Inspection sequence

Applies to: Commercial Building Permit

  1. 1

    Foundation / Footing

    Before concrete pour — verify excavation, forms, rebar, and anchor bolts, per 2024 IBC.

  2. 2

    Framing / Structural

    After framing, sheathing, and structural work — before insulation or wall cover.

  3. 3

    MEP Rough-In

    Electrical, mechanical, and plumbing rough-in inspected before walls closed.

  4. 4

    Final

    All work complete — certificate of occupancy issued upon passing.

Applies to: Residential Building Permit

  1. 1

    Foundation / Footing

    Before concrete pour — verify excavation, forms, rebar, anchor bolts, and the required footing/foundation sub-drain per Clinton City Code § 5-3-3(5)

  2. 2

    Framing

    After framing, sheathing, and rough-in MEP — before insulation or wall cover

  3. 3

    Insulation

    After insulation installed, before drywall

  4. 4

    Final

    All work complete — certificate of occupancy issued upon passing

Applies to: Commercial Tenant Improvement / Tenant Finish Permit

  1. 1

    Framing / Structural (if applicable)

    Interior wall framing and structural connections verified before close-in, where the scope includes structural work.

  2. 2

    MEP Rough-In

    Electrical, mechanical, and plumbing rough-in for the tenant space, inspected before walls closed.

  3. 3

    Final

    All tenant-finish or remodel work complete before occupancy.

Applies to: Residential Pool Permit

  1. 1

    Pre-Gunite / Bonding

    Steel, plumbing, and electrical bonding before shotcrete/gunite or liner installation (in-ground pools)

  2. 2

    Barrier / Fence

    Pool barrier compliance verified before water can be introduced

  3. 3

    Final

    Equipment, bonding, and barrier complete

Applies to: Residential Remodel Permit (Patio Covers, Awnings & Decks)

  1. 1

    Footings (decks/patio covers)

    Verify footing depth (minimum 30 inches below grade per Clinton's frost depth), diameter, and rebar before concrete pour

  2. 2

    Framing

    Wall or deck/patio-cover framing, fire blocking where applicable, MEP rough-in

  3. 3

    Final

    All finishes, railings, and fixtures complete

Applies to: Change of Use / Certificate of Occupancy

  1. 1

    Certificate of Occupancy / Zoning Compliance Inspection

    Building Inspector confirms the building, its proposed use, or the use of the land complies with the Zoning Ordinance before issuing the Certificate of Occupancy (§ 28-1-6); the Community Development Director may withhold the Certificate if the change in use would violate the Zoning Ordinance or any other city/state law (§ 28-1-8(1))

  2. 2

    Business License Inspections (Building / Fire)

    Building Inspection Fee ($59.00) and Fire Inspection Fee ($59.00) apply to commercial business licenses per the Consolidated Fee Schedule; may be required with initial issue of the license or annually based on assessment of the business

Applies to: Demolition Permit

  1. 1

    Utility Disconnect Verification

    Sewer, water, secondary water, land drain, power, and telephone/cable laterals disconnected per Clinton City Code § 5-6-3

  2. 2

    Final / Site Restoration

    Site cleared of debris, graded for natural drainage, per Clinton City Code § 5-6-4

Applies to: Electrical / Mechanical / Plumbing Permit (Utility Modifications)

  1. 1

    Rough-In

    Wiring, piping, or ductwork installed, before walls closed

  2. 2

    Final

    Equipment installed and operational, venting/gas connections verified where applicable

Applies to: Solar Energy System Permit

  1. 1

    Rough Electrical

    Conduit runs, wire sizing, disconnect placement before energizing

  2. 2

    Final / Structural

    Panel mounting, racking attachment, roof penetration sealing, and electrical connections verified

Re-inspection fees

Electrical / Mechanical / Plumbing Permit (Utility Modifications)Re-inspection Fee (assessed under adopted Construction Codes) · Clinton City Consolidated Fee Schedule, FY 2026-27, Other Inspection Fees, item 2
$58.80 per inspection
EV Charger / EVSE PermitRe-inspection Fee (if a re-inspection of the EV charger circuit is needed) · Clinton City Consolidated Fee Schedule, FY 2026-27, Other Inspection Fees, item 2.
$58.80 per inspection

Clinton building permits

Get alerts for Clinton

We'll email you when Clinton's fees, documents, or codes change — not often.

We only use your email to send permit updates. No spam, unsubscribe anytime. Privacy.