How to schedule
Inspections are requested through the building department below.
- Address
- 2267 North 1500 West, Clinton, UT 84015
- Phone
- (801) 614-0740
- Office hours
- Monday–Friday, 8:00 AM – 5:00 PM
- Website
- Official site
Inspection sequence
Applies to: Commercial Building Permit
- 1
Foundation / Footing
Before concrete pour — verify excavation, forms, rebar, and anchor bolts, per 2024 IBC.
- 2
Framing / Structural
After framing, sheathing, and structural work — before insulation or wall cover.
- 3
MEP Rough-In
Electrical, mechanical, and plumbing rough-in inspected before walls closed.
- 4
Final
All work complete — certificate of occupancy issued upon passing.
Applies to: Residential Building Permit
- 1
Foundation / Footing
Before concrete pour — verify excavation, forms, rebar, anchor bolts, and the required footing/foundation sub-drain per Clinton City Code § 5-3-3(5)
- 2
Framing
After framing, sheathing, and rough-in MEP — before insulation or wall cover
- 3
Insulation
After insulation installed, before drywall
- 4
Final
All work complete — certificate of occupancy issued upon passing
Applies to: Commercial Tenant Improvement / Tenant Finish Permit
- 1
Framing / Structural (if applicable)
Interior wall framing and structural connections verified before close-in, where the scope includes structural work.
- 2
MEP Rough-In
Electrical, mechanical, and plumbing rough-in for the tenant space, inspected before walls closed.
- 3
Final
All tenant-finish or remodel work complete before occupancy.
Applies to: Residential Pool Permit
- 1
Pre-Gunite / Bonding
Steel, plumbing, and electrical bonding before shotcrete/gunite or liner installation (in-ground pools)
- 2
Barrier / Fence
Pool barrier compliance verified before water can be introduced
- 3
Final
Equipment, bonding, and barrier complete
Applies to: Residential Remodel Permit (Patio Covers, Awnings & Decks)
- 1
Footings (decks/patio covers)
Verify footing depth (minimum 30 inches below grade per Clinton's frost depth), diameter, and rebar before concrete pour
- 2
Framing
Wall or deck/patio-cover framing, fire blocking where applicable, MEP rough-in
- 3
Final
All finishes, railings, and fixtures complete
Applies to: Change of Use / Certificate of Occupancy
- 1
Certificate of Occupancy / Zoning Compliance Inspection
Building Inspector confirms the building, its proposed use, or the use of the land complies with the Zoning Ordinance before issuing the Certificate of Occupancy (§ 28-1-6); the Community Development Director may withhold the Certificate if the change in use would violate the Zoning Ordinance or any other city/state law (§ 28-1-8(1))
- 2
Business License Inspections (Building / Fire)
Building Inspection Fee ($59.00) and Fire Inspection Fee ($59.00) apply to commercial business licenses per the Consolidated Fee Schedule; may be required with initial issue of the license or annually based on assessment of the business
Applies to: Demolition Permit
- 1
Utility Disconnect Verification
Sewer, water, secondary water, land drain, power, and telephone/cable laterals disconnected per Clinton City Code § 5-6-3
- 2
Final / Site Restoration
Site cleared of debris, graded for natural drainage, per Clinton City Code § 5-6-4
Applies to: Electrical / Mechanical / Plumbing Permit (Utility Modifications)
- 1
Rough-In
Wiring, piping, or ductwork installed, before walls closed
- 2
Final
Equipment installed and operational, venting/gas connections verified where applicable
Applies to: Solar Energy System Permit
- 1
Rough Electrical
Conduit runs, wire sizing, disconnect placement before energizing
- 2
Final / Structural
Panel mounting, racking attachment, roof penetration sealing, and electrical connections verified
Final inspection only: Automatic Fire Extinguishing (Sprinkler) and Alarm System Permit, EV Charger / EVSE Permit, Roofing Permit, Sign Permit
Re-inspection fees
Sources & verification
Verified against official sources. Last reviewed 2026-07-13.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Clinton building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Clinton building permits
Get alerts for Clinton
We'll email you when Clinton's fees, documents, or codes change — not often.
We only use your email to send permit updates. No spam, unsubscribe anytime. Privacy.