This is PermitBase’s published record for Morgan County as of 2026-07-19. It has since been superseded — see the current record. A historical record reflects what PermitBase had verified at that time; it may not capture a real-world change the jurisdiction had made but PermitBase had not yet verified, and it includes any errors we later corrected. Snapshots are never edited retroactively.

Morgan County building permits

Verified

Morgan County, Utah — as published 2026-07-19.

Verified 2026-07-08 · Source

Codes adopted

2024 International Building Code (IBC) — Utah Code § 15A-2-103(1)(a); effective since July 1, 2026, superseding the 2021 IBC2021 International Residential Code (IRC) — Utah Code § 15A-2-103(1)(b); unchanged by the July 1, 2026 statewide update, remains in force2024 International Plumbing Code (IPC) — Utah Code § 15A-2-103(1)(d); effective since July 1, 2026, superseding the 2021 IPC2024 International Mechanical Code (IMC) — Utah Code § 15A-2-103(1)(e); effective since July 1, 2026, superseding the 2021 IMC2024 International Fuel Gas Code (IFGC) — Utah Code § 15A-2-103(1)(f); effective since July 1, 2026, superseding the 2021 IFGC2024 International Energy Conservation Code (IECC) — Utah Code § 15A-2-103(1)(h); effective since July 1, 2026, superseding the 2021 IECC. The statute adopts a single IECC edition with no residential/commercial split.2024 International Existing Building Code (IEBC) — Utah Code § 15A-2-103(1)(i); effective since July 1, 2026, superseding the 2021 IEBC2024 residential provisions of the International Swimming Pool and Spa Code (ISPSC) — Utah Code § 15A-2-103(1)(n); effective since July 1, 2026, superseding the 2021 ISPSC2023 National Electrical Code (NEC) — Utah Code § 15A-2-103(1)(g); statewide in force, unchanged by the July 1, 2026 updateNOTE (updated 2026-07-16): The July 1, 2026 statewide code-edition transition (2024 IBC/IPC/IMC/IFGC/IECC/IEBC/ISPSC replacing 2021 editions) took effect 15 days ago per Utah Code § 15A-2-103 (version effective 7/1/2026, superseded 1/1/2027; next version's editions confirmed identical). 2021 IRC and 2023 NEC are unchanged. Live-checked the Morgan County buildingpermits page today (2026-07-16) — it does not cite specific code edition years at all (references 'Chapter 11 of the IRC' and 'the IECC' generically), so no page-lag discrepancy to flag there. The International Fire Code is NOT adopted by § 15A-2-103 (it lives in Title 15A Chapter 5) and is not referenced elsewhere in this file.

Permit types & fees

Residential Building Permit

Verified

Required for new single-family dwelling construction, multi-family dwellings, home additions/remodels, and manufactured/modular homes throughout Morgan County — including unincorporated county land and Morgan City, both served by the same Morgan County Planning and Development Services department. All applications are submitted through the Civic Review online portal.

Verified 2026-07-08 · Source

Requirements

  • New single-family or multi-family dwelling construction
  • Home additions and remodels
  • Manufactured/modular home installation
  • Non-refundable pre-plan review deposit due at time of application submission
  • Complete digital PDF submission through Civic Review portal (signed/notarized paperwork must be scanned and attached)

Required documents

  • RequiredCivic Review ApplicationAll building permit applications are submitted through the Civic Review online portal (app.civicreview.com). Digital plans as PDFs and all supporting documentation required at submittal.
  • RequiredComplete Set of Building Plans (PDF)Floor plans, elevations, structural details, and MEP plans as applicable to project scope
  • RequiredFire Protection Plan ApprovalForm must be printed and taken to the appropriate fire district for signature: Mountain Green Fire Chief (801-876-2277) for Mountain Green area, or Morgan County Fire Marshal (801-845-4049) for all other areas including Morgan City. Signed approval must be emailed with the application.
  • RequiredPre-Plan Review Deposit PaymentNon-refundable deposit paid to the Morgan County Treasurer's Office (801-845-4030, 48 W Young Street) before review begins

