Unincorporated Tooele County building permits

Verified

Department contacts, adopted codes, permit types, fees, and gotchas for Unincorporated Tooele County, Utah.

Last verified 2026-07-03 · Source · Embed this page’s badge · Version history

Building department

Address
47 South Main Street, Room 208, Tooele, UT 84074
Phone
(435) 843-4737
Office hours
Not published on tooeleco.gov as of 2026-07-04 — the Building Inspection page and Building Permits page list contact info (phone, fax, email) but no posted office hours. General county offices are listed at 47 S. Main St., Tooele, UT 84074, main line (435) 843-3100. A separate Building & Zoning Questions line, (435) 843-3160, and a Fire Department Questions line, (435) 833-8125, appear on the county's own Building Permit Application Instructions form (building-permit-012225.pdf).

Inspection guide

See how inspections work in Unincorporated Tooele County — sequence, scheduling & re-inspection fees.

Codes adopted

Utah adopts construction codes statewide under Utah Code Title 15A (State Construction and Fire Codes Act), enforced by every jurisdiction. Chapter 4 of Title 15A codifies Legislature-enacted amendments for specific named jurisdictions (e.g., Park City, Salt Lake City, Sandy City) as part of the state construction code. Through June 30, 2026, the editions in force under Utah Code § 15A-2-103 are the 2021 IBC (with Appendices C and J), 2021 IRC, 2021 IPC, 2021 IMC, 2021 IFGC, 2021 IECC, 2021 IEBC, and 2021 ISPSC (residential provisions), together with the 2023 NEC. Effective July 1, 2026, § 15A-2-103 adopts the 2024 editions of the IBC, IPC, IMC, IFGC, IECC, IEBC, and ISPSC; the IRC remains the 2021 edition and the NEC remains the 2023 edition. Note: residential energy requirements are modified by statewide amendments, and several Utah jurisdictions document their residential energy provisions at the 2015 IECC level rather than the adopted IECC year — confirm the applicable residential energy code with your local jurisdiction. Always confirm the edition in force with your local jurisdiction.

  • 2024 International Building Code (IBC), including Appendices C and J — governs per Utah Code §15A-2-103(1)(a) (https://le.utah.gov/xcode/Title15A/Chapter2/15A-2-S103.html), in force statewide since 7/1/2026 and binding on counties under §15A-1-204. Tooele County's own Building Permits page still lists the 2021 IBC (no appendices specified) — live-checked 2026-07-16, the county's own page has not been updated to the current statewide edition.
  • 2021 International Residential Code (IRC), including Appendix AQ — governs per Utah Code §15A-2-103(1)(b)/(c); this edition is UNCHANGED from the prior code cycle. Tooele County's own Building Permits page lists the 2021 IRC — live-checked 2026-07-16, consistent with the current statute on the base edition.
  • 2024 International Mechanical Code (IMC) — governs per Utah Code §15A-2-103(1)(e). Tooele County's own Building Permits page still lists the 2021 IMC — live-checked 2026-07-16, lags the current statewide edition.
  • 2024 International Plumbing Code (IPC) — governs per Utah Code §15A-2-103(1)(d). Tooele County's own Building Permits page still lists the 2021 IPC — live-checked 2026-07-16, lags the current statewide edition.
  • 2024 International Fuel Gas Code (IFGC) — governs per Utah Code §15A-2-103(1)(f). Tooele County's own Building Permits page still lists the 2021 IFGC — live-checked 2026-07-16, lags the current statewide edition.
  • 2024 International Energy Conservation Code (IECC) — one code, no residential/commercial split, per Utah Code §15A-2-103(1)(h). Tooele County's own Building Permits page still lists the 2021 IECC — live-checked 2026-07-16, lags the current statewide edition.
  • 2021 International Fire Code (IFC) — per Tooele County's own Building Permits page, live-checked 2026-07-16 and unchanged. Utah Code §15A-2-103 does NOT adopt the IFC (fire codes are addressed separately under Title 15A, Chapter 5, the State Fire Code Act) — this edition is left as the county's own published figure rather than reconciled to §15A-2-103, since that statute does not govern it. NOTE: Tooele County's own list includes the IFC explicitly (cited directly in its Fire Protection Criteria for Unincorporated Tooele County, referencing IFC 503.1.1 and Appendix D); Tooele City's own sheet does not list a standalone IFC edition. This is a genuine difference between the two jurisdictions' own published code lists, reported as each jurisdiction states it.
  • 2023 National Electrical Code (NEC) — governs per Utah Code §15A-2-103(1)(g); this edition is UNCHANGED from the prior code cycle, and Tooele County's own Building Permits page already correctly lists the 2023 NEC — live-checked 2026-07-16, no lag on this edition.
  • 2024 International Existing Building Code (IEBC) — governs statewide per Utah Code §15A-2-103(1)(i). Tooele County's own Building Permits page does NOT list the IEBC at all — live-checked 2026-07-16; added here per the statute, not omitted from this file.
  • Residential provisions of the 2024 International Swimming Pool and Spa Code (ISPSC) — governs statewide per Utah Code §15A-2-103(1)(n). Tooele County's own Building Permits page does NOT list the ISPSC at all — live-checked 2026-07-16; added here per the statute, not omitted from this file.
  • Modular Building Institute (MBI) Standards 1200 and 1205 — governs statewide per Utah Code §15A-2-103(1)(o). Not listed on Tooele County's own Building Permits page — live-checked 2026-07-16.
  • Utah State Amendments to the Building Codes (Utah Code Title 15A, Chapter 3) — per Tooele County's own Building Permits page, linking directly to le.utah.gov Title 15A Chapter 3.

