This is PermitBase’s published record for Unincorporated Millard County as of 2026-07-19. It has since been superseded — see the current record. A historical record reflects what PermitBase had verified at that time; it may not capture a real-world change the jurisdiction had made but PermitBase had not yet verified, and it includes any errors we later corrected. Snapshots are never edited retroactively.

Unincorporated Millard County building permits

Verified

Unincorporated Millard County, Utah — as published 2026-07-19.

Verified 2026-07-08 · Source

Codes adopted

2021 International Residential Code (IRC) with State of Utah Amendments — per Utah Code § 15A-2-103(1)(b); unchanged by the July 1, 2026 statewide update. Millard County Building Inspection Department page (adopted codes list) also lists 2021 IRC — live-checked 2026-07-16, page unchanged since last check.2024 International Building Code (IBC) with State of Utah Amendments — per Utah Code § 15A-2-103(1)(a), effective since July 1, 2026, superseding the 2021 IBC. NOTE (2026-07-16, live-checked): the Millard County Building Inspection Department page still lists 2021 IBC — the county page is lagging the statewide statutory update by 15+ days; the statute is controlling.2024 International Plumbing Code (IPC) with State of Utah Amendments — per Utah Code § 15A-2-103(1)(d), effective since July 1, 2026, superseding the 2021 IPC. NOTE (2026-07-16, live-checked): the county page still lists 2021 IPC — page lag, statute controls.2024 International Mechanical Code (IMC) with State of Utah Amendments — per Utah Code § 15A-2-103(1)(e), effective since July 1, 2026, superseding the 2021 IMC. NOTE (2026-07-16, live-checked): the county page still lists 2021 IMC — page lag, statute controls.2023 National Electrical Code (NEC) per Utah Code § 15A-2-103(1)(g), statewide in force and NOT changed by the July 1, 2026 update — NOTE: this is a separate, pre-existing discrepancy: Millard County's own Building Inspection page lists 2020 NEC (live-checked again 2026-07-16, page still shows 2020 NEC, unrelated to the 2021→2024 code-edition transition affecting the other codes below). Contractors/homeowners should confirm current applicability with the Building Official as the county page lags the statewide amendment.2024 International Fuel Gas Code (IFGC) with State of Utah Amendments — per Utah Code § 15A-2-103(1)(f), effective since July 1, 2026, superseding the 2021 IFGC. NOTE (2026-07-16, live-checked): the county page still lists 2021 IFGC — page lag, statute controls.2024 International Energy Conservation Code (IECC), Residential & Commercial — per Utah Code § 15A-2-103(1)(h), effective since July 1, 2026, superseding the 2021 IECC. The statute adopts a single IECC edition with no residential/commercial split (this file's existing single combined line already reflects that — no split to collapse). NOTE (2026-07-16, live-checked): the county page still lists 2021 IECC — page lag, statute controls.2024 International Existing Building Code (IEBC) — per Utah Code § 15A-2-103(1)(i), effective since July 1, 2026. Not separately listed on the Millard County Building Inspection Department page (live-checked 2026-07-16, page has no IEBC entry at all) — added here because § 15A-2-103 adopts it statewide regardless of the county page's omission.2024 residential provisions of the International Swimming Pool and Spa Code (ISPSC) — per Utah Code § 15A-2-103(1)(n), effective since July 1, 2026. Not separately listed on the Millard County Building Inspection Department page (live-checked 2026-07-16, page has no ISPSC entry at all) — added here because § 15A-2-103 adopts it statewide regardless of the county page's omission.Utah Wildland Urban Interface CodeNOTE (updated 2026-07-16): The July 1, 2026 statewide code-edition transition (2024 IBC/IPC/IMC/IFGC/IECC replacing 2021 editions, per Utah Code § 15A-2-103 version effective 7/1/2026, superseded 1/1/2027) took effect 15 days ago; the next statute version's editions were diffed and confirmed identical, so this should not go stale again around 1/1/2027. 2021 IRC is unchanged by this transition. The International Fire Code is NOT adopted by § 15A-2-103 (it is addressed separately in Title 15A Chapter 5) and is not otherwise referenced in this file.

