This is PermitBase’s published record for Unincorporated Tooele County as of 2026-07-19. It has since been superseded — see the current record. A historical record reflects what PermitBase had verified at that time; it may not capture a real-world change the jurisdiction had made but PermitBase had not yet verified, and it includes any errors we later corrected. Snapshots are never edited retroactively.
Unincorporated Tooele County building permits
VerifiedUnincorporated Tooele County, Utah — as published 2026-07-19.
Verified 2026-07-03 · Source
Codes adopted
Permit types & fees
Residential Building Permit
VerifiedRequired for new residential construction, additions, remodels, and any work regulated by the statewide-adopted 2024 IBC / 2021 IRC (per Utah Code §15A-2-103) in unincorporated Tooele County; the county's own application form still cites 2021-cycle editions (live-checked 2026-07-16). The county's own application form covers Building, Electrical, HVAC, Plumbing, Energy, Occupancy, Sign, Construction, and Demolition permits under a single combined application.
Verified 2026-07-03 · Source
Requirements
- New single-family residential construction, additions, remodels regulated by the statewide-adopted 2024 IBC / 2021 IRC (Utah Code §15A-2-103); Tooele County's own application form cites 2021 IRC/IBC
- Complete and submit all supporting documents at time of submittal — incomplete applications are not accepted
- Dimensioned site plan showing north direction, lot lines, adjacent streets/roads/rights-of-way, existing structures/wells/septic tanks, proposed construction, and motor vehicle access
- One complete set of construction plans (may include gas pipe sizing diagram, stucco specifications, proof of energy code compliance)
- Site Plan Approval from the Tooele County Fire Department
- Utility approval forms (gas, electric, sewer, water) if new service or additional load is being added
- For properties not connected to community water/sewer: certificate of approval from the Tooele County Health Department for water and septic, per Tooele County Land Use Ord. 4-16 (Ord. 2005-22, 9/13/2005)
- Architectural Control Committee approval where required in subdivisions
Required documents
- RequiredBuilding Permit Application and General InstructionsTooele County's combined application form (building-permit-012225.pdf, rev. 01-22-2025) covering Building, Electrical, HVAC, Plumbing, Energy, Occupancy, Sign, Construction, and Demolition permits; includes utility contact list, fire department contacts, and Fire Protection Criteria for Unincorporated Tooele County.
- RequiredDimensioned Site PlanMust show north direction, lot lines, adjacent streets/roads/rights-of-way, location of existing structures/wells/septic tanks, location of proposed construction, and motor vehicle access; must carry Site Plan Approval from the Tooele County Fire Department.
- RequiredComplete Set of Construction PlansMay include gas pipe sizing diagram, stucco specifications, proof of compliance with the adopted energy code, and Fire Department plan approval.
- RequiredProof of OwnershipRequired for all applications per the county's own checklist.
- OptionalHealth Department Water/Septic CertificateRequired only for properties not connected to a community water or sewer system, per Tooele County Land Use Ord. 4-16 (Ord. 2005-22).
Fee schedule
| Fee type | Amount | Notes |
|---|---|---|
| Building Permit Fee | Valuation-based, per Uniform Building Code fee-calculation provisions | Tooele County adopted Fee Schedule (effective 5-19-26), Building Permit Fees section: 'The Building Official shall determine valuations for the purpose of calculating fees by using for each calendar… Show full citationHideTooele County adopted Fee Schedule (effective 5-19-26), Building Permit Fees section: 'The Building Official shall determine valuations for the purpose of calculating fees by using for each calendar year the first Building Valuation Data publication issued during that calendar year by the International Conference of Building Officials. The Building Official shall adjust each calculated valuation by the regional modifier listed in said publication for Utah using the grade of construction determined to be applicable. The fee shall then be determined by reference to the Uniform Building Code provisions regarding the calculation of fees.' |
| Factory Built Housing, Manufactured Homes, and Modular Units | 45% of the valuation listed in the applicable Building Valuation Data publication | Tooele County adopted Fee Schedule (effective 5-19-26), Building Permit Fees section. |
| State Surcharge | 1% of the building permit fee | Tooele County adopted Fee Schedule (effective 5-19-26): 'Tooele County shall assess and collect a surcharge equal to one percent of the building permit fee in compliance with Utah state law... Show full citationHideTooele County adopted Fee Schedule (effective 5-19-26): 'Tooele County shall assess and collect a surcharge equal to one percent of the building permit fee in compliance with Utah state law... shall remit eighty percent of the amount of the surcharge to have been assessed to said Division [DOPL].' |
