Commercial Building Permit in Midvale, Utah

Required for new commercial building construction in Midvale, valuation-based per the FY2026 Approved Fee Schedule (Ordinance 2026-O-14, adopted May 20, 2026), using the same Building Permit Fees table applied to all building permits. A pre-construction meeting is required on all new commercial buildings, per the city's Building & Safety page.

Verified 2026-07-19 · Source

When you need this permit

  • New commercial building construction
  • Building Permit Application submitted online via forms.midvaleut.gov (document uploads limited to 4 MB each; larger files emailed to Building & Safety)
  • Pre-construction meeting required on all new commercial buildings
  • Commercial Construction Completion Checklist signed off before occupancy

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 3 required documents checked.

This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29

Fee schedule

Building Permit Fee — valuation-basedMidvale City FY2026 Approved Fee Schedule (adopted per Ordinance 2026-O-14, May 20, 2026), 'Building Permit Fees' table. Same table used for all building permits, including commercial.
$48 + $9.30 per $1,000 (or fraction thereof) for $0–$100,000 valuation; $978 for first $100,000 + $14 per additional $1,000 to $125,000; $1,328 for first $125,000 + $10.10 per additional $1,000 to $150,000; $1,580 for first $150,000 + $7 per additional $1,000 to $200,000; $1,930 for first $200,000 + $5.60 per additional $1,000 to $600,000; $4,170 for first $600,000 + $4.75 per additional $1,000 to $1,100,000; $6,545 for first $1,100,000 + $3.65 per additional $1,000 over that.
Plan Check FeeMidvale City FY2026 Approved Fee Schedule, 'Building Permit Fees' table: 'Plan Check Fee — 65% of Building Fee.'
65% of the Building Permit Fee
Electrical Fee (included with building permit for MEP)Midvale City FY2026 Approved Fee Schedule, 'Building Permit Fees' table: 'Electrical Fee — 5% of Building Fee.'
5% of the Building Permit Fee
Mechanical Fee (included with building permit for MEP)Midvale City FY2026 Approved Fee Schedule, 'Building Permit Fees' table: 'Mechanical Fee — 5% of Building Fee.'
5% of the Building Permit Fee
Plumbing Fee (included with building permit for MEP)Midvale City FY2026 Approved Fee Schedule, 'Building Permit Fees' table: 'Plumbing Fee — 5% of Building Fee.'
5% of the Building Permit Fee
State SurchargeMidvale City FY2026 Approved Fee Schedule, 'Building Permit Fees' table: 'Surcharge — 1% of the sum of Building, Electrical, Mechanical, and Plumbing Fees.'
1% of the sum of the Building, Electrical, Mechanical, and Plumbing fees
Pre-Plan Check Fee (credited toward building permit fee; non-refundable after plan review commences)Midvale City FY2026 Approved Fee Schedule, 'Pre-Plan Check Fees' table.
$0 (<$100,000 valuation); $200 ($100,000–$300,000); $1,000 ($300,000–$500,000); $2,000 ($500,000–$1,000,000); $5,000 ($1,000,000–$10,000,000); $10,000 (>$10,000,000)

Review timeline

Plan review
Not published — contact the department

How long did your Commercial Building Permit permit actually take in Midvale?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    Foundation / Footing

    Before concrete pour, per standard IBC inspection sequence.

  2. 2

    Framing

    After framing, sheathing, and roof installed.

  3. 3

    Final

    All work complete before occupancy; requires the signed Commercial Construction Completion Checklist.

See the full Midvale inspection guide — scheduling & re-inspection fees →

Tips

  • A pre-construction meeting is required on all new commercial buildings in Midvale (and may be required for some remodels).
  • Midvale bills Electrical, Mechanical, and Plumbing each at 5% of the Building Permit Fee when included with the building permit, plus a 1% state surcharge on the combined total.
  • A Pre-Plan Check Fee (credited toward the building permit fee) applies above $100,000 in valuation and becomes non-refundable once plan review begins.

