This is PermitBase’s published record for Unincorporated Millard County as of 2026-07-20. It has since been superseded — see the current record. A historical record reflects what PermitBase had verified at that time; it may not capture a real-world change the jurisdiction had made but PermitBase had not yet verified, and it includes any errors we later corrected. Snapshots are never edited retroactively.
Unincorporated Millard County building permits
VerifiedUnincorporated Millard County, Utah — as published 2026-07-20.
Verified 2026-07-08 · Source
Codes adopted
Permit types & fees
Residential Building Permit
VerifiedRequired for new residential construction, additions, and structural alterations in unincorporated Millard County. Millard County Building Department (Building Official Adam Richins) issues permits for the unincorporated county and, per a 2020 interlocal arrangement, performs building inspections for Delta City (Delta City Council voted to hire the county for inspections in March 2020, ending its contract with Sunrise Engineering). Fillmore City is NOT covered — Fillmore continues to contract with Sunrise Engineering as of the sources checked.
Verified 2026-07-08 · Source
Requirements
- New single-family dwelling construction
- Additions to existing residential structures
- Any structural modification, alteration, repair, move, demolition, or occupancy change (UCA 17-27a-802)
- All residential dwellings in the unincorporated parts of the County require a Conditional Use Permit recorded with the deed, per Millard County Building Department policy (protection of the agriculture industry in Millard County)
- Residential structures with 2,500+ sq ft on the main floor and more than one story require construction documents stamped by a licensed structural engineer and/or architect
- Certified water source capable of delivering minimum 40 psi (Millard County Code 5-2-5; 2009 IRC P2903.3)
- Minimum electrical service capable of delivering 100 amps continuously (2009 IRC E3602.1)
Required documents
- RequiredBuilding Permit Pre-Application WorksheetMillard County Building Permit Pre-Application Worksheet — applicant, owner, contractor, and project information
- RequiredTwo Complete Sets of Plans (1/4-inch to foot scale, min. 11x17)Accurate detailed drawings per the Residential Plan and Permit Acceptance Policy: plot plan, footing/foundation plan, basement plan, main/upper floor plans, elevations, wall sections, floor framing plan, roof/truss framing plan, window/door schedule, stairway sections, handrail/guardrail details, plumbing plan, electrical plan, HVAC/water heater details. Two sets required.
- RequiredLegal Description & Plat MapComplete legal description of the property, obtained from deed or Millard County Recorder's office
- RequiredZoning DesignationObtained from the zoning administrator of the jurisdiction the site is located in
- OptionalSeptic/Sewer ApprovalIf public sewer is not available, a waste water permit from the Central Utah Public Health Department is required before a building permit can be issued
- OptionalOwner/Builder AgreementRequired if the owner will act as general contractor on their own residence — must be signed and notarized
- OptionalEncroachment Permit from Millard County Road DepartmentRequired if the project needs to encroach on a public road or highway for site access
Fee schedule
| Fee type | Amount | Notes |
|---|---|---|
| Demolition Permit (as reference point for county-published flat fees) | $25.00 + 1% state surcharge ($0.25) = $25.25 total | Millard County Demolition Application/Permit form (millardcounty.gov). Listed for reference only — see requirements note below on the residential valuation-based fee. |
Electrical / Mechanical / Plumbing / Stucco Permit
VerifiedRequired for electrical, mechanical, plumbing, and stucco work in unincorporated Millard County, per the county's combined Electrical/Mechanical/Plumbing/Stucco permit application form. EV charger/EVSE installation is electrical work and falls under this general Electrical permit line; Millard County's permit application form does not publish a separate EV-specific fee item.
Verified 2026-07-08 · Source
Requirements
- Electrical work (residential or commercial/pivot)
- Mechanical (HVAC) installation or replacement
- Plumbing installation or alteration
- Stucco application (including after-the-fact stucco permits)
Required documents
- RequiredMillard County Building Permit Application — Electrical/Mechanical/Plumbing/StuccoSingle combined application form listing permit type, building address, contractor or owner information, and project description
- OptionalContractor License NumberValid Utah contractor license (Utah DOPL) if not performed by the homeowner
Fee schedule
| Fee type | Amount | Notes |
|---|---|---|
| Electrical Permit (Residential) | $45.00 | Millard County Building Permit Application — Electrical/Mechanical/Plumbing/Stucco form (millardcounty.gov) |
| Electrical Permit (Commercial or Pivot) | $75.00 | Millard County Building Permit Application — Electrical/Mechanical/Plumbing/Stucco form |
| Mechanical Permit | $45.00 | Millard County Building Permit Application — Electrical/Mechanical/Plumbing/Stucco form |
| Plumbing Permit | $45.00 | Millard County Building Permit Application — Electrical/Mechanical/Plumbing/Stucco form |
| Stucco Permit | $75.00 | Millard County Building Permit Application — Electrical/Mechanical/Plumbing/Stucco form |
| Stucco Permit (After the Fact) | $100.00 | Millard County Building Permit Application — Electrical/Mechanical/Plumbing/Stucco form; charged when stucco was applied before a permit was obtained |
Demolition Permit
VerifiedRequired for demolition of any structure in unincorporated Millard County. Homeowner-performed demolition is regulated by the county (not State Air Quality, which only regulates contractors) for asbestos determination purposes.
