Commercial Building Permit in Unincorporated Emery County, Utah

Required for new commercial construction on unincorporated land in Emery County. The Building Type & Fee Calculation table on the county's own Building Permit Application lists 'Commercial Building' as its own line item, valued the same per-square-foot valuation mechanism as residential building types (no separate commercial multiplier), with the same 65% Plan Check Fee and 80%-of-1% State Surcharge applied uniformly. Commercial plans must be drawn by a certified architect and/or engineer, per the county's Permit Process page.

Reviewed 2026-07-19 · Source

When you need this permit

  • New commercial construction on unincorporated land
  • Zoning clearance/plot plan review by the County Zoning Administrator
  • Plans drawn by a certified architect and/or engineer — per Emery County's Permit Process page: 'Commercial buildings...require an architect/engineer stamp'
  • Road Encroachment Permit from Emery County Road Department or UDOT if the driveway/access crosses a county or state road
  • Health Department approval of septic system/drain field (Southeast Utah Health Department) where no sewer connection exists, or Letter of Intent for sewer hookup
  • Outside city limits, the same underlying 10-acre minimum lot / qualifying 2-acre minor-subdivision threshold and Building Permit Point System worksheet requirements documented for the Residential Building Permit are listed as general application checklist items — the county's materials do not explicitly state whether commercial projects are exempt from the point system (it is written in residential terms: dwelling size, culinary water, etc.); confirm applicability with the Zoning Administrator before applying

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 4 required documents checked.

This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29

Fee schedule

Base Building Permit Fee — Commercial BuildingEmery County Building Permit Application (Building Type & Fee Calculation table) lists 'Commercial Building' as its own row, using the same per-square-foot mechanism (Sq Ft Area x Sq Ft Value) as all other building types on the form. No separate commercial dollar-per-square-foot rate distinct from the form's general ICBO 1997 UBC methodology was independently confirmed in this review — the underlying PDF's fee table is form-field/scanned content that could not be fully machine-verified; treat this fee structure as consistent with, but not pixel-verified against, the residential entry's already-confirmed base fee formula.
Valuation-based, per square foot value assigned to the 'Commercial Building' line on the Building Type & Fee Calculation table, using the ICBO 1997 Uniform Building Code (UBC) valuation/fee schedule
Minimum Permit FeeEmery County Permit Process page: 'Fees: Minimum $50, calculated per square foot using ICBO 1997 UBC guidelines' — applies to all building types including commercial.
$50
Plan Check FeeEmery County Building Permit Application, Office Use Only section: '+Plan Check Fee (Base x .65)' — a flat rate applied uniformly across building types on the form, not a commercial-specific rate.
65% of Base Building Permit Fee
State SurchargeEmery County Building Permit Application, Office Use Only section.
80% of 1% of the (Base + Plan Check) subtotal

Review timeline

Plan review
Not published — contact the department

How long did your Commercial Building Permit permit actually take in Unincorporated Emery County?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    Sub-Rough (Footings, Foundation, Electrical, Mechanical, Plumbing)

    Before concrete pour and before rough work is covered.

  2. 2

    Rough (Building, Electrical, Mechanical, Plumbing, Weather Barrier, Bond Beam, Block Building)

    After framing and rough-in MEP, before drywall/wall cover.

  3. 3

    Final (Building, Electrical, Mechanical, Plumbing, Grading)

    All work complete; occupancy is prohibited until after final inspection and Certificate of Occupancy is issued.

See the full Unincorporated Emery County inspection guide — scheduling & re-inspection fees →

Tips

  • Emery County requires a certified architect and/or engineer stamp on ALL commercial building plans — an unconditional requirement, unlike residential where a stamp is only required for unconventional construction (log, metal frame) per the county's Permit Process page.
  • Inspections are scheduled through Sunrise Engineering (1-800-560-6151, ask for Katrina), which the county contracts for inspection services — a minimum of 24 business hours' notice is required.
  • It is not explicitly published whether Emery County's outside-city-limits 10-acre minimum lot rule and 1000-point Building Permit Point System (both written in residential/dwelling terms) apply to commercial projects — confirm directly with the Zoning Administrator before assuming either does or doesn't apply to a commercial site.
  • For inside-city-limits commercial construction (Castle Dale, Clawson, Cleveland, Elmo, Emery, Ferron, Green River, Huntington, Orangeville), contact the respective city hall — this file covers unincorporated land only.

Frequently asked questions

Unincorporated Emery County requires a commercial building permit for: New commercial construction on unincorporated land; Zoning clearance/plot plan review by the County Zoning Administrator; Plans drawn by a certified architect and/or engineer — per Emery County's Permit Process page: 'Commercial buildings...require an architect/engineer stamp'; Road Encroachment Permit from Emery County Road Department or UDOT if the driveway/access crosses a county or state road; Health Department approval of septic system/drain field (Southeast Utah Health Department) where no sewer connection exists, or Letter of Intent for sewer hookup; Outside city limits, the same underlying 10-acre minimum lot / qualifying 2-acre minor-subdivision threshold and Building Permit Point System worksheet requirements documented for the Residential Building Permit are listed as general application checklist items — the county's materials do not explicitly state whether commercial projects are exempt from the point system (it is written in residential terms: dwelling size, culinary water, etc.); confirm applicability with the Zoning Administrator before applying. If your project isn't listed, confirm with Emery County Building & Zoning Department at (435) 381-3555 before starting work.

