Draper building inspections
VerifiedInspection sequence, scheduling, and re-inspection fees for building permits in Draper, Utah.
Verified 2026-07-13 · Source
How to schedule
Inspections are requested through the building department below.
- Address
- 1020 E. Pioneer Rd., Draper, UT 84020
- Phone
- (801) 576-6399
- Office hours
- Mon–Fri 8:00 AM – 5:00 PM
- Website
- Official site
Published scheduling rules
- Schedule inspections through the Online Services Portal at draper.onlama.com or by calling (801) 576-6399. (Residential Building Permit)
Inspection sequence
Applies to: Accessory Dwelling Unit (ADU)
- 1
Foundation
Footings, forms, rebar — before concrete pour
- 2
Framing
Structure, fire separation, egress windows
- 3
MEP Rough-In
Mechanical, electrical, plumbing rough-ins before walls closed
- 4
Insulation
Insulation and vapor barrier before drywall
- 5
Final
All work complete, smoke/CO detectors installed, address posted, ready for occupancy
Applies to: Commercial Building Permit
- 1
Foundation / Footing
Before concrete pour — verify excavation, forms, rebar, and anchor bolts
- 2
Underground / Rough-In (MEP)
Before backfill and before closing walls or ceilings
- 3
Framing
After framing, sheathing, and rough-in mechanical/electrical/plumbing — before insulation or wall cover
- 4
Fire Sprinkler / Fire Alarm
Included in the Fire Department's Commercial Fire Sprinkler/Alarm System Plan Review fee (3 inspections included in the base fee)
- 5
Final
All work complete — certificate of occupancy issued upon passing
Applies to: Basement Finish Permit
- 1
Framing
Wall framing, fire blocking, egress window wells and openings verified
- 2
MEP Rough-In
Electrical, plumbing, and HVAC rough-ins before walls closed
- 3
Insulation
Insulation on exterior walls, vapor barrier placement
- 4
Final
Drywall, fixtures, smoke/CO detectors, and all finishes complete
Applies to: Residential Building Permit
- 1
Foundation / Footing
Before concrete pour — verify excavation, forms, rebar, and anchor bolts
- 2
Framing
After framing, sheathing, and rough-in mechanical/electrical/plumbing — before insulation or wall cover
- 3
Insulation
After insulation installed, before drywall
- 4
Final
All work complete — certificate of occupancy issued upon passing
Applies to: Sign Permit
- 1
Footing / Structural
Required on all freestanding signs
- 2
Electrical
Required on all illuminated signs
- 3
Wall Attachment
Inspection of braces, anchors, supports, and connections on all wall signs
- 4
Final
Confirms the sign was located and constructed according to the approved sign permit; a weatherproof certification tag is affixed to the sign
Applies to: Commercial Tenant Improvement / Tenant Finish Permit
- 1
Framing / Rough-In (MEP)
After framing and rough-in mechanical, electrical, and plumbing work — before insulation or wall cover
- 2
Fire Sprinkler / Fire Alarm (if applicable)
Included in the Fire Department's Remodel or Tenant Finish Plan Review fee where the scope modifies existing systems (3 inspections included)
- 3
Final
All work complete; space approved for occupancy under the tenant's use classification
Applies to: Deck Permit
- 1
Footing
Post footings before concrete pour
- 2
Framing
All framing, connections, and ledger attachment complete
- 3
Final
Railings, stairs, and all work complete
Applies to: Electrical Permit
- 1
Rough-In
After wiring installed, before walls closed — verify box placement, wire sizing, proper support
- 2
Service / Panel
Panel installation, grounding electrode system, service entrance conductors
- 3
Final
All devices installed, GFCI/AFCI protection verified, panel labeled
Applies to: Plumbing Permit
- 1
Underground / Slab
Before concrete pour — verify pipe slope, materials, and cleanouts
- 2
Rough-In
After pipes installed, before walls closed — pressure test required
- 3
Final
All fixtures connected, water flowing, no leaks, proper venting verified
Applies to: Retaining Wall Permit
- 1
Footing
Footing excavation, rebar, and forms before concrete pour
- 2
Backfill / Drainage
Drainage gravel, pipe, and filter fabric before backfill
- 3
Final
Wall complete, drainage functional, site graded
Applies to: Demolition Permit
- 1
Pre-Demolition
Verify utility disconnects complete and any required asbestos clearance obtained before work begins
- 2
Final / Site Clear
Site cleared, foundation removed or capped, erosion control in place
Applies to: EV Charger / EVSE Permit
- 1
Rough-In
After wiring installed, before walls closed — verify box placement, wire sizing, proper support.
- 2
Final
Charger mounted and energized, GFCI/breaker sizing verified, labeling complete.
Applies to: Fire Alarm Permit
- 1
Rough-In
Wiring, device placement, and panel installation verified before concealment
- 2
Acceptance Test / Final
Functional test of all initiating and notification devices on the completed alarm system
Applies to: Fire Sprinkler Permit
- 1
Rough-In / Underground
Piping, hangers, and underground supply verified before concealment
- 2
Acceptance Test / Final
Hydrostatic test, flow test, and final acceptance of the completed system; included in the base plan review fee (2 inspections residential, 3 inspections commercial)
Applies to: Mechanical / HVAC Permit
- 1
Rough-In
Ductwork and gas piping installed, before walls closed — verify clearances and support
- 2
Final
Equipment operational, combustion air verified, gas pressure tested, thermostat functional
Applies to: Roofing Permit
- 1
Deck / Substrate
After tear-off — verify sheathing condition, replace damaged decking before proceeding
- 2
Final
Completed roof — verify ice and water shield, flashing, drip edge, and nailing pattern
Applies to: Solar Panel Permit
- 1
Rough Electrical
Conduit runs, wire sizing, disconnect placement before energizing
- 2
Final / Structural
Panel mounting, racking attachment, roof penetration sealing, and electrical connections verified
Final inspection only: Change of Use / Certificate of Occupancy, Water Heater Permit
Re-inspection fees
Sources & verification
Verified against official sources. Last reviewed 2026-07-13.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Draper building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Draper building permits