Re-Roof Permit (2nd or 3rd Layer) in Pleasant View, Utah

Required for re-roofing work involving a second or third layer, classified by Pleasant View as a 'Misc. permit' with a flat minimum fee under the Consolidated Fee Schedule.

Verified 2026-07-08 · Source

When you need this permit

  • Re-roof involving a 2nd or 3rd layer of roofing material, per the Consolidated Fee Schedule's 'Misc. permits' category
  • Building Permit Application submitted through the City Inspect online portal

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 1 required documents checked.

This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29

Fee schedule

Misc. Permit Fee (re-roof, 2nd or 3rd layer)Pleasant View City Consolidated Fee Schedule (as of July 1, 2026), page 2: 'Misc. permits ................................................................ $100.00 minimum fee for any building permit' with the category defined as '(i.e. demolition, fence, mechanical only, plumbing only, re-roof (2nd or 3rd layer)...)'. A first-layer re-roof (tear-off and replace) is not separately itemized and would be assessed under the general valuation-based Table for Permit Fees if it constitutes a full roofing replacement.
$100.00 minimum

Review timeline

Plan reviewTypical estimate — confirm current times with the Pleasant View building department
~14–14 business days

How long did your Re-Roof Permit (2nd or 3rd Layer) permit actually take in Pleasant View?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    Building

    Scheduled via City Inspect (pleasantview.cityinspect.com) or Sunrise Engineering (1-800-560-6151).

See the full Pleasant View inspection guide — scheduling & re-inspection fees →

Tips

  • Pleasant View bundles re-roof (2nd or 3rd layer), demolition, fence, mechanical-only, and plumbing-only work together under a single 'Misc. permits' $100.00 minimum fee category — it is not a distinct dedicated fee schedule per project type.
  • A full tear-off/first-layer re-roof is not listed under the Misc. permits minimum and may instead be assessed valuation-based fees under the general Table for Permit Fees — confirm classification with the Building Department (801-782-8529) before applying.

Frequently asked questions

Pleasant View requires a re-roof permit (2nd or 3rd layer) for: Re-roof involving a 2nd or 3rd layer of roofing material, per the Consolidated Fee Schedule's 'Misc. permits' category; Building Permit Application submitted through the City Inspect online portal. If your project isn't listed, confirm with Pleasant View City Planning, Zoning & Building Department at (801) 782-8529 before starting work.

A 2nd or 3rd layer re-roof falls under Pleasant View's 'Misc. permits' category, which carries a $100.00 minimum fee per the Consolidated Fee Schedule (as of July 1, 2026).

Plan review for a re-roof permit (2nd or 3rd layer) in Pleasant View typically runs 14–14 business days. This is an estimate, not a published figure — confirm current review times with Pleasant View City Planning, Zoning & Building Department at (801) 782-8529.

You'll need: Building Permit Application (City Inspect). See the required-documents checklist on this page for details on each.

Pleasant View requires 1 inspection(s) for a re-roof permit (2nd or 3rd layer), in order: Building. Schedule each through Pleasant View City Planning, Zoning & Building Department ((801) 782-8529).

Apply through Pleasant View City Planning, Zoning & Building Department at 520 W Elberta Dr, Pleasant View, UT 84414. Phone: (801) 782-8529. Office hours: Mon–Thu 8:00 AM – 5:00 PM; Fri 8:00 AM – 12:00 PM. Official information: https://www.pleasantviewut.gov/168/Planning-Zoning-Building.

Pleasant View, Utah has adopted: 2024 International Building Code (IBC), including Appendices C and J — current statewide code per Utah Code § 15A-2-103(1)(a), in force since July 1, 2026, under the statewide preemption mandate of § 15A-1-204 (State Construction and Fire Codes Act); Pleasant View's own codified Title 15.04 text still references the 2000 IBC (Ord. 2002-10), but that codification is stale and superseded by the mandatory statewide cycle.; 2021 International Residential Code (IRC) — current statewide code per Utah Code § 15A-2-103(1)(b) (unchanged by the July 1, 2026 code cycle flip); Pleasant View's Consolidated Fee Schedule (as of July 1, 2026) still labels its Table for Permit Fees 'Appendix L, 2015 IRC,' which is stale fee-table boilerplate, not evidence the city enforces an outdated code edition — plan review and inspections apply the current statewide IRC per § 15A-1-204.; 2024 International Plumbing Code (IPC) — current statewide code per Utah Code § 15A-2-103(1)(d); Pleasant View's codified Title 15.16.010 references the 2000 IPC (stale codification), superseded by § 15A-1-204.; 2024 International Mechanical Code (IMC) / International Fuel Gas Code (IFGC) — current statewide code per Utah Code § 15A-2-103(1)(e)/(f); Pleasant View's codified Title 15.12.010 references the 2000 IMC (stale codification), superseded by § 15A-1-204.; 2024 International Energy Conservation Code (IECC) with Utah amendments — current statewide code per Utah Code § 15A-2-103(1)(h) (a single edition applies statewide, no separate residential/commercial split); Pleasant View's codified Title 15.28.010 references the 2000 IECC (stale codification), superseded by § 15A-1-204.; 2023 National Electrical Code (NEC) — current statewide code per Utah Code § 15A-2-103(1)(g) (unchanged by the July 1, 2026 code cycle flip); Pleasant View's codified Title 15.20.010 references the 1999 NEC (stale codification), superseded by § 15A-1-204.. Local amendments apply — see the Pleasant View overview page for the full list.

Sources & verification

Verified against official sources. Last reviewed 2026-07-08.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Pleasant View building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.