Permit types & fees

Residential Building Permit

Verified

Required for new residential construction, additions, and structural alterations in unincorporated Millard County. Millard County Building Department (Building Official Adam Richins) issues permits for the unincorporated county and, per a 2020 interlocal arrangement, performs building inspections for Delta City (Delta City Council voted to hire the county for inspections in March 2020, ending its contract with Sunrise Engineering). Fillmore City is NOT covered — Fillmore continues to contract with Sunrise Engineering as of the sources checked.

Verified 2026-07-08 · Source

Requirements

  • New single-family dwelling construction
  • Additions to existing residential structures
  • Any structural modification, alteration, repair, move, demolition, or occupancy change (UCA 17-27a-802)
  • All residential dwellings in the unincorporated parts of the County require a Conditional Use Permit recorded with the deed, per Millard County Building Department policy (protection of the agriculture industry in Millard County)
  • Residential structures with 2,500+ sq ft on the main floor and more than one story require construction documents stamped by a licensed structural engineer and/or architect
  • Certified water source capable of delivering minimum 40 psi (Millard County Code 5-2-5; 2009 IRC P2903.3)
  • Minimum electrical service capable of delivering 100 amps continuously (2009 IRC E3602.1)

Required documents

  • RequiredBuilding Permit Pre-Application WorksheetMillard County Building Permit Pre-Application Worksheet — applicant, owner, contractor, and project information
  • RequiredTwo Complete Sets of Plans (1/4-inch to foot scale, min. 11x17)Accurate detailed drawings per the Residential Plan and Permit Acceptance Policy: plot plan, footing/foundation plan, basement plan, main/upper floor plans, elevations, wall sections, floor framing plan, roof/truss framing plan, window/door schedule, stairway sections, handrail/guardrail details, plumbing plan, electrical plan, HVAC/water heater details. Two sets required.
  • RequiredLegal Description & Plat MapComplete legal description of the property, obtained from deed or Millard County Recorder's office
  • RequiredZoning DesignationObtained from the zoning administrator of the jurisdiction the site is located in
  • OptionalSeptic/Sewer ApprovalIf public sewer is not available, a waste water permit from the Central Utah Public Health Department is required before a building permit can be issued
  • OptionalOwner/Builder AgreementRequired if the owner will act as general contractor on their own residence — must be signed and notarized
  • OptionalEncroachment Permit from Millard County Road DepartmentRequired if the project needs to encroach on a public road or highway for site access

Fee schedule

Fee typeAmountNotes
Demolition Permit (as reference point for county-published flat fees)$25.00 + 1% state surcharge ($0.25) = $25.25 totalMillard County Demolition Application/Permit form (millardcounty.gov). Listed for reference only — see requirements note below on the residential valuation-based fee.

Electrical / Mechanical / Plumbing / Stucco Permit

Verified

Required for electrical, mechanical, plumbing, and stucco work in unincorporated Millard County, per the county's combined Electrical/Mechanical/Plumbing/Stucco permit application form. EV charger/EVSE installation is electrical work and falls under this general Electrical permit line; Millard County's permit application form does not publish a separate EV-specific fee item.

