Midvale does not publish a distinct EV-charger fee line item. Per the Midvale City FY2026 Approved Fee Schedule, installing an EV charger (EVSE) is electrical work billed under the city's general Electrical Permit — as a standalone Service Charge (over-the-counter permit) or, if tied to a new building permit, at 5% of the Building Permit Fee.

Verified 2026-07-20 · Source

When you need this permit

  • Installation of a Level 2 or DC fast EV charger (EVSE) at a residential or commercial property
  • New dedicated circuit and/or panel/service capacity to serve the charger
  • Compliance with the 2023 NEC, adopted statewide by Utah Code § 15A-2-103(1)(g)

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 1 required documents checked.

This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29

Fee schedule

Service Charge (over-the-counter permit — standalone)Midvale City FY2026 Approved Fee Schedule, 'Over the Counter Permit Fees' table: 'Service Charge — $47 electrical fee + 0.47 surcharge.' Applies to a standalone EV charger circuit/service install not tied to a new building permit.
$47 electrical fee + $0.47 surcharge
Electrical Fee (tied to a new building permit)Midvale City FY2026 Approved Fee Schedule, 'Building Permit Fees' table: 'Electrical Fee — 5% of Building Fee.'
5% of the Building Permit Fee

Review timeline

Plan review
Not published — contact the department

How long did your EV Charger / EVSE Permit permit actually take in Midvale?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

    See the full Midvale inspection guide — scheduling & re-inspection fees →

    Tips

    • Midvale does not have a distinct EV charger permit category — a standalone charger install is billed as the $47 + $0.47 surcharge Service Charge over-the-counter permit.
    • All electrical work must comply with the 2023 National Electrical Code (NEC) adopted statewide per Utah Code § 15A-2-103(1)(g).

    Frequently asked questions

    Midvale requires an ev charger / evse permit for: Installation of a Level 2 or DC fast EV charger (EVSE) at a residential or commercial property; New dedicated circuit and/or panel/service capacity to serve the charger; Compliance with the 2023 NEC, adopted statewide by Utah Code § 15A-2-103(1)(g). If your project isn't listed, confirm with Midvale City Community Development — Building & Safety Division at (801) 567-7200 ext. 1016 before starting work.

    No. The Midvale City FY2026 Approved Fee Schedule does not publish a distinct EV-charger fee category. A standalone EV charger/EVSE install is billed as a Service Charge over-the-counter electrical permit ($47 + $0.47 surcharge); electrical work tied to a new building permit is billed at 5% of the building permit fee.

    Midvale does not publish a plan-review timeline for this permit. Contact Midvale City Community Development — Building & Safety Division at (801) 567-7200 ext. 1016 for current turnaround.

    You'll need: Building Permit Application (online). Depending on your project, Midvale may also ask for: Contractor Verification Form. See the required-documents checklist on this page for details on each.

    Apply through Midvale City Community Development — Building & Safety Division at 7505 S Holden Street, 2nd Floor, Midvale, UT 84047. Phone: (801) 567-7200 ext. 1016, email: buildingpermit@midvaleut.gov. Office hours: Mon–Thu 8:00 AM – 6:00 PM; closed Friday–Sunday. Official information: https://www.midvale.utah.gov/government/departments/community_development/building___safety.php.

    Midvale, Utah has adopted: 2024 International Building Code (IBC), including Appendices C and J — current statewide edition per Utah Code § 15A-2-103(1)(a), effective July 1, 2026.; 2021 International Residential Code (IRC) — current statewide edition per Utah Code § 15A-2-103(1)(b); unchanged by the July 1, 2026 statewide update.; 2024 International Plumbing Code (IPC) — current statewide edition per Utah Code § 15A-2-103(1)(d), effective July 1, 2026.; 2024 International Mechanical Code (IMC) — current statewide edition per Utah Code § 15A-2-103(1)(e), effective July 1, 2026.; 2024 International Fuel Gas Code (IFGC) — current statewide edition per Utah Code § 15A-2-103(1)(f), effective July 1, 2026.; 2024 International Energy Conservation Code (IECC), covering both commercial and residential provisions in a single edition — current statewide edition per Utah Code § 15A-2-103(1)(h), effective July 1, 2026.; 2024 International Existing Building Code (IEBC) — current statewide edition per Utah Code § 15A-2-103(1)(i), effective July 1, 2026.; 2023 National Electrical Code (NEC) — current statewide edition per Utah Code § 15A-2-103(1)(g); unchanged by the July 1, 2026 statewide update.; Residential provisions of the 2024 International Swimming Pool and Spa Code (ISPSC) — current statewide edition per Utah Code § 15A-2-103(1)(n), effective July 1, 2026.; Modular Building Institute Standards 1200 and 1205 — adopted statewide per Utah Code § 15A-2-103(1)(o); not separately itemized on Midvale's own published sources, but applies statewide.; Midvale City is a compliance agency under Utah Code § 15A-1-202 and enforces these statewide codes through its own Building & Safety Division, per the Midvale Building & Safety FAQ (midvale.utah.gov), which references ICC standards, DOPL requirements, and Statewide Amendments to the State Construction Code.. Local amendments apply — see the Midvale overview page for the full list.

    Sources & verification

    Verified against official sources. Last reviewed 2026-07-20.

    Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Midvale building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.