Frequently asked questions

Midvale requires a commercial building permit for: New commercial building construction; Building Permit Application submitted online via forms.midvaleut.gov (document uploads limited to 4 MB each; larger files emailed to Building & Safety); Pre-construction meeting required on all new commercial buildings; Commercial Construction Completion Checklist signed off before occupancy. If your project isn't listed, confirm with Midvale City Community Development — Building & Safety Division at (801) 567-7200 ext. 1016 before starting work.

Midvale calculates the building permit fee from a valuation table (e.g., $6,545 for the first $1,100,000 plus $3.65 per additional $1,000 above that), plus a 65% Plan Check Fee, 5% each for Electrical/Mechanical/Plumbing when bundled, and a 1% state surcharge — per the FY2026 Approved Fee Schedule (Ordinance 2026-O-14).

Midvale does not publish a plan-review or permit-issuance turnaround time for commercial building permits on midvale.utah.gov, in its Building & Safety FAQ, or in its FY2026 Fee Schedule or Commercial Construction Completion Checklist as of 2026-07-19 — the same gap the city's residential building permit page also has. Contact Building & Safety at (801) 567-7200 ext. 1016 for current estimates.

You'll need: Building Permit Application (online); Commercial Construction Completion Checklist; Digital As-Built Plans (GIS Shapefile). Depending on your project, Midvale may also ask for: Owner Builder Form; Contractor Verification Form. See the required-documents checklist on this page for details on each.

Midvale requires 3 inspection(s) for a commercial building permit, in order: Foundation / Footing, Framing, Final. Schedule each through Midvale City Community Development — Building & Safety Division ((801) 567-7200 ext. 1016).

Apply through Midvale City Community Development — Building & Safety Division at 7505 S Holden Street, 2nd Floor, Midvale, UT 84047. Phone: (801) 567-7200 ext. 1016, email: buildingpermit@midvaleut.gov. Office hours: Mon–Thu 8:00 AM – 6:00 PM; closed Friday–Sunday. Official information: https://www.midvale.utah.gov/government/departments/community_development/building___safety.php.

Midvale, Utah has adopted: 2024 International Building Code (IBC), including Appendices C and J — current statewide edition per Utah Code § 15A-2-103(1)(a), effective July 1, 2026.; 2021 International Residential Code (IRC) — current statewide edition per Utah Code § 15A-2-103(1)(b); unchanged by the July 1, 2026 statewide update.; 2024 International Plumbing Code (IPC) — current statewide edition per Utah Code § 15A-2-103(1)(d), effective July 1, 2026.; 2024 International Mechanical Code (IMC) — current statewide edition per Utah Code § 15A-2-103(1)(e), effective July 1, 2026.; 2024 International Fuel Gas Code (IFGC) — current statewide edition per Utah Code § 15A-2-103(1)(f), effective July 1, 2026.; 2024 International Energy Conservation Code (IECC), covering both commercial and residential provisions in a single edition — current statewide edition per Utah Code § 15A-2-103(1)(h), effective July 1, 2026.; 2024 International Existing Building Code (IEBC) — current statewide edition per Utah Code § 15A-2-103(1)(i), effective July 1, 2026.; 2023 National Electrical Code (NEC) — current statewide edition per Utah Code § 15A-2-103(1)(g); unchanged by the July 1, 2026 statewide update.; Residential provisions of the 2024 International Swimming Pool and Spa Code (ISPSC) — current statewide edition per Utah Code § 15A-2-103(1)(n), effective July 1, 2026.; Modular Building Institute Standards 1200 and 1205 — adopted statewide per Utah Code § 15A-2-103(1)(o); not separately itemized on Midvale's own published sources, but applies statewide.; Midvale City is a compliance agency under Utah Code § 15A-1-202 and enforces these statewide codes through its own Building & Safety Division, per the Midvale Building & Safety FAQ (midvale.utah.gov), which references ICC standards, DOPL requirements, and Statewide Amendments to the State Construction Code.. Local amendments apply — see the Midvale overview page for the full list.

Sources & verification

Verified against official sources. Last reviewed 2026-07-19.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Midvale building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.

This one’s complicated · Get an expediter

Tell us about your project and we’ll connect you with a permit expediter who works in Midvale.

PermitBase may receive a referral fee from the expediter. This is a service introduction, not verified permit data or legal advice.