Electrical Permit (incl. Electric Meter) — Cedar City, Utah · Requirements sheet
Verified 2026-07-03 · Source: https://www.cedarcityut.gov/639/Fee-Schedule
PermitBase is an independent reference and is not affiliated with any government agency. Requirements change and vary by project — confirm current details with the building department before you submit.
Electrical Permit (incl. Electric Meter) in Cedar City, Utah
Required for electrical work in Cedar City, including meter installations/upgrades. Fee schedule includes distinct commercial and residential flat-fee structures based on service entrance amperage. EV charger/EVSE installation is electrical work and falls under this general Electrical Permit; the Consolidated Fee Schedule (LAST UPDATED 3-Dec-25) does not publish an EV-specific line item — a charger circuit would most likely be billed as a Minor Remodel & Additional Circuits item or a Service Change under the residential electrical fee tiers.
Verified 2026-07-03 · Source
When you need this permit
- Electric meter installation or upgrade — requires site plan showing meter location
- New service entrance or amperage upgrade
- Minor remodel and additional circuits, or service change with 1-2 new circuits
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 1 required documents checked.
This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29 →
Fee schedule
Review timeline
Inspection process
- 1
Temporary Power
Panel pole secured, GFCI-protected circuits, ground/neutral bonded.
- 2
Underground Electrical
Trench depth and conduit/conductor sizing per code/utility standards.
- 3
Rough Electrical
Outlet spacing, conductor protection, smoke/CO detector placement, box grounding.
- 4
Permanent Power
Rocky Mountain Power service order number provided; grounding conductors landed; at least one GFCI outlet.
See the full Cedar City inspection guide — scheduling & re-inspection fees →
Tips
- Cedar City's residential electrical fee for a new single-family dwelling is a per-square-foot rate ($0.02/sq ft up to 1,500 sq ft, $0.01/sq ft above), not a flat fee — distinct from several other Utah cities in this corpus that charge a flat electrical permit fee.
- Provide the Rocky Mountain Power service order number when requesting the Permanent Power inspection, per Cedar City's Inspection Reference Guide.
- Cedar City does not publish a distinct EV charger/EVSE permit or fee — a home or workplace charging station is billed under the standard residential/commercial electrical fee tiers (e.g., Minor Remodel & Additional Circuits, or Service Change).
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-07-03.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Cedar City building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Other permits in Cedar City
Electrical Permit (incl. Electric Meter) in other cities
Compare electrical permit (incl. electric meter) fees across Utah →
Look up this fee in a different city →
Now live
Build your Cedar City project checklist
Describe your project once and get every permit, document, and fee it triggers in Cedar City — in one checklist. Sign up and pay once to generate it, or go unlimited with Pro.
Get started →