Fee schedule

Fee typeAmountNotes
Single Family Dwelling — Preplan Review Deposit$500.00Morgan County Planning and Development Services — Building Permit Fees and Worksheet (Rev 9-2021). Non-refundable, applied toward actual plan review fees. Verified live at county-hosted PDF 2026-07-08.
Multi-Family Dwelling — Preplan Review Deposit$500.00 + $50 per unitMorgan County Building Permit Fees and Worksheet (Rev 9-2021)
Home Addition/Remodel — Preplan Review Deposit$50.00Morgan County Building Permit Fees and Worksheet (Rev 9-2021)
Manufactured/Modular Home — Preplan Review Deposit$200.00Morgan County Building Permit Fees and Worksheet (Rev 9-2021)
Manufactured/Modular Home Addition/Remodel — Preplan Review Deposit$100.00Morgan County Building Permit Fees and Worksheet (Rev 9-2021)
Remaining Building Permit Fee (post-deposit)Approx. 1-2% of total project valuation (labor + materials), calculated per valuation breakdown; plus 1% State fee; plus applicable impact feesMorgan County Building Permit Fees and Worksheet (Rev 9-2021). Example given in the document: $300,000 valuation project = ~$3,000 permit/review/State fee + $1,319.57 impact fee = $4,319.57 total.
Minimum Building Permit Fee$100.00Morgan County Building Permit Fees and Worksheet (Rev 9-2021), amending CR-07-06 Exhibit B Base Fee Schedule
County Impact Fees (Transportation + Regional Park + Community Park)$1,319.57 total ($348.57 Transportation + $485.50 Regional Park + $485.50 Community Park)Morgan County Building Permit Fees and Worksheet (Rev 9-2021)
Performance Bond (public infrastructure) — New residential/commercial/industrial$2,500 or $15 per linear foot of frontage, whichever is greaterMorgan County Building Permit Fees and Worksheet (Rev 9-2021); applies where curb, gutter, sidewalk, or storm drainage facilities exist
Temporary Occupancy Bond (Residential)$1,025.00 ($25 non-refundable)Morgan County Building Permit Fees and Worksheet (Rev 9-2021)
Re-inspection Fee (not ready)$70.00 (+1% State Fee)Morgan County Building Permit Fees and Worksheet (Rev 9-2021)
Investigation Fee (work started without permit)Double the base building permit feeMorgan County Building Permit Fees and Worksheet (Rev 9-2021)

Electrical Permit

Verified

Required for electrical work in Morgan County, covering both unincorporated county land and Morgan City through the same Morgan County Planning and Development Services department. Governed by the 2023 National Electrical Code (NEC) as adopted statewide by Utah Code § 15A-2-103(1)(g). EV charger/EVSE installation is electrical work and falls under this general Electrical Permit; the Morgan County Building Permit Fees and Worksheet (Rev 9-2021) does not publish a separate EV-specific fee line item.

Verified 2026-07-08 · Source

Requirements

  • New electrical service or panel upgrade
  • New circuits, rewiring, or major electrical alterations
  • Submission through Civic Review portal

Required documents

  • RequiredCivic Review ApplicationSubmitted digitally through app.civicreview.com with supporting documentation
  • OptionalElectrical Plan / Single-Line DiagramRequired for service upgrades and new construction

Fee schedule

Fee typeAmountNotes
Electrical Permit$100.00Morgan County Building Permit Fees and Worksheet (Rev 9-2021), flat fee line item under 'Building Permit Fees'
Re-inspection Fee (not ready)$70.00 (+1% State Fee)Morgan County Building Permit Fees and Worksheet (Rev 9-2021)

Plumbing Permit

Verified

Required for plumbing installations and alterations in Morgan County, covering both unincorporated county land and Morgan City through the same Morgan County Planning and Development Services department. Governed by the 2024 International Plumbing Code (IPC) as adopted by Utah Code § 15A-2-103, effective since July 1, 2026 (supersedes the 2021 IPC previously in force).

