Residential Building Permit in Clinton, Utah
Required for new residential construction, additions, alterations, and most structural or MEP modifications to existing structures in Clinton, governed by the 2021 IRC per Clinton's Design Criteria (rev. 07/03/2023). Fees are valuation-based per the 1997 ICBO Uniform Administrative Code Table 1-A as modified by the city, with a 0.85 permit-fee multiplier applied except for shell-only buildings (0.80), commercial tenant finish (0.35), and commercial remodel (0.60).
Verified 2026-07-03 · Source
When you need this permit
- New single-family or multi-family residential construction
- Additions requiring structural work
- Structural, plumbing, mechanical, and/or electrical modifications to existing structures (Clinton City Code § 5-1-1)
- Conversion of non-habitable space to habitable space
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 2 required documents checked.
This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29 →
Fee schedule
Review timeline
Inspection process
- 1
Foundation / Footing
Before concrete pour — verify excavation, forms, rebar, anchor bolts, and the required footing/foundation sub-drain per Clinton City Code § 5-3-3(5)
- 2
Framing
After framing, sheathing, and rough-in MEP — before insulation or wall cover
- 3
Insulation
After insulation installed, before drywall
- 4
Final
All work complete — certificate of occupancy issued upon passing
See the full Clinton inspection guide — scheduling & re-inspection fees →
Tips
- Clinton City's building permit fee schedule uses a 0.85 permit-fee multiplier on the base valuation-fee table for most residential work — this is distinct from simply reading the raw Table 1-A-style valuation fee, and reduces the effective charge versus a sibling city that does not apply a multiplier.
- A $1,500 refundable Building Bond applies to single-family dwellings and modifications; this rises to $8,500 for single-family dwellings in a 'PH Zone' requiring trees, landscaping, and an automatic sprinkling system.
- Clinton is served by the North Davis Sewer District — a separate $3,454.03 sewer impact fee (est. 2024) applies in addition to Clinton's own $113 sewer impact-fee line item.
- Design Criteria (rev. 07/03/2023): Seismic Zone D, ground snow load per utahsnowload.usu.edu, wind speed 105 mph (conventional construction; ASCE 7-10 for non-conventional), Exposure B or C, frost depth 30 inches, allowable soil bearing pressure 1,500 psi absent a geotechnical study.
- Clinton City Code § 5-3-3 requires a 4-inch minimum layer of 1-inch-or-smaller rock under all basement floors and a Ufer ground installed in the garage wall cavity with permanent access via a mud ring or outlet box cover.
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-07-03.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Clinton building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Other permits in Clinton
Residential Building Permit in other cities
Compare residential building permit fees across Utah →
Look up this fee in a different city →