Skip to main content
PermitBase

Commercial Building Permit in Draper, Utah

Required for new commercial building construction, additions, and structural alterations in Draper. Draper does not use a separate commercial fee table — the same "Building Permit" fee formula (100% of the ICC Building Valuation Data schedule) applies to both residential and commercial structures. A $500 deposit is due at application, applied to the total fee. Commercial projects also require a geotechnical report and are subject to commercial-specific impact fees and fire sprinkler/alarm plan review fees not charged on residential permits.

Verified 2026-07-19 · Source

When you need this permit

  • New commercial building construction, addition, or structural alteration
  • Complete architectural and structural drawings, unlocked (not password-protected) digital files
  • Geotechnical engineering report reviewed, approved, and accepted by Draper City — required before the application will be accepted
  • Energy code compliance documentation (COMcheck or equivalent) for the adopted commercial IECC
  • Fire sprinkler and/or fire alarm system plans where required by the adopted IBC/IFC

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 4 required documents checked.

This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29

Fee schedule

Building Permit — valuation-basedDraper Consolidated Fee Schedule, Resolution 26-29 (Jul 2026), item 44 — same formula applies to commercial as residential; no separate commercial table exists. $500 deposit due at application, applied to total fee; refunds on canceled/changed permits capped at 60% of the building permit fee.
100% of the ICC Schedule (International Code Council Building Valuation Data table, as published in Building Safety Journal)
Plan ReviewDraper Consolidated Fee Schedule, Resolution 26-29, item 45
65% of the building permit fee
Additional Plan Review (changes/alterations/revisions to plans)Draper Consolidated Fee Schedule, Resolution 26-29, item 46
$85.00 per hour
Commercial Fire Sprinkler System Plan Review (New System Install) — under 100 headsDraper Consolidated Fee Schedule, Resolution 26-29, items 171-175 — scales to $175 (100-199 heads), $225 (200-299 heads), $275 (>300 heads), plus $0.50 per sprinkler head installed
$125.00 (includes 3 inspections)
Fire Alarm Systems Plan Review and Inspection — New SystemDraper Consolidated Fee Schedule, Resolution 26-29, item 188
$150.00
Fire Impact Fee — Commercial (per 1,000 sq ft gross lease area)Draper Consolidated Fee Schedule, Resolution 26-29, item 240 — New Residential and Commercial Development impact fee, paid when building permit is issued
$97.00
Police Facilities Impact Fee — Commercial (per 1,000 sq ft gross lease area)Draper Consolidated Fee Schedule, Resolution 26-29, item 251
$130.00
Transportation Facilities Impact Fee — Commercial (per 1,000 sq ft gross area lease)Draper Consolidated Fee Schedule, Resolution 26-29, item 257
$3,040.00
Public Infrastructure Repair and Restoration Bond (new commercial buildings)Draper Consolidated Fee Schedule, Resolution 26-29, item 62. Required for projects where public improvements are potentially affected.
$5,000.00
Geologic Hazard Report Review — Commercial Development, Non-Geo Hazard AreaDraper Consolidated Fee Schedule, Resolution 26-29, item 69 (item 68: $10,000.00 if In Geo Hazard Area). Applicant pays actual direct costs deducted from this deposit; excess is refunded.
$1,000.00
Re-inspection FeeDraper Consolidated Fee Schedule, Resolution 26-29, item 56
$85.00 per inspection

Review timeline

Plan review
Not published — contact the department

How long did your Commercial Building Permit permit actually take in Draper?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    Foundation / Footing

    Before concrete pour — verify excavation, forms, rebar, and anchor bolts

  2. 2

    Underground / Rough-In (MEP)

    Before backfill and before closing walls or ceilings

  3. 3

    Framing

    After framing, sheathing, and rough-in mechanical/electrical/plumbing — before insulation or wall cover

  4. 4

    Fire Sprinkler / Fire Alarm

    Included in the Fire Department's Commercial Fire Sprinkler/Alarm System Plan Review fee (3 inspections included in the base fee)

  5. 5

    Final

    All work complete — certificate of occupancy issued upon passing

See the full Draper inspection guide — scheduling & re-inspection fees →

Tips

  • Draper does not have a separate commercial fee table — the same ICC Building Valuation Data formula and $500 deposit apply to commercial as to residential permits; only the impact fees, geotechnical requirement, and fire sprinkler/alarm fees differ.
  • Commercial development is subject to Fire, Police, and Transportation Facilities Impact Fees calculated per 1,000 sq ft of gross lease area, in addition to the building permit fee — budget these separately.
  • A geotechnical engineering report must be reviewed and approved by Draper City before the city will even accept a commercial building permit application — start this process early.
  • Commercial fire sprinkler and alarm system plan reviews are billed by the Fire Department separately from the Building Division's permit fee.