Verified 2026-07-08 · Source

Requirements

  • New plumbing fixture installations
  • Water line, sewer line, or gas line work
  • Submission through Civic Review portal

Required documents

  • RequiredCivic Review ApplicationSubmitted digitally through app.civicreview.com with supporting documentation

Fee schedule

Fee typeAmountNotes
Plumbing Permit$100.00Morgan County Building Permit Fees and Worksheet (Rev 9-2021), flat fee line item under 'Building Permit Fees'
Re-inspection Fee (not ready)$70.00 (+1% State Fee)Morgan County Building Permit Fees and Worksheet (Rev 9-2021)

Mechanical / HVAC Permit

Verified

Required for furnace/AC installation, replacement, and other mechanical work in Morgan County, covering both unincorporated county land and Morgan City through the same Morgan County Planning and Development Services department. Governed by the 2024 International Mechanical Code (IMC) / International Fuel Gas Code (IFGC) as adopted by Utah Code § 15A-2-103, effective since July 1, 2026 (supersedes the 2021 editions previously in force).

Verified 2026-07-08 · Source

Requirements

  • New HVAC system installation
  • Furnace or AC replacement
  • Submission through Civic Review portal

Required documents

  • RequiredCivic Review ApplicationSubmitted digitally through app.civicreview.com with supporting documentation

Fee schedule

Fee typeAmountNotes
Mechanical Permit$100.00Morgan County Building Permit Fees and Worksheet (Rev 9-2021), flat fee line item under 'Building Permit Fees'
Re-inspection Fee (not ready)$70.00 (+1% State Fee)Morgan County Building Permit Fees and Worksheet (Rev 9-2021)

Retaining Wall Permit

Verified

Required for retaining wall construction in Morgan County, covering both unincorporated county land and Morgan City through the same Morgan County Planning and Development Services department.

Verified 2026-07-08 · Source

Requirements

  • Retaining wall construction — engineered plans recommended for walls over 4 feet
  • Submission through Civic Review portal

Required documents

  • RequiredCivic Review ApplicationSubmitted digitally through app.civicreview.com with supporting documentation
  • OptionalEngineered Wall PlansStamped structural drawings from a licensed Utah PE for taller/load-bearing walls

Fee schedule

Fee typeAmountNotes
Retaining Wall Permit$250.00Morgan County Building Permit Fees and Worksheet (Rev 9-2021), flat fee line item under 'Building Permit Fees'
Re-inspection Fee (not ready)$70.00 (+1% State Fee)Morgan County Building Permit Fees and Worksheet (Rev 9-2021)

Demolition Permit

Verified

Required for demolition of any structure in Morgan County, covering both unincorporated county land and Morgan City through the same Morgan County Planning and Development Services department.

Verified 2026-07-08 · Source

Requirements

  • Complete or partial demolition of any structure
  • Asbestos inspection required for structures that may contain asbestos-containing materials — contact Utah DEQ (801) 536-4000

Required documents

  • RequiredCivic Review ApplicationSubmitted digitally through app.civicreview.com
  • OptionalAsbestos Survey / DEQ ClearanceContact Utah Department of Environmental Quality at (801) 536-4000 for asbestos inspection requirements

Fee schedule

Fee typeAmountNotes
Demolition Permit — Initial Inspection$50.00Morgan County Building Permit Fees and Worksheet (Rev 9-2021)
Demolition Permit — Additional Inspections (if required)$50.00/hr ($50.00 minimum)Morgan County Building Permit Fees and Worksheet (Rev 9-2021)

Solar Panel Permit

Verified

Required for installation of rooftop or ground-mounted solar photovoltaic systems in Morgan County, covering both unincorporated county land and Morgan City through the same Morgan County Planning and Development Services department.

