Midvale building inspections

Verified

Inspection sequence, scheduling, and re-inspection fees for building permits in Midvale, Utah.

Verified 2026-07-04 · Source

How to schedule

Inspections are requested through the building department below.

Address
7505 S Holden Street, 2nd Floor, Midvale, UT 84047
Phone
(801) 567-7200 ext. 1016
Office hours
Mon–Thu 8:00 AM – 6:00 PM; closed Friday–Sunday

Published scheduling rules

  • All building permit applications and inspection requests must be submitted online; document uploads are capped at 4 MB per file (email Building & Safety for larger files). (Residential Building Permit)
  • All building permit applications and inspection requests must be submitted online through forms.midvaleut.gov; document uploads are capped at 4 MB per file. (General)

Inspection sequence

Applies to: Commercial Building Permit

  1. 1

    Foundation / Footing

    Before concrete pour, per standard IBC inspection sequence.

  2. 2

    Framing

    After framing, sheathing, and roof installed.

  3. 3

    Final

    All work complete before occupancy; requires the signed Commercial Construction Completion Checklist.

Applies to: Change of Use / Nonconforming Use Permit

  1. 1

    Zoning/Use Compliance Review

    Application is sent to the Planning Department for zoning review before license issuance; a Conditional Use Permit is applied for and obtained at this stage if required, per the Commercial Business License Application's workflow diagram.

  2. 2

    Building/Fire/Health Inspections

    Required for certain business types before a business license is issued, per the Obtain a Business License page and Commercial Business License Application.

Applies to: Commercial Tenant Improvement / Tenant Finish Permit

  1. 1

    Framing / Structural

    Where applicable to the tenant-improvement scope, before close-in.

  2. 2

    Final

    All work complete before occupancy.

Applies to: Demolition Permit

  1. 1

    Pre-Demolition Inspection (Salt Lake County Health Department)

    Completed and approved 'Pre-demolition Building Inspection Form' required from the Salt Lake County Health Department before a demolition permit is issued.

  2. 2

    Asbestos Inspection (Utah DEQ Division of Air Quality)

    Asbestos inspection from an approved asbestos inspector; the Demolition Requirements packet notes scheduling and approval 'takes time; allow several weeks for approval.'

Applies to: Fire Sprinkler / Fire Alarm System Peer Review and Permit

  1. 1

    Acceptance Testing (Sprinkler)

    Includes underground flush and final acceptance testing per UFA's Fire Sprinkler Plan Submittal Guide; systems with 20+ heads require off-site monitoring.

  2. 2

    Acceptance Testing (Fire Alarm)

    Final acceptance test of the fire alarm and detection system per UFA's Fire Alarm Plan Submittal Guide.

Midvale building permits

Get alerts for Midvale

We'll email you when Midvale's fees, documents, or codes change — not often.

We only use your email to send permit updates. No spam, unsubscribe anytime. Privacy.