Midvale building inspections
VerifiedInspection sequence, scheduling, and re-inspection fees for building permits in Midvale, Utah.
Verified 2026-07-04 · Source
How to schedule
Inspections are requested through the building department below.
- Address
- 7505 S Holden Street, 2nd Floor, Midvale, UT 84047
- Phone
- (801) 567-7200 ext. 1016
- Office hours
- Mon–Thu 8:00 AM – 6:00 PM; closed Friday–Sunday
- Website
- Official site
Published scheduling rules
- All building permit applications and inspection requests must be submitted online; document uploads are capped at 4 MB per file (email Building & Safety for larger files). (Residential Building Permit)
- All building permit applications and inspection requests must be submitted online through forms.midvaleut.gov; document uploads are capped at 4 MB per file. (General)
Inspection sequence
Applies to: Commercial Building Permit
- 1
Foundation / Footing
Before concrete pour, per standard IBC inspection sequence.
- 2
Framing
After framing, sheathing, and roof installed.
- 3
Final
All work complete before occupancy; requires the signed Commercial Construction Completion Checklist.
Applies to: Change of Use / Nonconforming Use Permit
- 1
Zoning/Use Compliance Review
Application is sent to the Planning Department for zoning review before license issuance; a Conditional Use Permit is applied for and obtained at this stage if required, per the Commercial Business License Application's workflow diagram.
- 2
Building/Fire/Health Inspections
Required for certain business types before a business license is issued, per the Obtain a Business License page and Commercial Business License Application.
Applies to: Commercial Tenant Improvement / Tenant Finish Permit
- 1
Framing / Structural
Where applicable to the tenant-improvement scope, before close-in.
- 2
Final
All work complete before occupancy.
Applies to: Demolition Permit
- 1
Pre-Demolition Inspection (Salt Lake County Health Department)
Completed and approved 'Pre-demolition Building Inspection Form' required from the Salt Lake County Health Department before a demolition permit is issued.
- 2
Asbestos Inspection (Utah DEQ Division of Air Quality)
Asbestos inspection from an approved asbestos inspector; the Demolition Requirements packet notes scheduling and approval 'takes time; allow several weeks for approval.'
Applies to: Fire Sprinkler / Fire Alarm System Peer Review and Permit
- 1
Acceptance Testing (Sprinkler)
Includes underground flush and final acceptance testing per UFA's Fire Sprinkler Plan Submittal Guide; systems with 20+ heads require off-site monitoring.
- 2
Acceptance Testing (Fire Alarm)
Final acceptance test of the fire alarm and detection system per UFA's Fire Alarm Plan Submittal Guide.
Final inspection only: Fire Alarm System Permit, Residential Addition / Remodel Permit, Residential Building Permit, Sign Permit
Sources & verification
Verified against official sources. Last reviewed 2026-07-04.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Midvale building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Midvale building permits
Get alerts for Midvale
We'll email you when Midvale's fees, documents, or codes change — not often.
We only use your email to send permit updates. No spam, unsubscribe anytime. Privacy.