Verified 2026-07-08 · Source

Requirements

  • Rooftop or ground-mounted solar panel installation
  • Non-refundable $100 preplan review deposit due at application
  • Submission through Civic Review portal

Required documents

  • RequiredCivic Review ApplicationSubmitted digitally through app.civicreview.com with supporting documentation
  • RequiredSolar Site Plan / Roof PlanDiagrams showing panel placement and dimensions
  • RequiredElectrical Single-Line DiagramSystem wiring from panels to inverter to main panel and utility meter

Fee schedule

Fee typeAmountNotes
Solar Panel — Preplan Review Deposit$100.00Morgan County Building Permit Fees and Worksheet (Rev 9-2021). Non-refundable, applied toward actual plan review fees; remaining fee calculated per project valuation plus 1% State fee.

Accessory Structure Permit (Garage, Pool, Storage, Detached Structures)

Verified

Required for detached garages, storage buildings, swimming pools, and other residential accessory structures in Morgan County, covering both unincorporated county land and Morgan City through the same Morgan County Planning and Development Services department.

Verified 2026-07-08 · Source

Requirements

  • Detached garage, storage building, swimming pool, or other accessory structure
  • Non-refundable $50 preplan review deposit due at application
  • Submission through Civic Review portal

Required documents

  • RequiredCivic Review ApplicationSubmitted digitally through app.civicreview.com with supporting documentation
  • RequiredSite PlanStructure location relative to property lines and setbacks

Fee schedule

Fee typeAmountNotes
Garage/Swimming Pool/Accessory Structure — Preplan Review Deposit$50.00Morgan County Building Permit Fees and Worksheet (Rev 9-2021). Non-refundable, applied toward actual plan review fees; remaining fee calculated per project valuation plus 1% State fee and possible impact fees.
Performance Bond (pools and accessory buildings, if public infrastructure affected)$2,500 or $15 per linear foot of frontage, whichever is greaterMorgan County Building Permit Fees and Worksheet (Rev 9-2021)

Commercial Building Permit

Required for new commercial and industrial construction throughout Morgan County — including unincorporated county land and Morgan City, both served by the same Morgan County Planning and Development Services department — regulated by the statewide-adopted 2024 IBC (Utah Code § 15A-2-103(1)(a), effective July 1, 2026). Morgan County's Building Permits page lists a separate 'Commercial Building Checklist' (item #7 in its document list) but does not publish a distinct commercial preplan-review-deposit tier the way it does for Single Family, Multi-Family, Addition/Remodel, and Manufactured/Modular Home categories — commercial projects instead follow the same general remaining-fee formula (~1-2% of project valuation plus 1% State fee plus applicable impact fees) documented on this file's Residential Building Permit entry.

Reviewed 2026-07-19 · Source

Requirements

  • New commercial or industrial construction throughout Morgan County (unincorporated land or Morgan City)
  • Complete digital PDF submission through the Civic Review portal, including engineer stamps and architectural review committee electrical stamps
  • Fire Protection Plan Approval obtained BEFORE submission: Mountain Green Fire Chief (801-876-2277) for the Mountain Green area, or the Morgan County Fire Marshal (801-845-4049) for all other areas including Morgan City
  • Performance Bond required where curb, gutter, sidewalk, or storm drainage facilities exist on the frontage

Required documents

  • RequiredCivic Review ApplicationAll building permit applications, including commercial, are submitted through the Civic Review online portal (app.civicreview.com). Digital plans as PDFs and all supporting documentation required at submittal.
  • RequiredCommercial Building ChecklistMorgan County's Building Permits page (morgancountyutah.gov/buildingpermits) lists a 'Commercial Building Checklist' as a distinct document in its submission-requirements list (item #7); the checklist's own detailed content could not be independently retrieved as of 2026-07-19 — confirm its specific requirements with the Planning and Development Department.
  • RequiredEngineer StampRequired on commercial construction plans, per Morgan County's general commercial submission requirements.
  • RequiredArchitectural Review Committee Electrical StampRequired as part of the commercial plan submittal per Morgan County's building permit process page.
  • RequiredFire Protection Plan ApprovalForm must be printed and taken to the appropriate fire district for signature before submission: Mountain Green Fire Chief (801-876-2277) for Mountain Green area, or Morgan County Fire Marshal (801-845-4049) for all other areas including Morgan City.