Frequently asked questions

Draper requires a commercial building permit for: New commercial building construction, addition, or structural alteration; Complete architectural and structural drawings, unlocked (not password-protected) digital files; Geotechnical engineering report reviewed, approved, and accepted by Draper City — required before the application will be accepted; Energy code compliance documentation (COMcheck or equivalent) for the adopted commercial IECC; Fire sprinkler and/or fire alarm system plans where required by the adopted IBC/IFC. If your project isn't listed, confirm with Draper City Building Division at (801) 576-6399 before starting work.

Draper charges the same formula for commercial as residential: 100% of the ICC Building Valuation Data schedule based on project valuation, plus a 65% plan review fee, with a $500 deposit due at application. There is no separate flat commercial fee table.

Draper does not publish a plan-review timeline for this permit. Contact Draper City Building Division at (801) 576-6399 for current turnaround.

You'll need: Building Permit Application; Construction Plans; Geotechnical Engineering Report; Energy Code Compliance Documentation. Depending on your project, Draper may also ask for: Fire Sprinkler / Fire Alarm System Plans. See the required-documents checklist on this page for details on each.

Draper requires 5 inspection(s) for a commercial building permit, in order: Foundation / Footing, Underground / Rough-In (MEP), Framing, Fire Sprinkler / Fire Alarm, Final. Schedule each through Draper City Building Division ((801) 576-6399).

Apply through Draper City Building Division at 1020 E. Pioneer Rd., Draper, UT 84020. Phone: (801) 576-6399, email: building@draperutah.gov. Office hours: Mon–Fri 8:00 AM – 5:00 PM. Official information: https://www.draperutah.gov/business-development/building-and-renovating/.

Draper, Utah has adopted: 2024 International Building Code (IBC), including Appendices C and J — Utah Code § 15A-2-103(1)(a); effective 2026-07-01, superseded the 2021 edition; 2021 International Residential Code (IRC) — Utah Code § 15A-2-103(1)(b); unaffected by the 7/1/2026 statute revision, continues in force; 2024 International Plumbing Code (IPC) — Utah Code § 15A-2-103(1)(d); effective 2026-07-01, superseded the 2021 edition; 2024 International Mechanical Code (IMC) — Utah Code § 15A-2-103(1)(e); effective 2026-07-01, superseded the 2021 edition; 2024 International Fuel Gas Code (IFGC) — Utah Code § 15A-2-103(1)(f); effective 2026-07-01, superseded the 2021 edition; 2023 National Electrical Code (NEC) — Utah Code § 15A-2-103(1)(g); unaffected by the 7/1/2026 statute revision, continues in force; 2024 International Energy Conservation Code (IECC) — Utah Code § 15A-2-103(1)(h); effective 2026-07-01, superseded the 2021 edition; 2024 International Existing Building Code (IEBC) — Utah Code § 15A-2-103(1)(i); effective 2026-07-01, superseded the 2021 edition; 2024 International Swimming Pool and Spa Code (ISPSC), residential provisions — Utah Code § 15A-2-103(1)(n); effective 2026-07-01, superseded the 2021 edition; NOTE: Effective July 1, 2026 (now in force) — 2024 editions of IBC, IPC, IMC, IFGC, IECC, IEBC, and ISPSC replaced the 2021 editions per Utah Code § 15A-2-103 (version effective 7/1/2026, superseded 1/1/2027; text independently re-verified live at le.utah.gov 2026-07-16). The 2021 IRC and 2023 NEC were unaffected by this revision and remain in force..

Yes. Commercial development pays Fire ($97/1,000 sq ft), Police ($130/1,000 sq ft), and Transportation ($3,040/1,000 sq ft gross lease area) Impact Fees at permit issuance, plus separate Fire Department plan review fees for sprinkler and alarm systems, per Draper's Consolidated Fee Schedule (Resolution 26-29).

Sources & verification

Verified against official sources. Last reviewed 2026-07-19.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Draper building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.

This one’s complicated · Get an expediter

Tell us about your project and we’ll connect you with a permit expediter who works in Draper.

PermitBase may receive a referral fee from the expediter. This is a service introduction, not verified permit data or legal advice.