Residential Building Permit (New Construction, Single Family, Duplexes, Twin Homes, Townhomes) — Cedar City, Utah · Requirements sheet
Reviewed 2026-07-30 · Source: https://www.cedarcityut.gov/DocumentCenter/View/14648/Permit-Document-List
PermitBase is an independent reference and is not affiliated with any government agency. Requirements change and vary by project — confirm current details with the building department before you submit.
Residential Building Permit (New Construction, Single Family, Duplexes, Twin Homes, Townhomes) in Cedar City, Utah
Required for new single-family, duplex, twin-home, and townhome construction in Cedar City, regulated by the state-adopted 2024 IBC / 2021 IRC (per Utah Code § 15A-2-103, effective 7/1/2026 — Cedar City's own Current Adopted Codes page has not yet been updated to reflect the 2024 IBC as of 2026-07-16). Base building permit fee is scaled to water meter size per the city's own Fee Estimate Request form rather than solely a flat ICC-valuation chart; the underlying fee ordinance is codified in Chapter 36 of Cedar City's municipal code.
Reviewed 2026-07-30 · Source
When you need this permit
- New single-family, duplex, twin-home, or townhome construction
- Site plan showing actual building setbacks, address/lot/subdivision, directional arrow, street name, and parking
- Utah Prairie Dog Clearance letter (Department of Natural Resources) required any time ground is broken
- Geo-Technical Data Sheet / Pre-Construction Document with Engineer's Stamp required any time ground is broken
- All applicable contractors must hold current DOPL (Utah Division of Occupational and Professional Licensing) licenses, unless a Notarized Owner/Builder Certificate is submitted Owner-builder
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 7 required documents checked.
This checker covers one permit. A full project usually triggers several — our checklist will assemble all of them, free →
Fee schedule
Cedar City Fee Estimate Request form (cedarcityut.gov/DocumentCenter/View/14851/Estimate-of-Fees): 'Building Permit > Based on water meter size.' The Consolidated Fee Schedule edition LAST UPDATED… Show full citationHide
Cedar City Fee Estimate Request form (cedarcityut.gov/DocumentCenter/View/14851/Estimate-of-Fees): 'Building Permit > Based on water meter size.' The Consolidated Fee Schedule edition LAST UPDATED 3-Dec-25 states the underlying Building Permit Fee is 'As set by Uniform Codes Adopted by Ch. 36' of the municipal code (codified at cedarcity.municipalcodeonline.com). The Consolidated Fee Schedule has since been reissued (LAST UPDATED 24-Jun-26) and publishes an explicit valuation-based Building Permit Calculation Table, which does not align with the Fee Estimate Request form's 'based on water meter size' language; the two have not been reconciled by the city. Building Permit Calculation Table (total valuation → fee): $1-$500 = $24.00 · $501-$2,000 = $24 for the first $500 plus $3 per additional $100 or fraction, to $2,000 · $2,001-$40,000 = $69 for the first $2,000 plus $11 per additional $1,000 · $40,001-$100,000 = $487 for the first $40,000 plus $9 per additional $1,000 · $100,001-$500,000 = $1,027 for the first $100,000 plus $7 per additional $1,000 · $500,001-$1,000,000 = $3,827 for the first $500,000 plus $5 per additional $1,000 · $1,000,001 and over = $6,387 for the first $1,000,000 plus $4 per additional $1,000. Plan Review is 30% of the building permit and the Utah State Fee is 1% of it.Cedar City Fee Estimate Request form lists these as potentially applicable line items but states: 'This is not a complete list of possible fees... Show full citationHide
Cedar City Fee Estimate Request form lists these as potentially applicable line items but states: 'This is not a complete list of possible fees... These are estimates and not exact amounts. The exact amount can only be determined after plan check has been completed and the permit is processed.' No specific dollar figures for these impact fees are published on this form; omitted rather than invented. Residents can request a project-specific estimate via the same form.Review timeline
Inspection process
- 1
Footing Exterior
Footing depth per plan; rebar chaired/secured/lapped per plan; rebar Ufer ground tied to footing bar. Per Cedar City Building Department Inspection Reference Guide.
- 2
Interior Footing
Placement of footing and rebar verified; no plumbing running parallel inside footing; pipes crossing footings protected; footing depth checked.
- 3
Underground Electrical / Underground Mechanical / Underground Plumbing
Trench depth, conduit/conductor sizing, direct-burial-listed ducts with sealed joints, pipe slope, cleanouts, backflow preventers on basements, minimum 10-foot water head test or 15-minute air test.
- 4
Foundation Wall
Rebar spacing/ties per plan, wall thickness per plan, hold-downs in proper locations, wall height matching engineering.
- 5
Slab (suspended)
Rebar size/spacing and slab thickness per plan.
- 6
Temporary Power
Panel pole secured, all circuits GFCI-protected, ground/neutral bonded.
- 7
Roof
Sheathing gap, nailing, thickness per span rating, truss condition and bracing per plan.
- 8
Interior/Exterior Shear
Sheathing type/size, nailing, hold-down hardware, anchor bolts per plan.
- 9
Rough Mechanical / Rough Plumbing / Rough Electrical / Gas Piping
Ductwork support and insulation, DWV water/air test, vent slope, outlet spacing, smoke/CO detector placement, gas line pressure test (1.5x working pressure, minimum 3 psig) with Cedar City gas clearance form on site.
- 10
Framing
All prior inspections approved; notching/boring of structural members checked; tempered glass in hazardous locations; stair construction; fire blocking; egress window sizing (max 44 in. to opening).
- 11
Insulation
Batts installed per manufacturer instructions with correct R-value; top/bottom plate holes sealed; window/door jambs sealed to meet IECC minimums.
- 12
Lath / Drywall / Fire Assembly / Shower Pan
Weather barrier and lath wire installation; Type X drywall over garages with living space above; fire-rated assembly verification; shower pan 2-inch water dam test.
- 13
Permanent Power
Rocky Mountain Power service order number provided at inspection request; grounding conductors landed; at least one GFCI outlet installed.
- 14
Building Final
Address permanently posted; all trades complete; site clean (no dumpster/porta-potty); driveway finished; grading slopes away from house; all required certificates (stucco, insulation, grading) on site; utilities hooked up and operational.
See the full Cedar City inspection guide — scheduling & re-inspection fees →
Tips
- Cedar City's Inspection Reference Guide (Building Department Req. Inspection Reference Guide) is dated 7/2016 in its footer — the most recent version found via the city's Building Permit Forms & Guides page; verify with the Building Department whether a newer revision exists before relying on it for edge cases.
- All permit applications must be submitted online via the city's permit portal (cedarcity.cityinspect.com/login); there is no in-person/paper submittal path described in the city's own Building Permit Guide.
- A Utah Prairie Dog Clearance letter from the Department of Natural Resources is required any time ground is broken — request via the city's own Prairie Dog Clearance Request form.
- Building Permit fees are scaled to water meter size per Cedar City's own Fee Estimate Request form, rather than to the ICC valuation tables most Utah cities use — so a valuation-based estimate will not predict your fee. Request a project-specific estimate directly from the Building Department.
Frequently asked questions
Sources & verification
Key facts verified against official sources. Last reviewed 2026-07-30.
Fee schedules
Checklists & handouts
Department & other records
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Cedar City building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Property Access
Cedar City's permit history is searchable by address
204 permits on record for Cedar City, 2015–2026 — searchable by street address, with permit type, status, issued date and valuation where the city publishes them.
Other permits in Cedar City
Residential Building Permit (New Construction, Single Family, Duplexes, Twin Homes, Townhomes) in other cities
Look up this fee in a different city →