Emery County uses the same per-square-foot valuation mechanism (ICBO 1997 Uniform Building Code fee schedule) for a 'Commercial Building' line item as it does for residential building types, with a $50 minimum fee, a 65% Plan Check Fee, and an 80%-of-1% State Surcharge. Contact the Building & Zoning Office at (435) 381-3555 for a project-specific estimate.

Unincorporated Emery County does not publish a plan-review timeline for this permit. Contact Emery County Building & Zoning Department at (435) 381-3555 for current turnaround.

You'll need: Building Permit Application (Building Type & Fee Calculation table); Outside City Limits Building Permit Checklist; Complete Construction Plans (PDF), Architect/Engineer Stamped; Letter of Intent for Water/Sewer Hookup. See the required-documents checklist on this page for details on each.

Unincorporated Emery County requires 3 inspection(s) for a commercial building permit, in order: Sub-Rough (Footings, Foundation, Electrical, Mechanical, Plumbing), Rough (Building, Electrical, Mechanical, Plumbing, Weather Barrier, Bond Beam, Block Building), Final (Building, Electrical, Mechanical, Plumbing, Grading). Schedule each through Emery County Building & Zoning Department ((435) 381-3555).

Apply through Emery County Building & Zoning Department at 75 East Main St, Room 106, PO Box 417, Castle Dale, UT 84513. Phone: (435) 381-3555, email: building@emery.utah.gov. Office hours: Mon–Fri 8:30 AM – 5:00 PM, except county holidays. Official information: https://emery.utah.gov/home/department-directory/bz/.

Unincorporated Emery County, Utah has adopted: 2021 International Residential Code (IRC), plus Appendix AQ of the 2021 IRC — Emery County Building & Zoning, with State of Utah Amendments — Utah Code § 15A-2-103(1)(b)/(c); unchanged by the July 1, 2026 revision — still the current edition; 2024 International Building Code (IBC), including Appendices C and J — Emery County Building & Zoning, with State of Utah Amendments — Utah Code § 15A-2-103(1)(a); current edition as of July 1, 2026 (2021 edition governed through June 30, 2026); 2024 International Plumbing Code (IPC) — Emery County Building & Zoning, with State of Utah Amendments — Utah Code § 15A-2-103(1)(d); current edition as of July 1, 2026 (2021 edition governed through June 30, 2026); 2024 International Mechanical Code (IMC) — Emery County Building & Zoning, with State of Utah Amendments — Utah Code § 15A-2-103(1)(e); current edition as of July 1, 2026 (2021 edition governed through June 30, 2026); 2020 National Electrical Code (NEC), as listed on the Emery County Building Permit Requirements page — NOTE: Utah Code § 15A-2-103(1)(g) sets the 2023 NEC as the statewide in-force edition, unchanged by the July 1, 2026 revision; the county page has not been updated to reflect the statewide 2023 adoption (same discrepancy documented in the Cache County file for this corpus).; 2024 International Fuel Gas Code (IFGC) — Emery County Building & Zoning, with State of Utah Amendments — Utah Code § 15A-2-103(1)(f); current edition as of July 1, 2026 (2021 edition governed through June 30, 2026); 2024 International Energy Conservation Code (IECC) — Emery County Building & Zoning, with State of Utah Amendments — Utah Code § 15A-2-103(1)(h); current edition as of July 1, 2026 (2021 edition governed through June 30, 2026); statute has no residential/commercial split — one edition applies to both; 2024 International Existing Building Code (IEBC) — Emery County Building & Zoning, with State of Utah Amendments — Utah Code § 15A-2-103(1)(i); current edition as of July 1, 2026 (2021 edition governed through June 30, 2026); 2024 International Swimming Pool and Spa Code (ISPSC), residential provisions — Utah Code § 15A-2-103(1)(n). ADDED 2026-07-16: this code is not listed on Emery County's own building-code pages, but it is adopted statewide by statute, so it applies here regardless of the county page's omission.; Utah Wildland Urban Interface Code — Emery County Building & Zoning; COUNTY-PAGE LAG (live-checked 2026-07-16): the Emery County Building Permit Requirements page (emery.utah.gov/home/department-directory/bz/building-permit/) still lists '2021' for IBC, IPC, IMC, IFGC, IECC, and IEBC (plus '2020' for NEC, noted above) — the page has not been updated for the July 1, 2026 statewide flip to 2024 editions. The 2024 editions and 2023 NEC listed in this array are the legally in-force editions per Utah Code § 15A-2-103, not the county page.; NOTE (verified 2026-07-16 against the live Utah Code § 15A-2-103 text, version headed 'Effective 7/1/2026 / Superseded 1/1/2027'): the 2024 editions of IBC, IPC, IMC, IFGC, IECC, and IEBC listed above took effect July 1, 2026, replacing the 2021 editions; IRC (2021) and NEC (2023, per statute — see county-page discrepancy note above) did not change. The 1/1/2027 version of the statute carries identical editions, so no further flip is expected then. This file previously forecast this change but still led with the 2021 editions as current — corrected on this date.. Local amendments apply — see the Unincorporated Emery County overview page for the full list.

Yes. Per Emery County's Permit Process page, commercial buildings require plans drawn by a certified architect and/or engineer — this is a hard requirement, unlike residential permits where a stamp is only conditionally triggered for unconventional construction types.

Sources & verification

Key facts verified against official sources. Last reviewed 2026-07-19.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Unincorporated Emery County building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.

This one’s complicated · Get an expediter

Tell us about your project and we’ll connect you with a permit expediter who works in Unincorporated Emery County.