| Impact Fee — Tooele County Parks, Recreation and Trails (Single Family) | $2,305 | Tooele County adopted Fee Schedule (effective 5-19-26), Impact Fees section, created by Ordinance 2024-07 (adopted 9/3/2024, effective 12/2/2024). |
| Impact Fee — Parks (Multi Family, per unit) | $1,898 | Tooele County adopted Fee Schedule (effective 5-19-26), Impact Fees section. |
| Impact Fee — Tooele County Public Safety (Single Family, per dwelling unit) | $394 | Tooele County adopted Fee Schedule (effective 5-19-26), Impact Fees section. |
| Impact Fee — Tooele County Public Safety (Multi Family, per dwelling unit) | $289 | Tooele County adopted Fee Schedule (effective 5-19-26), Impact Fees section. |
| Impact Fee — Tooele County Fire (Single Family, per dwelling unit) | $201 | Tooele County adopted Fee Schedule (effective 5-19-26), Impact Fees section. |
| Impact Fee — Tooele County Fire (Multi Family, per dwelling unit) | $75 | Tooele County adopted Fee Schedule (effective 5-19-26), Impact Fees section. |
| Impact Fee — North Tooele Fire District | $583.93 | Tooele County adopted Fee Schedule (effective 5-19-26), Impact Fees section. Applies within the North Tooele Fire District boundary rather than county-wide. |
| Impact Fee — Stansbury Park Service Agency | $2,700 | Tooele County adopted Fee Schedule (effective 5-19-26), Impact Fees section. Applies within the Stansbury Park Service Agency boundary. |
| Impact Fee — Transportation (Single Family Home) | $489 | Tooele County adopted Fee Schedule (effective 5-19-26), Impact Fees section. |
| Impact Fee — Transportation (Multi Family, low-rise) | $349 | Tooele County adopted Fee Schedule (effective 5-19-26), Impact Fees section. |
| Impact Fee — Transportation (Multi Family, low-rise with ground-floor commercial) | $178 | Tooele County adopted Fee Schedule (effective 5-19-26), Impact Fees section. |
Demolition Permit
VerifiedRequired for demolition of any building or structure in unincorporated Tooele County. The county's combined Building Permit Application form explicitly covers 'Construction and Demolition' under a single application; no separate demolition-specific fee or bond line item was found in the county's adopted Fee Schedule.
Verified 2026-07-03 · Source
Requirements
- Demolition, moving, or change of use of any building or structure within unincorporated Tooele County requires a permit, per Utah state and Tooele County law
- Same combined Building Permit Application and General Instructions form used for new construction
Required documents
- RequiredBuilding Permit Application and General InstructionsTooele County's combined application form (building-permit-012225.pdf) marked for demolition scope of work.
Fee schedule
| Fee type | Amount | Notes |
|---|---|---|
| Demolition Permit Fee | Contact Tooele County Development Department for current amount | Tooele County's adopted Fee Schedule (effective 5-19-26) lists a valuation-based Building Permit Fee formula and a 1% state surcharge, but no separate flat demolition-specific fee or bond line item… Show full citationHideTooele County's adopted Fee Schedule (effective 5-19-26) lists a valuation-based Building Permit Fee formula and a 1% state surcharge, but no separate flat demolition-specific fee or bond line item was found anywhere in the 21-page fee schedule PDF as of 2026-07-04. The county's Building Permits page states state/county law requires a permit to 'demolish' a structure, and the application form covers demolition, but no distinct dollar figure for demolition alone is published. Omitted rather than estimated. |
Commercial Building Permit
VerifiedRequired for new commercial construction in unincorporated Tooele County, regulated by the statewide-adopted 2024 IBC (Utah Code §15A-2-103; the county's own Building Permits page still lists the 2021 IBC as of live re-check 2026-07-16). The Building Permit Fee follows the same Uniform Building Code valuation-based mechanism used for residential construction; commercial development also triggers the county's Transportation Impact Fee at a distinct 'Non-Residential/Commercial' per-square-foot rate.
Verified 2026-07-19 · Source
Requirements
- New commercial construction regulated by the statewide-adopted 2024 IBC (Utah Code §15A-2-103); Tooele County's own Building Permits page cites 2021-cycle editions (live-checked 2026-07-16 — see codesAdopted)
- Complete and submit all supporting documents at time of submittal — incomplete applications are not accepted
- Dimensioned site plan showing north direction, lot lines, adjacent streets/rights-of-way, existing structures, proposed construction, and motor vehicle access
- Site Plan Approval from the Tooele County Fire Department
- One complete set of construction plans, including structural, electrical, mechanical, and plumbing design
- Utility approval forms (gas, electric, sewer, water) if new service or additional load is being added
Required documents
- RequiredBuilding Permit Application and General InstructionsTooele County's combined application form (building-permit-012225.pdf) covering Building, Electrical, HVAC, Plumbing, Energy, Occupancy, Sign, Construction, and Demolition permits, used for both residential and commercial submittals.
