EV Charger / EVSE Permit in Clinton, Utah

Clinton City does not publish a distinct "EV Charger" or "EVSE" fee line item. Its Consolidated Fee Schedule (FY 2026-27) bills additions or modifications to existing electrical systems under a single valuation-based Building Permit Fee category ('Additions or Modifications to Existing Structures; Structural, Plumbing, Mechanical, and/or Electrical Systems'), assessed per Section 304 of the 1997 Uniform Administrative Code, Section 109 of the IBC, and Section R108 of the IRC — the same clause covering all trade work, not a specific EV category. A full-text search of the current fee schedule found no mention of "EV," "EVSE," "electric vehicle," or "charging station."

Reviewed 2026-07-20 · Source

When you need this permit

  • Installation of a Level 2 or DC fast EV charger (EVSE) at a residential or commercial property within Clinton City
  • Dedicated 240V circuit and/or panel capacity installed by a licensed electrician Contractor
  • Building permit filed with Clinton City for the electrical modification, valued per Section 304 UAC / Section 109 IBC / Section R108 IRC

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 1 required documents checked.

This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29

Fee schedule

Building Permit Fee — Additions or Modifications to Existing Structures (Structural, Plumbing, Mechanical, and/or Electrical Systems); no distinct EV charger line itemClinton City Consolidated Fee Schedule, FY 2026-27 (Building Permit Fees est. 2001): 'Additions or Modifications to Existing Structures; Structural, Plumbing, Mechanical, and/or Electrical Systems. Fees shall be assessed in accordance with the provisions of Section 304 of the 1997 Uniform Administrative Code (UAC), Section 109 of the IBC and Section R108 of the IRC.'
Assessed per Section 304 of the 1997 Uniform Administrative Code (UAC), Section 109 of the IBC, and Section R108 of the IRC (valuation-based)
Re-inspection Fee (if a re-inspection of the EV charger circuit is needed)Clinton City Consolidated Fee Schedule, FY 2026-27, Other Inspection Fees, item 2.
$58.80 per inspection

Review timeline

Plan review
Not published — contact the department

How long did your EV Charger / EVSE Permit permit actually take in Clinton?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    Electrical Inspection

    Inspection of the new circuit/equipment by Clinton City as part of the standard electrical/building permit process.

See the full Clinton inspection guide — scheduling & re-inspection fees →

Tips

  • Clinton bills EV charger installations under its general 'Additions or Modifications to Existing Structures' valuation-based fee clause, not a dedicated EV category — confirm the assigned valuation with the Building Department before applying.

Frequently asked questions

Clinton requires an ev charger / evse permit for: Installation of a Level 2 or DC fast EV charger (EVSE) at a residential or commercial property within Clinton City; Dedicated 240V circuit and/or panel capacity installed by a licensed electrician; Building permit filed with Clinton City for the electrical modification, valued per Section 304 UAC / Section 109 IBC / Section R108 IRC. If your project isn't listed, confirm with Clinton City Community Development Department — Building Division at (801) 614-0740 before starting work.

No. Clinton City's Consolidated Fee Schedule (FY 2026-27) has no EV/EVSE line item; electrical work is billed under the same valuation-based fee clause covering additions/modifications to structural, plumbing, mechanical, and electrical systems (Section 304 UAC / Section 109 IBC / Section R108 IRC).

Clinton does not publish a plan-review timeline for this permit. Contact Clinton City Community Development Department — Building Division at (801) 614-0740 for current turnaround.

You'll need: Building Permit Application (Electrical/Mechanical/Plumbing). See the required-documents checklist on this page for details on each.

Clinton requires 1 inspection(s) for an ev charger / evse permit, in order: Electrical Inspection. Schedule each through Clinton City Community Development Department — Building Division ((801) 614-0740).

Apply through Clinton City Community Development Department — Building Division at 2267 North 1500 West, Clinton, UT 84015. Phone: (801) 614-0740. Office hours: Monday–Friday, 8:00 AM – 5:00 PM. Official information: https://www.clintoncity.net/2164/Building-Division.