Verified 2026-07-08 · Source
Requirements
- Complete demolition of any structure
- Utilities must be disconnected before demolition begins
- Water and sewer lines must be located and terminated before demolition
- Asbestos determination required — contractor or homeowner is responsible for determining if asbestos is present
- All debris including foundation must be removed and holes filled by the completion date, with a final inspection scheduled
Required documents
- RequiredMillard County Demolition Application/PermitApplicant, owner, and contractor information; schedule of demolition (start/completion date); signature required
- OptionalState Air Quality Demolition PermitRequired from Utah Division of Air Quality for contractor-performed demolition (contact 801-536-4000); not required for owner-performed demolition, but asbestos determination still applies
- OptionalAsbestos Removal ReportIf structure contains asbestos, a copy of the report from an approved asbestos removal company must be submitted to the County within 48 hours of removal. No demolition work can commence before the County reviews this report and approves by issuing the demolition permit.
Fee schedule
| Fee type | Amount | Notes |
|---|---|---|
| Demolition Permit | $25.00 | Millard County Demolition Application/Permit form |
| State Surcharge | 1% of permit fee ($0.25 on the $25 base fee) | Millard County Demolition Application/Permit form — listed as a line item on the form ($25.25 total) |
Commercial Building Permit
Required for new commercial construction in unincorporated Millard County, regulated by the statewide-adopted 2024 IBC (Utah Code § 15A-2-103(1)(a), effective July 1, 2026). Millard County Building Department (Building Official Adam Richins) does not publish a distinct commercial building permit page, application form, or valuation-based fee schedule separate from the general process documented on this file's Residential Building Permit entry — an exhaustive search of the county website, all linked Building Forms PDFs, and the county's 2026 Adopted Budget found no published, dedicated commercial fee schedule, mirroring the same finding already documented for residential permits in this file.
Reviewed 2026-07-19 · Source
Requirements
- New commercial construction in unincorporated Millard County
- Any structural modification, alteration, repair, move, demolition, or occupancy change of a commercial structure (UCA 17-27a-802)
- Certified water source and adequate electrical service, consistent with the general building-permit conditions documented for residential permits in this county
- All contractors/subcontractors must hold a current Utah State Contractor's license
Required documents
- RequiredBuilding Permit Pre-Application WorksheetSame worksheet used for residential permits — applicant, owner, contractor, and project information; no separate commercial-specific worksheet was located as of 2026-07-19.
- RequiredConstruction Plans and SpecificationsPlans appropriate to commercial occupancy classification (structural, electrical, mechanical, plumbing, energy code compliance); no dedicated commercial submittal checklist distinct from the residential one documented in this file was located online as of 2026-07-19.
- RequiredLegal Description & Plat MapComplete legal description of the property, obtained from deed or Millard County Recorder's office.
- RequiredZoning DesignationObtained from the zoning administrator of the jurisdiction the site is located in.
- OptionalEncroachment Permit from Millard County Road DepartmentRequired if the project needs to encroach on a public road or highway for site access.
