.2.b).
Applies to: Solar Panel Permit
- 1
Rough Electrical
Conduit runs, wire sizing, disconnect placement before energizing
- 2
Final / Structural
Panel mounting, racking attachment, roof penetration sealing, and electrical connections verified. Allow minimum five working days for BCLP to complete electrical interconnection after building inspection clearance.
Final inspection only: Change of Use / Certificate of Occupancy Compliance, EV Charger / EVSE Permit, Fence Permit, Water Heater Permit
Sources & verification
Verified against official sources. Last reviewed 2026-06-30.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Bountiful building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Bountiful building permits
Get alerts for Bountiful
We'll email you when Bountiful's fees, documents, or codes change — not often.
We only use your email to send permit updates. No spam, unsubscribe anytime. Privacy.