- RequiredDimensioned Site PlanMust carry Site Plan Approval from the Tooele County Fire Department; must show north direction, lot lines, adjacent rights-of-way, existing structures, proposed construction, and motor vehicle access.
- RequiredComplete Set of Construction PlansStructural, electrical, mechanical, and plumbing design; proof of compliance with the adopted energy code.
Fee schedule
| Fee type | Amount | Notes |
|---|---|---|
| Building Permit Fee | Valuation-based, per Uniform Building Code fee-calculation provisions | Tooele County adopted Fee Schedule (effective 5-19-26): 'The Building Official shall determine valuations... Show full citationHideTooele County adopted Fee Schedule (effective 5-19-26): 'The Building Official shall determine valuations... using... Building Valuation Data publication issued... by the International Conference of Building Officials... The fee shall then be determined by reference to the Uniform Building Code provisions regarding the calculation of fees.' Same mechanism applies to commercial as to residential per the county's Fee Schedule — no separate valuation table specific to commercial occupancy classifications was found published (distinct from neighboring Iron County, which does publish per-occupancy-classification valuation rates). |
| State Surcharge | 1% of the building permit fee | Tooele County adopted Fee Schedule (effective 5-19-26); Tooele County remits 80% of the surcharge collected to DOPL. |
| Transportation Impact Fee — Non-Residential/Commercial | $0.259 per square foot | Tooele County adopted Fee Schedule (effective 5-19-26), Impact Fees section, Transportation table: 'Non-Residential/Commercial ... Show full citationHideTooele County adopted Fee Schedule (effective 5-19-26), Impact Fees section, Transportation table: 'Non-Residential/Commercial ... $0.259 per square foot.' A separate, more granular land-use-category table (e.g., 'General Commercial/Shopping Center $1,360 per 1,000 square feet,' 'General Office $561 per 1,000 square feet') appears under a 'North Tooele Fire District' heading in the same Impact Fees section, with a note that 'Table 7.5 of the LRB IFFP Impact Fee Study will be used' for land uses not covered by the standard rate — reported here without asserting whether that granular table is scoped only to the North Tooele Fire District or applies more broadly, since the fee schedule's own formatting does not make the scope unambiguous. |
| Impact Fee — Tooele County Public Safety (North Tooele Fire District, commercial) | $1,688 per 1,000 square feet | Tooele County adopted Fee Schedule (effective 5-19-26), Impact Fees section, listed under the North Tooele Fire District heading; applies within that district's boundary rather than county-wide. |
| Impact Fee — Tooele County Fire (North Tooele Fire District, commercial) | $861 per 1,000 square feet | Tooele County adopted Fee Schedule (effective 5-19-26), Impact Fees section, North Tooele Fire District heading. |
Commercial Tenant Improvement / Tenant Finish Permit
Required for tenant improvement and remodel work inside an existing commercial building in unincorporated Tooele County. No distinct tenant-improvement fee line was found in the county's adopted Fee Schedule — the same valuation-based Building Permit Fee mechanism (Uniform Building Code provisions) used for new commercial construction applies, scaled to the tenant improvement's own valuation.
Reviewed 2026-07-19 · Source
Requirements
- Tenant improvement or remodel work within an existing commercial building, regulated by the statewide-adopted 2024 IBC
- Complete set of construction plans for the scope of work
- Utility approval forms if new service or additional load is being added
Required documents
- RequiredBuilding Permit Application and General InstructionsSame combined application form used for all Tooele County building permit types.
- RequiredConstruction PlansCovering the tenant improvement scope, including any structural, electrical, mechanical, or plumbing changes.
Fee schedule
| Fee type | Amount | Notes |
|---|---|---|
| Building Permit Fee | Valuation-based, per Uniform Building Code fee-calculation provisions | Tooele County adopted Fee Schedule (effective 5-19-26) — same mechanism used for new commercial construction; no distinct tenant-improvement valuation table is published, so this general mechanism applies, scaled to the tenant improvement's own valuation. |
| State Surcharge | 1% of the building permit fee | Tooele County adopted Fee Schedule (effective 5-19-26). |
Sources & verification
Verified against official sources. Last reviewed 2026-07-03.
Fee schedules
Applications & forms
Codes & ordinances
Department & other records
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Unincorporated Tooele County building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.