Fee schedule
| Fee type | Amount | Notes |
|---|---|---|
| Building Permit Fee | Not published — no dedicated commercial or general valuation-based fee schedule was located on millardcounty.gov, in any linked Building Forms PDF, or in the county's 2026 Adopted Budget as of 2026-07-19 | This mirrors the identical finding already documented on this file's Residential Building Permit entry: 'No published, dedicated valuation-based fee schedule for the primary Residential Building Permit ... Show full citationHideThis mirrors the identical finding already documented on this file's Residential Building Permit entry: 'No published, dedicated valuation-based fee schedule for the primary Residential Building Permit ... could be located despite exhausting the county website, all linked building-department PDFs, the county's 2026 Adopted Budget and Department Expenditures summary, and web/targeted search.' The same conclusion applies to commercial construction — only flat fees for demolition and electrical/mechanical/plumbing/stucco permits are published countywide. Contact the Building Official (435-864-1400) directly for a project-specific commercial fee quote. |
| Demolition Permit (as reference point for county-published flat fees) | $25.00 + 1% state surcharge ($0.25) = $25.25 total | Millard County Demolition Application/Permit form (millardcounty.gov) — same flat fee applies to demolition of commercial or residential structures; listed for reference only. |
| Electrical Permit (Commercial or Pivot) | $75.00 | Millard County Building Permit Application — Electrical/Mechanical/Plumbing/Stucco form; Show full citationHideMillard County Building Permit Application — Electrical/Mechanical/Plumbing/Stucco form; the county's published fee schedule distinguishes a higher 'Commercial or Pivot' electrical rate ($75) from the residential rate ($45), documented on this file's Electrical/Mechanical/Plumbing/Stucco Permit entry — this is the ONE place the county's published fees do split by commercial vs. residential use. |
Commercial Tenant Improvement / Tenant Finish Permit
Required for tenant improvement and tenant finish work in existing commercial buildings in unincorporated Millard County. No dedicated tenant-improvement permit type, application, checklist, or fee is published by Millard County Building Department — an exhaustive search of the county website and all linked Building Forms PDFs found no tenant-improvement-specific materials, consistent with the same gap documented for the county's Commercial Building Permit entry.
Reviewed 2026-07-19 · Source
Requirements
- Tenant improvement or tenant finish work in an existing commercial building within unincorporated Millard County
- Any structural modification, alteration, repair, or occupancy change of a commercial structure (UCA 17-27a-802)
- All contractors/subcontractors must hold a current Utah State Contractor's license
Required documents
- RequiredBuilding Permit Pre-Application WorksheetSame general worksheet used for all other Millard County building permit types — no dedicated tenant-improvement application was located as of 2026-07-19.
- RequiredConstruction Plans (Tenant Space Scope)Plans showing the scope of tenant-space work; no dedicated tenant-improvement submittal checklist was located online as of 2026-07-19.
Fee schedule
| Fee type | Amount | Notes |
|---|---|---|
| Building Permit Fee | Not published — no tenant-improvement-specific or general commercial fee schedule was located on millardcounty.gov as of 2026-07-19 | Same gap documented on this file's Commercial Building Permit entry. Contact the Building Official (435-864-1400) directly for a project-specific fee quote. |
| Electrical Permit (Commercial or Pivot, where applicable to TI scope) | $75.00 | Millard County Building Permit Application — Electrical/Mechanical/Plumbing/Stucco form, if the tenant improvement scope includes standalone electrical work billed separately from a general building permit. |
Permitted Use Permit (P-1 / P-2) — Change or Establishment of Land Use
VerifiedMillard County requires a Permitted Use Permit before a use may be established or changed on a property in unincorporated Millard County — including changing a building's occupancy/use without new construction (e.g., a use that differs from the property's prior permitted use). Per the P-1 application form itself: 'Only when the county planner/zoning administrator has approved the permitted P-1 use... and a building permit issued, as required, may any building, activity, construction, or occupancy be commenced.' Reviewed under Millard County Code Title 10, Chapter 8. Uses permitted outright in a zoning district go through the lower-tier P-1 process (reviewed administratively by the County Planner/Zoning Administrator); uses requiring more scrutiny go through the P-2 Conditional Use Permit process. This is a zoning-authority use-permitting mechanism, distinct from and required in addition to any building permit.
Verified 2026-07-20 · Source
Requirements
- Property owner(s) of record (or an authorized agent with a signed affidavit) must submit the application
- Proposed use must be a P-1 permitted use within the zoning district per Millard County Code Title 10, Section 10-25-1, Appendix A, Table of Uses (or a P-2 conditional use if the district's table designates it as such)
- Site plan (up to 11" x 17") showing building/use locations, natural features, setbacks, streets, and easements
- County Recorder's plat map(s) showing the subject property and all adjoining properties within 300 feet
- List of names and mailing addresses of property owners within 300 feet of the subject property
- Written permission from any lienholders, mortgage companies, or other parties with a material interest in the property, if different from the applicant
- A building permit must still be obtained separately, as required, before any building, activity, construction, or occupancy commences
Required documents
- RequiredP-1 Permitted Use ApplicationMillard County Planning and Zoning's application form for a P-1 permitted use or P-1 permitted sign, last updated 4/5/2017.
- OptionalP-2 Permitted Use ApplicationUsed instead of the P-1 form when the proposed use is designated a conditional (P-2) use rather than an outright-permitted use in the applicable zoning district, per Millard County Planning and Zoning's forms page.
