West Valley City building inspections
VerifiedInspection sequence, scheduling, and re-inspection fees for building permits in West Valley City, Utah.
Verified 2026-07-01 · Source
How to schedule
Inspections are requested through the building department below.
- Address
- 3600 S Constitution Boulevard, Suite 220, West Valley City, UT 84119
- Phone
- (801) 963-3283
- building@wvc-ut.gov
- Office hours
- Monday–Thursday 7:00 AM – 6:00 PM
- Website
- Official site
Published scheduling rules
- Inspection requests can usually be accommodated within 24 hours. Call (801) 963-3283 to schedule. First field inspection: Mon–Thu 8 AM; last field inspection: Mon–Thu 4:30 PM. (Residential Building Permit)
- West Valley City operates its own city Fire Department (Fire Prevention & Inspections Division) rather than Unified Fire Authority or a special fire district. Contact Fire Marshal Jed Peters or Fire Inspector Lance Nielson at (801) 963-3336, or the Fire Prevention Office at (801) 965-7171, to coordinate plan review and inspection scheduling. (Fire Sprinkler & Fire Alarm Permit)
Inspection sequence
Applies to: Basement Finish Permit
- 1
Framing
Wall framing, fire blocking, egress window openings
- 2
MEP Rough-In
Electrical, plumbing, and HVAC rough-ins before walls closed
- 3
Insulation
Insulation on exterior walls before drywall
- 4
Final
Drywall, fixtures, smoke/CO detectors, and all finishes complete
Applies to: Residential Building Permit
- 1
Foundation / Footing
Before concrete pour — verify excavation, forms, rebar, and anchor bolts
- 2
Framing
After framing, sheathing, and rough-in MEP — before insulation or wall cover
- 3
Insulation
After insulation installed, before drywall
- 4
Final
All work complete — certificate of occupancy issued upon passing
Applies to: Swimming Pool Permit
- 1
Excavation / Steel
Pool shell excavation, rebar, and plumbing before gunite/shotcrete
- 2
Electrical / Bonding
Pool bonding grid, equipment connections, GFCI protection per NEC Article 680
- 3
Barrier
Pool fence/barrier — 48-inch minimum height, self-closing/self-latching gates per IRC Chapter 31
- 4
Final
Pool complete, filled, equipment operational, all barriers in place
Applies to: Commercial Building Permit
- 1
Foundation / Footing
Before concrete pour, per standard IBC inspection sequence.
- 2
Framing
After framing, sheathing, and roof installed.
- 3
Final
All work complete before occupancy; requires signed Special Inspector and Structural Engineer letters, HVAC balance report, and (if applicable) State Boiler/Elevator approvals.
Applies to: Deck Permit
- 1
Footings
Verify footing depth (below 30-inch frost line per WVC Design Criteria), diameter, and rebar before concrete pour
- 2
Framing
Posts, beams, joists, ledger connection, and hardware
- 3
Final
Decking, stairs, guards, and railings complete
Applies to: Electrical Permit
- 1
Rough-In
After wiring installed, before walls closed — verify box placement, wire sizing, proper support
- 2
Service / Panel
Panel installation, grounding electrode system, service entrance conductors. WVC contacts Rocky Mountain Power to authorize power after approval.
- 3
Final
All devices installed, GFCI/AFCI protection verified, panel labeled
Applies to: Change of Use / Certificate of Occupancy Permit
- 1
Building Final
WVC Building Inspection Division field final verifying life-safety and code compliance for the new use or occupancy
- 2
Fire Marshal Final
Required before Certificate of Occupancy issuance per the WVC Commercial Certificate of Occupancy Checklist; contact Fire Inspector Lance Nielson at (801) 963-3551 or Marcus Duarte at (801) 965-5811
Applies to: Commercial Tenant Improvement / Tenant Finish Permit
- 1
Framing / Structural
Where applicable to the tenant-improvement scope, before close-in.
- 2
Final
All work complete before occupancy.
Applies to: Demolition Permit
- 1
Pre-Demolition Clearance
All utility disconnects and pre-approvals (Air Quality, Dominion Energy) must be received by WVC before permit is issued
- 2
Final / Site Clear
Site cleared, foundation removed or capped, site conditions verified
Applies to: EV Charger / EVSE Permit
- 1
Service / Panel
Panel installation, grounding electrode system, service entrance conductors serving the EV charger circuit. WVC contacts Rocky Mountain Power to authorize power after approval.
- 2
Final
Charger installed and operational, GFCI/AFCI protection verified where required, panel labeled
Applies to: Fire Sprinkler & Fire Alarm Permit
- 1
Rough-In
Sprinkler piping, standpipe, or fire alarm wiring/devices installed and visible, before concealment
- 2
Final / Acceptance Test
Hydrostatic test of sprinkler/standpipe piping and/or full functional test of the fire alarm system, witnessed and approved by the WVC Fire Marshal before the system is placed in service or the space is occupied
Applies to: Mechanical / HVAC Permit
- 1
Rough-In
Ductwork and gas piping installed, before walls closed — verify clearances and support
- 2
Final
Equipment operational, combustion air verified, gas pressure tested, thermostat functional
Applies to: Roofing Permit
- 1
Deck / Substrate
After tear-off — verify sheathing condition before underlayment and new roofing is installed
- 2
Final
Completed roof — verify materials, ice and water shield, flashing, drip edge, and nailing pattern
Applies to: Solar Panel Permit
- 1
Rough Electrical
Conduit runs, wire sizing, disconnect placement before energizing
- 2
Final / Structural
Panel mounting, racking attachment, roof penetration sealing, and electrical connections verified
Re-inspection fees
Sources & verification
Verified against official sources. Last reviewed 2026-07-01.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the West Valley City building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
West Valley City building permits
Get alerts for West Valley City
We'll email you when West Valley City's fees, documents, or codes change — not often.
We only use your email to send permit updates. No spam, unsubscribe anytime. Privacy.