Permit types & fees

New residential construction activity

New privately-owned residential construction only

Housing units authorized by building permits for new privately-owned residential construction — this is not total permit volume (no commercial permits or remodels).

Latest month (2026-05)
45units

43 buildings · $16.9M valuation

Trailing 12 months
471units

12 of 12 months reported · #22 in Utah coverage by units

Year to date (2026 YTD through 2026-05)
183units

162 buildings · $77.8M valuation

Full year 2025
523units

460 buildings · $191.5M valuation

County-wide figures: BPS reports county-wide totals; this jurisdiction is the unincorporated remainder outside Tooele City and other incorporated municipalities (Grantsville, Stockton, Lake Point, Vernon, Rush Valley, Wendover, Erda) — county totals include those incorporated places.

Source: U.S. Census Bureau, Building Permits Survey (BPS), 2026-05 vintage. Census survey data — separate from the permit-requirements verification above. All Utah building activity

Tips & gotchas

  • Tooele County (unincorporated areas, department at tooeleco.gov) is a distinct jurisdiction from Tooele City (tooelecity.gov) — this file covers ONLY unincorporated Tooele County, i.e., areas outside Tooele City and the other incorporated municipalities (Grantsville, Stockton, Lake Point, Vernon, Rush Valley, Wendover, Erda). Verify you are on tooeleco.gov sources, not tooelecity.gov, when researching this jurisdiction.
  • Tooele County's own adopted code list includes the 2021 International Fire Code (IFC) explicitly, and the county's Fire Department issues its own 'Fire Protection Criteria for Unincorporated Tooele County (Outside of North Tooele Fire District)' governing fire apparatus access — a requirement not present in Tooele City's own building-codes sheet in this corpus.
  • Tooele County's own design criteria differ from Tooele City's: Wind Speed 115 mph (county, IRC projects) vs. 105 mph 3-second gust (city); Ground Snow Load 35 psf (county, IRC) vs. USU Utah Snow Load tool with ASCE 7-16 Chapter 7 (city) — reported exactly as each jurisdiction's own source states, not reconciled or assumed identical.
  • Tooele County's own code list does NOT include the International Existing Building Code (IEBC) or International Swimming Pool and Spa Code (ISPSC) as of 2026-07-16 (re-confirmed live) — reported as published, not assumed to match neighboring jurisdictions that do list these. Both codes apply statewide regardless, per Utah Code §15A-2-103(1)(i)/(n), and are added to codesAdopted above sourced to the statute rather than to the county's own (silent) page.
  • 2026-07-16 codesAdopted re-verification: Utah Code §15A-2-103 (live-checked at the canonical le.utah.gov URL, current version 'Effective 7/1/2026') now governs statewide construction codes for counties per §15A-1-204, adopting 2024 IBC/IMC/IPC/IFGC/IEBC/IECC and residential 2024 ISPSC, while IRC stays 2021 and NEC stays 2023 — Tooele County's own Building Permits page already correctly lists the 2023 NEC (no lag there), but still lists 2021-cycle IBC/IMC/IPC/IFGC/IECC (live-checked 2026-07-16, unchanged) and does not list IEBC, ISPSC, or MBI Standards 1200/1205 at all. IFC (2021, per the county's own page) is outside §15A-2-103's scope — it falls under Title 15A Chapter 5 — and is left as the county's own published figure. The statute is stated as governing above; the county's page is preserved as history.
  • Tooele County bundles multiple impact fees (Parks, Public Safety, Fire, Transportation, plus district-specific fees like North Tooele Fire District or Stansbury Park Service Agency depending on location) directly into the building permit fee under Ordinance 2024-07 (adopted 9/3/2024, effective 12/2/2024) — the department states on its own website it 'does not have authority to waive all or part of these fees.'
  • No jurisdiction-published plan-review or permit-issuance turnaround time (business or calendar days) was found for any permit type as of 2026-07-04 — reviewTimelineDays is honestly null with a note rather than estimated, matching the same gap already documented for sibling jurisdiction Tooele City in this corpus.
  • Tooele County does not release detailed building-permit issuance information directly to the public on its own website; it directs inquiries to the Utah State Construction Registry (a state-run public database of issued permits, searchable by jurisdiction) — per the county's own Building Inspection page.
  • Tooele County Development/Building Inspection contacts as of 2026-07-04: Building Inspection and Code Compliance, 47 South Main Street Room 208, Tooele, UT 84074, (435) 843-4737 (fax (435) 843-3252), building@tooeleco.gov; a separate Building & Zoning Questions line, (435) 843-3160, and Fire Department Questions line, (435) 833-8125 (Fire Marshal Anthony Bott, anthony.bott@tooeleco.org), are published on the county's own Building Permit Application form.
  • Rooftop solar PV installations on a home or business require the same Building Permit (structural, via the county's combined application) plus a standard electrical permit for wiring/inverter -- the county's adopted Fee Schedule (effective 5-19-26) contains no 'solar' or 'photovoltaic' line item (confirmed by direct text search of the full 21-page PDF, 2026-07-19), so the general valuation-based Uniform Building Code fee mechanism applies with no distinct solar tier. (Large utility-scale 'Solar Energy Systems' feeding off-site users are a separate Conditional Use in the M-G Manufacturing zone under the county's Land Use Ordinance -- a distinct zoning category from residential/commercial rooftop PV and not addressed by this file.)
  • Permits become null and void if work is not commenced within 180 days of issuance, if a progress inspection does not occur within 180 days, or if work is suspended/abandoned for 180+ days after commencement — mirrors the same 180-day rule used by Tooele City, per each jurisdiction's own application form.