Clinton, Utah has adopted: 2024 International Building Code (Appendices C & J) — governing edition per Utah Code § 15A-2-103(1)(a), effective 2026-07-01, superseded the 2021 edition; NOTE (2026-07-16): Clinton City's own Design Criteria document (rev. 07/03/2023) still lists 2021 and has not been confirmed updated to reflect this statewide transition — the statute governs regardless of the city document's lag; 2021 International Residential Code (Appendix AQ) — Clinton City Design Criteria, rev. 07/03/2023; one- and two-family dwellings and townhomes; unaffected by the 7/1/2026 statute revision (Utah Code § 15A-2-103(1)(b)/(c)) — Clinton's Design Criteria is current on this point; 2015 IRC Chapter 11, Energy Efficiency (residential) — Clinton City Design Criteria, rev. 07/03/2023; 2024 International Plumbing Code (IPC) — governing edition per Utah Code § 15A-2-103(1)(d), effective 2026-07-01, superseded the 2021 edition; NOTE (2026-07-16): Clinton City's own Design Criteria document (rev. 07/03/2023) still lists 2021 and has not been confirmed updated; 2024 International Mechanical Code (IMC) — governing edition per Utah Code § 15A-2-103(1)(e), effective 2026-07-01, superseded the 2021 edition; NOTE (2026-07-16): Clinton City's own Design Criteria document (rev. 07/03/2023) still lists 2021 and has not been confirmed updated; 2024 International Fuel Gas Code (IFGC) — governing edition per Utah Code § 15A-2-103(1)(f), effective 2026-07-01, superseded the 2021 edition; NOTE (2026-07-16): Clinton City's own Design Criteria document (rev. 07/03/2023) still lists 2021 and has not been confirmed updated; 2021 International Fire Code (IFC) — Clinton City Design Criteria, rev. 07/03/2023; 2020 National Electrical Code (NEC) — Clinton City Design Criteria, rev. 07/03/2023; this is one edition behind the 2023 NEC baseline confirmed in other Davis County cities (e.g., Kaysville) under Utah Code § 15A-2-103(1)(g) — Clinton's own published Design Criteria document is the only NEC-edition source found for this city and had not been superseded by a newer published revision as of verification; the 2023 NEC baseline itself was unaffected by the 7/1/2026 statute revision, so this gap predates and is unrelated to that transition; 2015 International Energy Conservation Code (residential provisions) — Clinton City Design Criteria, rev. 07/03/2023; 2024 International Energy Conservation Code (commercial provisions) — governing edition per Utah Code § 15A-2-103(1)(h), effective 2026-07-01, superseded the 2021 edition; NOTE (2026-07-16): Clinton City's own Design Criteria document (rev. 07/03/2023) still lists 2021 and has not been confirmed updated; 2024 International Existing Building Code (IEBC) — governing edition per Utah Code § 15A-2-103(1)(i), effective 2026-07-01, superseded the 2021 edition; NOTE (2026-07-16): Clinton City's own Design Criteria document (rev. 07/03/2023) still lists 2021 and has not been confirmed updated; Accessibility Code — 2021 IBC (ICC/ANSI A117.1-2017) — Clinton City Design Criteria, rev. 07/03/2023; 1997 ICBO Uniform Administrative Code (UAC), Chapter 3 and Table 1-A (as modified) — governs the Building Permit Fee valuation-fee-schedule methodology per Clinton City Consolidated Fee Schedule, FY 2026-27; 1997 Uniform Code for the Abatement of Dangerous Buildings — adopted by Clinton City Code § 5-3-2(2), with local exceptions (references to 'health officer' mean the Davis County Environmental Health and Laboratory Division; recovered funds return to the general fund rather than a repair/demolition fund); GOVERNANCE NOTE: Clinton City Code § 5-3-2(1) adopts 'the current editions of the technical/model codes as adopted by the State of Utah and as published by the International Code Council' as its baseline — i.e., Clinton does not independently select code editions the way some sibling cities' own Design Criteria documents do; it defers to the statewide code suite under Utah Code Title 15A. Because Clinton's own code text defers to the state, and the statute (Utah Code § 15A-2-103) is the ultimate authority here, the 2024 editions of IBC/IPC/IMC/IFGC/IECC(commercial)/IEBC that took effect 2026-07-01 govern in Clinton even though the city's own Design Criteria PDF (rev. 07/03/2023) has not been confirmed updated to show them. Clinton's Design Criteria remains the authoritative source for items the statute revision did not change (IRC, 2015 IRC Ch.11, NEC, IFC, accessibility code) and for local specifics not covered by the statute.; NOTE: Effective July 1, 2026 (now in force) — 2024 editions of IBC, IPC, IMC, IFGC, and IECC (commercial) replaced the 2021 editions statewide per Utah Code § 15A-2-103 (version effective 7/1/2026, superseded 1/1/2027; text independently re-verified live at le.utah.gov 2026-07-16). Clinton's Design Criteria document (last revised 07/03/2023) had not been confirmed updated to reflect this transition as of 2026-07-16 — confirm current adopted edition with the Building Division at (801) 614-0740. The 2021 IRC and 2020 NEC listed in Clinton's Design Criteria were unaffected by this statute revision (Utah's statewide NEC baseline is 2023; Clinton's Design Criteria was already one edition behind that baseline for an unrelated reason, per the NEC line above).. Local amendments apply — see the Clinton overview page for the full list.

Sources & verification

Key facts verified against official sources. Last reviewed 2026-07-20.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Clinton building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.