Verified 2026-07-08 · Source

Requirements

  • Electrical work (residential or commercial/pivot)
  • Mechanical (HVAC) installation or replacement
  • Plumbing installation or alteration
  • Stucco application (including after-the-fact stucco permits)

Required documents

  • RequiredMillard County Building Permit Application — Electrical/Mechanical/Plumbing/StuccoSingle combined application form listing permit type, building address, contractor or owner information, and project description
  • OptionalContractor License NumberValid Utah contractor license (Utah DOPL) if not performed by the homeowner

Fee schedule

Fee typeAmountNotes
Electrical Permit (Residential)$45.00Millard County Building Permit Application — Electrical/Mechanical/Plumbing/Stucco form (millardcounty.gov)
Electrical Permit (Commercial or Pivot)$75.00Millard County Building Permit Application — Electrical/Mechanical/Plumbing/Stucco form
Mechanical Permit$45.00Millard County Building Permit Application — Electrical/Mechanical/Plumbing/Stucco form
Plumbing Permit$45.00Millard County Building Permit Application — Electrical/Mechanical/Plumbing/Stucco form
Stucco Permit$75.00Millard County Building Permit Application — Electrical/Mechanical/Plumbing/Stucco form
Stucco Permit (After the Fact)$100.00Millard County Building Permit Application — Electrical/Mechanical/Plumbing/Stucco form; charged when stucco was applied before a permit was obtained

Demolition Permit

Verified

Required for demolition of any structure in unincorporated Millard County. Homeowner-performed demolition is regulated by the county (not State Air Quality, which only regulates contractors) for asbestos determination purposes.

Verified 2026-07-08 · Source

Requirements

  • Complete demolition of any structure
  • Utilities must be disconnected before demolition begins
  • Water and sewer lines must be located and terminated before demolition
  • Asbestos determination required — contractor or homeowner is responsible for determining if asbestos is present
  • All debris including foundation must be removed and holes filled by the completion date, with a final inspection scheduled

Required documents

  • RequiredMillard County Demolition Application/PermitApplicant, owner, and contractor information; schedule of demolition (start/completion date); signature required
  • OptionalState Air Quality Demolition PermitRequired from Utah Division of Air Quality for contractor-performed demolition (contact 801-536-4000); not required for owner-performed demolition, but asbestos determination still applies
  • OptionalAsbestos Removal ReportIf structure contains asbestos, a copy of the report from an approved asbestos removal company must be submitted to the County within 48 hours of removal. No demolition work can commence before the County reviews this report and approves by issuing the demolition permit.

Fee schedule

Fee typeAmountNotes
Demolition Permit$25.00Millard County Demolition Application/Permit form
State Surcharge1% of permit fee ($0.25 on the $25 base fee)Millard County Demolition Application/Permit form — listed as a line item on the form ($25.25 total)

Commercial Building Permit

Required for new commercial construction in unincorporated Millard County, regulated by the statewide-adopted 2024 IBC (Utah Code § 15A-2-103(1)(a), effective July 1, 2026). Millard County Building Department (Building Official Adam Richins) does not publish a distinct commercial building permit page, application form, or valuation-based fee schedule separate from the general process documented on this file's Residential Building Permit entry — an exhaustive search of the county website, all linked Building Forms PDFs, and the county's 2026 Adopted Budget found no published, dedicated commercial fee schedule, mirroring the same finding already documented for residential permits in this file.

Reviewed 2026-07-19 · Source

Requirements

  • New commercial construction in unincorporated Millard County
  • Any structural modification, alteration, repair, move, demolition, or occupancy change of a commercial structure (UCA 17-27a-802)
  • Certified water source and adequate electrical service, consistent with the general building-permit conditions documented for residential permits in this county
  • All contractors/subcontractors must hold a current Utah State Contractor's license

Required documents

  • RequiredBuilding Permit Pre-Application WorksheetSame worksheet used for residential permits — applicant, owner, contractor, and project information; no separate commercial-specific worksheet was located as of 2026-07-19.
  • RequiredConstruction Plans and SpecificationsPlans appropriate to commercial occupancy classification (structural, electrical, mechanical, plumbing, energy code compliance); no dedicated commercial submittal checklist distinct from the residential one documented in this file was located online as of 2026-07-19.
  • RequiredLegal Description & Plat MapComplete legal description of the property, obtained from deed or Millard County Recorder's office.
  • RequiredZoning DesignationObtained from the zoning administrator of the jurisdiction the site is located in.
  • OptionalEncroachment Permit from Millard County Road DepartmentRequired if the project needs to encroach on a public road or highway for site access.