Fee schedule

Fee typeAmountNotes
Remaining Building Permit Fee (valuation-based)Approx. 1-2% of total project valuation (labor + materials), calculated per valuation breakdown; plus 1% State fee; plus applicable impact feesMorgan County Building Permit Fees and Worksheet (Rev 9-2021) — same valuation-based formula documented on this file's Residential Building Permit entry; the document does not publish a separate commercial-only percentage or valuation table distinct from the residential formula.
Performance Bond (public infrastructure) — New residential/commercial/industrial$2,500 or $15 per linear foot of frontage, whichever is greaterMorgan County Building Permit Fees and Worksheet (Rev 9-2021); applies where curb, gutter, sidewalk, or storm drainage facilities exist — explicitly listed as covering commercial and industrial construction alongside residential.
Minimum Building Permit Fee$100.00Morgan County Building Permit Fees and Worksheet (Rev 9-2021), amending CR-07-06 Exhibit B Base Fee Schedule — same minimum documented for residential permits, not itemized separately by use classification.
Re-inspection Fee (not ready)$70.00 (+1% State Fee)Morgan County Building Permit Fees and Worksheet (Rev 9-2021), same fee applied county-wide regardless of use classification.
Investigation Fee (work started without permit)Double the base building permit feeMorgan County Building Permit Fees and Worksheet (Rev 9-2021).

Commercial Tenant Improvement / Tenant Finish Permit

Required for tenant improvement and tenant finish work in existing commercial buildings throughout Morgan County (unincorporated land and Morgan City alike), served by Morgan County Planning and Development Services. Morgan County does not publish a distinct tenant-improvement permit type, checklist, or fee tier separate from its general Commercial Building Permit process — the Home Addition/Remodel preplan deposit tier ($50) documented for residential remodels was not confirmed to extend to commercial tenant-space remodels, so no deposit figure is asserted here without direct confirmation.

Reviewed 2026-07-19 · Source

Requirements

  • Tenant improvement or tenant finish work in an existing commercial building within Morgan County
  • Complete digital PDF submission through the Civic Review portal
  • Fire Protection Plan Approval obtained before submission
  • Engineer stamp and architectural review committee electrical stamp where applicable to the scope of work

Required documents

  • RequiredCivic Review ApplicationSubmitted digitally through app.civicreview.com — same portal used for all Morgan County building permits, including new commercial construction.
  • RequiredCommercial Building ChecklistMorgan County's published checklist referenced on its Building Permits page; no distinct tenant-improvement-specific checklist was located separately from this general commercial checklist as of 2026-07-19.
  • RequiredFire Protection Plan ApprovalSigned by the appropriate fire district (Mountain Green Fire Chief or Morgan County Fire Marshal) before submission.

Fee schedule

Fee typeAmountNotes
Remaining Building Permit Fee (valuation-based)Approx. 1-2% of total project valuation (labor + materials); plus 1% State fee; plus applicable impact feesSame general formula documented on this file's Commercial Building Permit entry — Morgan County's published fee worksheet does not carve out a separate, lower tenant-improvement rate.
Minimum Building Permit Fee$100.00Morgan County Building Permit Fees and Worksheet (Rev 9-2021) — county-wide minimum, not itemized separately by remodel/tenant-improvement scope.
Re-inspection Fee (not ready)$70.00 (+1% State Fee)Morgan County Building Permit Fees and Worksheet (Rev 9-2021).

Sources & verification

Verified against official sources. Last reviewed 2026-07-08.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Morgan County building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.

← Earlier version (2026-07-16)Later version (2026-07-20) →View current record →All versions →

Permalink: /utah/morgan-county-ut/unincorporated-morgan/as-of/2026-07-19/

Snapshot date: 2026-07-19

Commit: f0554ce

Reproducible from PermitBase’s version-controlled dataset, commit f0554ce.