Bountiful building inspections

Verified

Inspection sequence, scheduling, and re-inspection fees for building permits in Bountiful, Utah.

Verified 2026-06-30 · Source

How to schedule

Inspections are requested through the building department below.

Address
795 South Main Street, Bountiful, UT 84010
Phone
(801) 298-6125
Office hours
Mon–Thu 7:00 AM – 6:00 PM (permits issued until 5:30 PM); closed Fri–Sun

Inspection sequence

Applies to: Accessory Dwelling Unit (ADU)

  1. 1

    Foundation

    Footings, forms, rebar — before concrete pour

  2. 2

    Framing

    Structure, fire separation between units, egress windows

  3. 3

    MEP Rough-In

    Mechanical, electrical, plumbing rough-ins before walls closed

  4. 4

    Insulation

    Insulation and vapor barrier before drywall

  5. 5

    Final

    All work complete, smoke/CO detectors, address posted, ready for occupancy

Applies to: Commercial Building Permit

  1. 1

    Foundation / Footing

    Before concrete pour — verify excavation, forms, rebar, and anchor bolts, per 2024 IBC.

  2. 2

    Framing / Structural

    After framing, sheathing, and structural steel/concrete work — before insulation or wall cover.

  3. 3

    MEP Rough-In

    Electrical, plumbing, and mechanical rough-in inspected before walls closed.

  4. 4

    Fire / Life Safety

    Fire sprinkler and/or fire alarm rough-in and final, where required by the adopted IBC/IFC — coordinated with South Davis Metro Fire Agency.

  5. 5

    Final

    All work complete before certificate of occupancy is issued.

Applies to: Basement Finish Permit

  1. 1

    Framing

    Wall framing, fire blocking, egress window openings

  2. 2

    MEP Rough-In

    Electrical, plumbing, and HVAC rough-ins before walls closed

  3. 3

    Insulation

    Insulation on exterior walls, vapor barrier placement

  4. 4

    Final

    Drywall, fixtures, smoke/CO detectors, and all finishes complete

Applies to: Commercial Tenant Improvement / Tenant Finish Permit

  1. 1

    Framing / Structural (if applicable)

    Interior wall framing, rebar, and structural connections verified before close-in, where the scope includes structural work.

  2. 2

    MEP Rough-In

    Electrical, plumbing, and mechanical rough-in for the tenant space, inspected before walls closed.

  3. 3

    Fire / Life Safety (if applicable)

    Fire sprinkler/alarm modifications inspected where required by the adopted IBC/IFC — coordinated with South Davis Metro Fire Agency.

  4. 4

    Final

    All tenant-finish work complete before occupancy/certificate of occupancy.

Applies to: Residential Building Permit

  1. 1

    Foundation / Footing

    Before concrete pour — verify excavation, forms, rebar, and anchor bolts

  2. 2

    Framing

    After framing, sheathing, and rough-in MEP — before insulation or wall cover

  3. 3

    Insulation

    After insulation installed, before drywall

  4. 4

    Final

    All work complete — certificate of occupancy issued upon passing

Applies to: Deck Permit

  1. 1

    Footings

    Verify footing depth (minimum 30 inches below grade per Bountiful frost depth), diameter, and rebar before concrete pour

  2. 2

    Framing

    Posts, beams, joists, ledger connection, and hardware

  3. 3

    Final

    Decking, stairs, guards, and railings complete

Applies to: Electrical Permit

  1. 1

    Rough-In

    After wiring installed, before walls closed — verify box placement, wire sizing, proper support

  2. 2

    Service / Panel

    Panel installation, grounding electrode system, service entrance conductors, overhead clearances verified per Change of Service policy

  3. 3

    Final

    All devices installed, GFCI/AFCI protection verified, panel labeled

Applies to: Fire Sprinkler System Permit

  1. 1

    Inspection 1 of 3

    SDMF Fee Ordinance (04/2024) lists the $300 Fire Sprinkler System Permit as covering '(3 Inspections)' without naming each stage individually; contact SDMF for the specific inspection stages on a given project.

  2. 2

    Inspection 2 of 3

    Second of the 3 inspections included in the $300 permit fee, per the SDMF Fee Ordinance.

  3. 3

    Inspection 3 of 3 (Final)

    Third of the 3 inspections included in the $300 permit fee. Final inspections will not be scheduled until SDMF's pre-check list is complete.

Applies to: Plumbing Permit

  1. 1

    Underground / Slab

    Before concrete pour — verify pipe slope, materials, and cleanouts

  2. 2

    Rough-In

    After pipes installed, before walls closed — pressure test required

  3. 3

    Final

    All fixtures connected, water flowing, no leaks, proper venting verified

Applies to: Demolition Permit

  1. 1

    Pre-Demolition

    Verify utility disconnects are complete and any required asbestos clearance is obtained before work begins

  2. 2

    Final / Site Clear

    Site cleared, foundation removed or capped per plan, erosion control in place

Applies to: Fire Alarm System Permit

  1. 1

    First Inspection

    Included in the $200 permit fee; SDMF fire alarm permits include 2 inspections total.

  2. 2

    Final Inspection

    Second of the 2 inspections included in the permit fee.

Applies to: Mechanical / HVAC Permit

  1. 1

    Rough-In

    Ductwork and gas piping installed, before walls closed — verify clearances and support

  2. 2

    Final

    Equipment operational, combustion air verified, gas pressure tested, thermostat functional

Applies to: Roofing Permit

  1. 1

    Deck / Substrate

    After tear-off — verify sheathing condition; structurally unsound decking must be repaired before new roofing. Bountiful (Seismic Zone D2): spaced lumber sheathing must be covered with 7/16" min plywood/OSB overlay.

  2. 2

    Final

    Completed roof — verify ice barrier at valleys/eaves, drip edge, flashing, and nailing per manufacturer instructions

Applies to: Sign Permit

  1. 1

    Initial Inspection After Construction

    The Planning Director or Building Official may make an initial inspection upon completion of construction, erection, re-erection, or remodeling of a permitted sign, when an inspection request is made; includes inspection of temporary signs using an electrical connection (§ 14-19-105.E.2.a).

  2. 2

    Re-Inspection (when necessary)

    The Planning Director or an authorized representative may re-inspect any sign for which a permit was issued but which did not pass a previous inspection (§ 14-19-105.E.2.b).

Applies to: Solar Panel Permit

  1. 1

    Rough Electrical

    Conduit runs, wire sizing, disconnect placement before energizing

  2. 2

    Final / Structural

    Panel mounting, racking attachment, roof penetration sealing, and electrical connections verified. Allow minimum five working days for BCLP to complete electrical interconnection after building inspection clearance.

Bountiful building permits

Get alerts for Bountiful

We'll email you when Bountiful's fees, documents, or codes change — not often.

We only use your email to send permit updates. No spam, unsubscribe anytime. Privacy.