Electrical Permit (incl. Electric Meter) in Cedar City, Utah
Required for electrical work in Cedar City, including meter installations/upgrades. Fee schedule includes distinct commercial and residential flat-fee structures based on service entrance amperage. EV charger/EVSE installation is electrical work and falls under this general Electrical Permit; the Consolidated Fee Schedule (LAST UPDATED 3-Dec-25) does not publish an EV-specific line item — a charger circuit would most likely be billed as a Minor Remodel & Additional Circuits item or a Service Change under the residential electrical fee tiers.
Reviewed 2026-07-30 · Source
When you need this permit
- Electric meter installation or upgrade — requires site plan showing meter location
- New service entrance or amperage upgrade
- Minor remodel and additional circuits, or service change with 1-2 new circuits
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 1 required documents checked.
This checker covers one permit. A full project usually triggers several — our checklist will assemble all of them, free →
Fee schedule
Cedar City Consolidated Fee Schedule, LAST UPDATED 24-Jun-26, BUILDING DEPARTMENT section pp. Show full citationHide
Cedar City Consolidated Fee Schedule, LAST UPDATED 24-Jun-26, BUILDING DEPARTMENT section pp. 2-3. The PDF's two-column layout misaligns values against labels in a copy-paste, so read the figures from the page as published. The current schedule lists 'Electrical (service upgrade, new meter base, etc.) $50.00' under **Building Valuations** — the same list that sets Remodel / Basement Finish / Tenant Improvement at '$50.00 per Sq foot' — and the permit fee is then derived from the Building Permit Calculation Table. The schedule does not state whether this $50.00 is a valuation input (which would yield a $24.00 permit fee via the $1-$500 tier) or the permit fee itself, so confirm with Cedar City Building before relying on a total. Building Permit Calculation Table (total valuation → fee): $1-$500 = $24.00 · $501-$2,000 = $24 for the first $500 plus $3 per additional $100 or fraction, to $2,000 · $2,001-$40,000 = $69 for the first $2,000 plus $11 per additional $1,000 · $40,001-$100,000 = $487 for the first $40,000 plus $9 per additional $1,000 · $100,001-$500,000 = $1,027 for the first $100,000 plus $7 per additional $1,000 · $500,001-$1,000,000 = $3,827 for the first $500,000 plus $5 per additional $1,000 · $1,000,001 and over = $6,387 for the first $1,000,000 plus $4 per additional $1,000. Plan Review is 30% of the building permit and the Utah State Fee is 1% of it.Review timeline
Inspection process
- 1
Temporary Power
Panel pole secured, GFCI-protected circuits, ground/neutral bonded.
- 2
Underground Electrical
Trench depth and conduit/conductor sizing per code/utility standards.
- 3
Rough Electrical
Outlet spacing, conductor protection, smoke/CO detector placement, box grounding.
- 4
Permanent Power
Rocky Mountain Power service order number provided; grounding conductors landed; at least one GFCI outlet.
See the full Cedar City inspection guide — scheduling & re-inspection fees →
Tips
- Cedar City charges the residential electrical fee for a new single-family dwelling by the square foot rather than as a flat fee: $0.02/sq ft up to 1,500 sq ft and $0.01/sq ft above that. Size this line item off your finished square footage.
- Provide the Rocky Mountain Power service order number when requesting the Permanent Power inspection, per Cedar City's Inspection Reference Guide.
- Cedar City does not publish a distinct EV charger/EVSE permit or fee — a home or workplace charging station is billed under the standard residential/commercial electrical fee tiers (e.g., Minor Remodel & Additional Circuits, or Service Change).
Frequently asked questions
Sources & verification
Key facts verified against official sources. Last reviewed 2026-07-30.
Fee schedules
Checklists & handouts
Department & other records
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Cedar City building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Property Access
Cedar City's permit history is searchable by address
204 permits on record for Cedar City, 2015–2026 — searchable by street address, with permit type, status, issued date and valuation where the city publishes them.
Other permits in Cedar City
Electrical Permit (incl. Electric Meter) in other cities
Compare electrical permit (incl. electric meter) fees across Utah →
Look up this fee in a different city →
Related guides
Now live
Build your Cedar City project checklist
Describe your project once and get every permit, document, and fee it triggers in Cedar City — in one checklist. Free, for any city and any number of projects.
Get started →