Skip to main content
PermitBase

West Valley City building inspections

Verified

Inspection sequence, scheduling, and re-inspection fees for building permits in West Valley City, Utah.

Verified 2026-07-01 · Source

How to schedule

Inspections are requested through the building department below.

Address
3600 S Constitution Boulevard, Suite 220, West Valley City, UT 84119
Phone
(801) 963-3283
Office hours
Monday–Thursday 7:00 AM – 6:00 PM

Published scheduling rules

  • Inspection requests can usually be accommodated within 24 hours. Call (801) 963-3283 to schedule. First field inspection: Mon–Thu 8 AM; last field inspection: Mon–Thu 4:30 PM. (Residential Building Permit)
  • West Valley City operates its own city Fire Department (Fire Prevention & Inspections Division) rather than Unified Fire Authority or a special fire district. Contact Fire Marshal Jed Peters or Fire Inspector Lance Nielson at (801) 963-3336, or the Fire Prevention Office at (801) 965-7171, to coordinate plan review and inspection scheduling. (Fire Sprinkler & Fire Alarm Permit)

Inspection sequence

Applies to: Basement Finish Permit

  1. 1

    Framing

    Wall framing, fire blocking, egress window openings

  2. 2

    MEP Rough-In

    Electrical, plumbing, and HVAC rough-ins before walls closed

  3. 3

    Insulation

    Insulation on exterior walls before drywall

  4. 4

    Final

    Drywall, fixtures, smoke/CO detectors, and all finishes complete

Applies to: Residential Building Permit

  1. 1

    Foundation / Footing

    Before concrete pour — verify excavation, forms, rebar, and anchor bolts

  2. 2

    Framing

    After framing, sheathing, and rough-in MEP — before insulation or wall cover

  3. 3

    Insulation

    After insulation installed, before drywall

  4. 4

    Final

    All work complete — certificate of occupancy issued upon passing

Applies to: Swimming Pool Permit

  1. 1

    Excavation / Steel

    Pool shell excavation, rebar, and plumbing before gunite/shotcrete

  2. 2

    Electrical / Bonding

    Pool bonding grid, equipment connections, GFCI protection per NEC Article 680

  3. 3

    Barrier

    Pool fence/barrier — 48-inch minimum height, self-closing/self-latching gates per IRC Chapter 31

  4. 4

    Final

    Pool complete, filled, equipment operational, all barriers in place

Applies to: Commercial Building Permit

  1. 1

    Foundation / Footing

    Before concrete pour, per standard IBC inspection sequence.

  2. 2

    Framing

    After framing, sheathing, and roof installed.

  3. 3

    Final

    All work complete before occupancy; requires signed Special Inspector and Structural Engineer letters, HVAC balance report, and (if applicable) State Boiler/Elevator approvals.

Applies to: Deck Permit

  1. 1

    Footings

    Verify footing depth (below 30-inch frost line per WVC Design Criteria), diameter, and rebar before concrete pour

  2. 2

    Framing

    Posts, beams, joists, ledger connection, and hardware

  3. 3

    Final

    Decking, stairs, guards, and railings complete

Applies to: Electrical Permit

  1. 1

    Rough-In

    After wiring installed, before walls closed — verify box placement, wire sizing, proper support

  2. 2

    Service / Panel

    Panel installation, grounding electrode system, service entrance conductors. WVC contacts Rocky Mountain Power to authorize power after approval.

  3. 3

    Final

    All devices installed, GFCI/AFCI protection verified, panel labeled

Applies to: Change of Use / Certificate of Occupancy Permit

  1. 1

    Building Final

    WVC Building Inspection Division field final verifying life-safety and code compliance for the new use or occupancy

  2. 2

    Fire Marshal Final

    Required before Certificate of Occupancy issuance per the WVC Commercial Certificate of Occupancy Checklist; contact Fire Inspector Lance Nielson at (801) 963-3551 or Marcus Duarte at (801) 965-5811

Applies to: Commercial Tenant Improvement / Tenant Finish Permit

  1. 1

    Framing / Structural

    Where applicable to the tenant-improvement scope, before close-in.

  2. 2

    Final

    All work complete before occupancy.

Applies to: Demolition Permit

  1. 1

    Pre-Demolition Clearance

    All utility disconnects and pre-approvals (Air Quality, Dominion Energy) must be received by WVC before permit is issued

  2. 2

    Final / Site Clear

    Site cleared, foundation removed or capped, site conditions verified

Applies to: EV Charger / EVSE Permit

  1. 1

    Service / Panel

    Panel installation, grounding electrode system, service entrance conductors serving the EV charger circuit. WVC contacts Rocky Mountain Power to authorize power after approval.

  2. 2

    Final

    Charger installed and operational, GFCI/AFCI protection verified where required, panel labeled

Applies to: Fire Sprinkler & Fire Alarm Permit

  1. 1

    Rough-In

    Sprinkler piping, standpipe, or fire alarm wiring/devices installed and visible, before concealment

  2. 2

    Final / Acceptance Test

    Hydrostatic test of sprinkler/standpipe piping and/or full functional test of the fire alarm system, witnessed and approved by the WVC Fire Marshal before the system is placed in service or the space is occupied

Applies to: Mechanical / HVAC Permit

  1. 1

    Rough-In

    Ductwork and gas piping installed, before walls closed — verify clearances and support

  2. 2

    Final

    Equipment operational, combustion air verified, gas pressure tested, thermostat functional

Applies to: Roofing Permit

  1. 1

    Deck / Substrate

    After tear-off — verify sheathing condition before underlayment and new roofing is installed

  2. 2

    Final

    Completed roof — verify materials, ice and water shield, flashing, drip edge, and nailing pattern

Applies to: Solar Panel Permit

  1. 1

    Rough Electrical

    Conduit runs, wire sizing, disconnect placement before energizing

  2. 2

    Final / Structural

    Panel mounting, racking attachment, roof penetration sealing, and electrical connections verified

Re-inspection fees

Residential Building PermitRe-inspection Fee · WVC Permit Costs & Fees page (wvc-ut.gov/307)
$53 per occurrence
Electrical PermitRe-inspection Fee · WVC Permit Costs & Fees page (wvc-ut.gov/307)
$53 per occurrence
EV Charger / EVSE PermitRe-inspection Fee · WVC Permit Costs & Fees page (wvc-ut.gov/307)
$53 per occurrence
Mechanical / HVAC PermitRe-inspection Fee · WVC Permit Costs & Fees page (wvc-ut.gov/307)
$53 per occurrence
Roofing PermitRe-inspection Fee · WVC Permit Costs & Fees page (wvc-ut.gov/307)
$53 per occurrence
Solar Panel PermitRe-inspection Fee · WVC Permit Costs & Fees page (wvc-ut.gov/307)
$53 per occurrence
Deck PermitRe-inspection Fee · WVC Permit Costs & Fees page (wvc-ut.gov/307)
$53 per occurrence
Demolition PermitRe-inspection Fee · WVC Permit Costs & Fees page (wvc-ut.gov/307)
$53 per occurrence
Basement Finish PermitRe-inspection Fee · WVC Permit Costs & Fees page (wvc-ut.gov/307)
$53 per occurrence
Swimming Pool PermitRe-inspection Fee · WVC Permit Costs & Fees page (wvc-ut.gov/307)
$53 per occurrence

Sources & verification

Verified against official sources. Last reviewed 2026-07-01.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the West Valley City building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.

West Valley City building permits

Get alerts for West Valley City

We'll email you when West Valley City's fees, documents, or codes change — not often.

We only use your email to send permit updates. No spam, unsubscribe anytime. Privacy.