Fee schedule

Fee typeAmountNotes
Building Permit FeeNot published — no dedicated commercial or general valuation-based fee schedule was located on millardcounty.gov, in any linked Building Forms PDF, or in the county's 2026 Adopted Budget as of 2026-07-19
This mirrors the identical finding already documented on this file's Residential Building Permit entry: 'No published, dedicated valuation-based fee schedule for the primary Residential Building Permit ... Show full citation

This mirrors the identical finding already documented on this file's Residential Building Permit entry: 'No published, dedicated valuation-based fee schedule for the primary Residential Building Permit ... could be located despite exhausting the county website, all linked building-department PDFs, the county's 2026 Adopted Budget and Department Expenditures summary, and web/targeted search.' The same conclusion applies to commercial construction — only flat fees for demolition and electrical/mechanical/plumbing/stucco permits are published countywide. Contact the Building Official (435-864-1400) directly for a project-specific commercial fee quote.

Demolition Permit (as reference point for county-published flat fees)$25.00 + 1% state surcharge ($0.25) = $25.25 totalMillard County Demolition Application/Permit form (millardcounty.gov) — same flat fee applies to demolition of commercial or residential structures; listed for reference only.
Electrical Permit (Commercial or Pivot)$75.00
Millard County Building Permit Application — Electrical/Mechanical/Plumbing/Stucco form; Show full citation

Millard County Building Permit Application — Electrical/Mechanical/Plumbing/Stucco form; the county's published fee schedule distinguishes a higher 'Commercial or Pivot' electrical rate ($75) from the residential rate ($45), documented on this file's Electrical/Mechanical/Plumbing/Stucco Permit entry — this is the ONE place the county's published fees do split by commercial vs. residential use.

Commercial Tenant Improvement / Tenant Finish Permit

Required for tenant improvement and tenant finish work in existing commercial buildings in unincorporated Millard County. No dedicated tenant-improvement permit type, application, checklist, or fee is published by Millard County Building Department — an exhaustive search of the county website and all linked Building Forms PDFs found no tenant-improvement-specific materials, consistent with the same gap documented for the county's Commercial Building Permit entry.

Reviewed 2026-07-19 · Source

Requirements

  • Tenant improvement or tenant finish work in an existing commercial building within unincorporated Millard County
  • Any structural modification, alteration, repair, or occupancy change of a commercial structure (UCA 17-27a-802)
  • All contractors/subcontractors must hold a current Utah State Contractor's license

Required documents

  • RequiredBuilding Permit Pre-Application WorksheetSame general worksheet used for all other Millard County building permit types — no dedicated tenant-improvement application was located as of 2026-07-19.
  • RequiredConstruction Plans (Tenant Space Scope)Plans showing the scope of tenant-space work; no dedicated tenant-improvement submittal checklist was located online as of 2026-07-19.

Fee schedule

Fee typeAmountNotes
Building Permit FeeNot published — no tenant-improvement-specific or general commercial fee schedule was located on millardcounty.gov as of 2026-07-19Same gap documented on this file's Commercial Building Permit entry. Contact the Building Official (435-864-1400) directly for a project-specific fee quote.
Electrical Permit (Commercial or Pivot, where applicable to TI scope)$75.00Millard County Building Permit Application — Electrical/Mechanical/Plumbing/Stucco form, if the tenant improvement scope includes standalone electrical work billed separately from a general building permit.

Sources & verification

Verified against official sources. Last reviewed 2026-07-08.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Unincorporated Millard County building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.

← Earlier version (2026-07-16)Later version (2026-07-20) →View current record →All versions →

Permalink: /utah/millard-county/unincorporated-millard/as-of/2026-07-19/

Snapshot date: 2026-07-19

Commit: 00bdf0a

Reproducible from PermitBase’s version-controlled dataset, commit 00bdf0a.