- OptionalOwner/Agent AgreementRequired if the application is signed by an agent rather than the property owner of record; must be notarized.
Fee schedule
| Fee type | Amount | Notes |
|---|---|---|
| P-1 Permitted Use Permit — Commercial | $85.00 (After the Fact: $170.00) | Millard County Land Use Fee Schedule, Planning and Zoning Department (millardcounty.gov/wp-content/uploads/departments/planning-zoning/pz-docs/land-use-fee-schedule-2009.pdf). |
| P-1 Permitted Use Permit — Residential Home Occupation (Major) | $40.00 | Millard County Land Use Fee Schedule. |
| P-1 Permitted Use Permit — Residential Home Occupation (Minor) | $20.00 | Millard County Land Use Fee Schedule. |
| P-1 Permitted Use Permit — Residential Dwelling | $20.00 | Millard County Land Use Fee Schedule. |
| P-2 Permitted Use Permit (Conditional Use) | $130.00 (After the Fact: $260.00) | Millard County Land Use Fee Schedule; also confirmed as '$130.00' fee-collected line printed directly on the P-2 Permitted Use Application form itself. |
Sign Permit (P-1/P-2/C-1 depending on sign type)
VerifiedRequired for signs in unincorporated Millard County under Millard County Code Title 10, Chapter 9 (Sign Standards). Re-chased 2026-07-20: the full text of MCC 10-9-1 through 10-9-21 was located and read via the county's amlegal.com code library (a prior pass only had the P-1 application form and fee schedule, and assumed all signs used the P-1/administrator process). Table 10-9-2 (Allowed Signs) shows this is NOT correct for the most common commercial sign types — freestanding pylon and monument signs are actually Conditional C-1 signs decided by the Commission, and wall signs are Permitted P-2 signs also decided by the Commission; only canopy signs go through the P-1/county-planner process the prior entry described. Small on-premises signs, freestanding directional signs, and temporary signs (≤64 sq ft, ≤12 months) require no land use authority approval at all.
Verified 2026-07-20 · Source
Requirements
- Per MCC 10-9-17, Table 10-9-2 (Allowed Signs), the required application type depends on sign type: freestanding PYLON and freestanding MONUMENT signs are Conditional C-1 signs decided by the Commission; WALL signs are Permitted P-2 signs also decided by the Commission; CANOPY signs are Permitted P-1 signs decided by the county planner/zoning administrator — MCC 10-9-12
- Small on-premises signs, freestanding directional signs, and temporary signs (up to 12 months) are allowed in all zones WITHOUT any land use authority approval, provided all standards in Table 10-9-2 are met (no part within 5 ft of any road/street ROW, property line, or utility easement; must maintain clear-view-area and fire-appliance-access requirements) — MCC 10-9-17
- A separate table of exempt signs (MCC 10-9-3, Table 10-9-1) needs no permit or fee at all: access location signs (max 2 per driveway, 6 sq ft, 3 ft height), community event posters/fliers, flags, historic plaques, official government notices, and on-premises temporary signs up to 64 sq ft for up to 12 months — provided the sign is not also a prohibited sign under MCC 10-9-4
- Maximum sign area for a freestanding PYLON sign scales with lot frontage: 80 sq ft under 140 ft frontage, up to 140 sq ft at 260+ ft frontage (MCC Table 10-9-3); max height 25 ft above grade
- Maximum sign area for a freestanding MONUMENT sign scales with lot frontage on the same 80-140 sq ft schedule (MCC Table 10-9-4); max height 8 ft above grade
- Maximum WALL sign area scales with the building wall area on the same 80-140 sq ft schedule (MCC Table 10-9-5); may not project above the wall's eave line or parapet, max 2 wall signs per building (only on walls facing a public road/street)
- CANOPY signs: max 40% of the canopy's total area, no higher than the canopy itself, max 2 per canopy (only on sides facing a public road/street) — MCC 10-9-17
- No part of any sign may be within 5 feet of any road/street right-of-way or utility easement; signs may not interfere with fire protection appliances/fire lanes or be located in a clear-view area — MCC 10-9-5
- A valid building permit must be issued (separate from the sign land-use application) before any sign is erected, moved, reconstructed, enlarged, or structurally altered — MCC 10-9-6
- All businesses/services advertised on a sign must maintain a valid Millard County business license — MCC 10-9-9
- All persons with a fee interest in the subject property must join in and sign the application; the sign must be authorized by the property owner — MCC 10-9-2
Required documents
- OptionalP-1 Permitted Use/Sign Application (canopy signs only)Used for canopy signs, reviewed by the county planner/zoning administrator per MCC 10-9-12(A). The applicant checks 'P-1 Sign' in the case-number box at the top of the form.
- OptionalP-2 / C-1 Application (wall, pylon, and monument signs)Wall signs use the P-2 Permitted Use process; freestanding pylon and monument signs use the C-1 Conditional Use process — both decided by the Commission per MCC 10-9-12(B), following the same procedures as a P-2 use application or C-1 use application respectively (MCC 10-9-13).
- RequiredSite PlanDrawn to scale and of sufficient size to show the proposed sign's location, dimensions, and relationship to property lines and existing structures.
- OptionalOwner/Agent Agreement (notarized)Required only if the application is signed by an agent rather than the property owner of record.
- RequiredBuilding Permit ApplicationRequired separately, after the applicable sign land-use approval, before construction may begin — MCC 10-9-6.
Fee schedule
| Fee type | Amount | Notes |
|---|---|---|
| P-1 Permitted Use Permit — Commercial (canopy signs) | $85.00 (After the Fact $170.00) | Millard County Land Use Fee Schedule (Millard County Planning and Zoning Department; Show full citationHideMillard County Land Use Fee Schedule (Millard County Planning and Zoning Department; Word-generated PDF, creation date 3/10/2016, confirmed as the current version linked from the department's live PC Forms page as of 2026-07-20, visually re-verified against a fresh render of page 1), 'CONDITIONAL USE PERMIT FEES' table. Per MCC 10-9-17 Table 10-9-2, the P-1 process applies specifically to canopy signs (the only sign type reviewed by the county planner/zoning administrator). |
| Residential Dwelling P-1 Permitted Use Permit | $20.00 | Same fee schedule, same table. |
| P-2 Permitted Use Permit (wall signs) | $130.00 (After the Fact $260.00) | Same fee schedule. Per MCC 10-9-17 Table 10-9-2, wall signs are Permitted P-2 signs decided by the Commission (not the P-1 administrator process) — this fee, not the P-1 fee, is the correct governing figure for a wall sign. |
| C-1 Conditional Use Permit (freestanding pylon and monument signs) | $165.00 (After the Fact $330.00) | Same fee schedule. Per MCC 10-9-17 Table 10-9-2, freestanding pylon signs and freestanding monument signs are Conditional C-1 signs decided by the Commission — this fee, not the P-1 fee, is the… Show full citationHideSame fee schedule. Per MCC 10-9-17 Table 10-9-2, freestanding pylon signs and freestanding monument signs are Conditional C-1 signs decided by the Commission — this fee, not the P-1 fee, is the correct governing figure for these sign types, which are the most common commercial freestanding sign format. |
| Small On-Premises / Freestanding Directional / Temporary Signs | No fee — no land use authority approval required | MCC 10-9-17, Table 10-9-2: these three sign types are allowed in all zones without land use authority approval provided all standards and requirements are met. A building permit may still be required per MCC 10-9-6 depending on construction scope. |
EV Charger / EVSE Permit
VerifiedMillard County does not publish a distinct EV charger, EVSE, or electric vehicle charging station permit or fee. EV charger/EVSE installation is electrical work and falls under the county's combined Electrical/Mechanical/Plumbing/Stucco permit application, at the $45 residential (or $75 commercial/pivot) Electrical line item. The county's permit application form does not publish a separate EV-specific fee item.
Verified 2026-07-20 · Source
Requirements
- Installation of a Level 2 or DC fast EV charger (EVSE) at a residential or commercial property
- New dedicated electrical circuit and/or panel capacity to serve the charger, covered under the general Electrical line item
- Compliance with the 2023 National Electrical Code (NEC) per Utah Code § 15A-2-103(1)(g)
Required documents
- RequiredMillard County Building Permit Application — Electrical/Mechanical/Plumbing/StuccoSingle combined application form listing permit type, building address, contractor or owner information, and project description
- OptionalContractor License NumberValid Utah contractor license (Utah DOPL) if not performed by the homeowner
Fee schedule
| Fee type | Amount | Notes |
|---|---|---|
| Electrical Permit (Residential) | $45.00 | Millard County Building Permit Application — Electrical/Mechanical/Plumbing/Stucco form (millardcounty.gov). Same line item covers EV charger circuit installation; no distinct EV-specific fee is published. |
| Electrical Permit (Commercial or Pivot) | $75.00 | Millard County Building Permit Application — Electrical/Mechanical/Plumbing/Stucco form |
Sources & verification
Verified against official sources. Last reviewed 2026-07-08.
Fee schedules
Checklists & handouts
Codes & ordinances
Department & other records
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Unincorporated Millard County building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.