Fire Sprinkler & Fire Alarm System Permit — Unincorporated Tooele County, Utah · Requirements sheet
Verified 2026-07-20 · Source: https://www.ntfdutah.gov/files/48f72d471/NTFD+Fee+Schedule+2024.pdf
PermitBase is an independent reference and is not affiliated with any government agency. Requirements change and vary by project — confirm current details with the building department before you submit.
Fire Sprinkler & Fire Alarm System Permit in Unincorporated Tooele County, Utah
Fire sprinkler and fire alarm system permitting in unincorporated Tooele County is handled by whichever fire authority has jurisdiction over the property's location, not by the County's Building Permits office. A large share of unincorporated Tooele County (including Erda, Lake Point, Pine Canyon, and Stansbury Park) sits within the North Tooele Fire District (NTFD), which publishes a detailed, itemized fee schedule covering fire alarm and fire sprinkler system plan review, permits, and inspections separately from the County building permit. Properties outside the NTFD boundary fall under the Tooele County Fire Department directly (Fire Chief/Fire Warden Daniel B. Walton; Fire Marshal Anthony Bott, (435) 833-8125, anthony.bott@tooeleco.org) -- this jurisdiction's own residential/commercial-building-permit entries already document that the County Fire Department requires Site Plan Approval and enforces the county's 'Fire Protection Criteria for Unincorporated Tooele County (Outside of North Tooele Fire District)' for fire-apparatus-access-road compliance. Re-chased 2026-07-20: no distinct, separately published fire sprinkler/alarm PERMIT fee schedule for the County Fire Department itself (outside NTFD) exists -- confirmed by checking the county's current consolidated Fee Schedule (effective 5-19-26) specifically for a fire alarm/sprinkler line item and finding none (only per-dwelling-unit/per-square-foot 'Tooele County Fire' IMPACT fees, a different one-time development fee already documented in this file's building-permit entries). Sprinkler/alarm plan review for properties outside NTFD is therefore folded into the standard valuation-based Tooele County building permit fee, with no separate dollar figure. This entry documents NTFD's separately verified fire sprinkler/alarm permitting process and fees, plus the countywide sprinkler-mandate trigger conditions that apply outside NTFD under Tooele County Code § 6-17-10.
Verified 2026-07-20 · Source
When you need this permit
- New installation, alteration, or extension of a fire sprinkler system or fire alarm system on a property within the North Tooele Fire District (Erda, Lake Point, Pine Canyon, Stansbury Park, and surrounding unincorporated areas)
- Automatic fire sprinkler systems are mandatory in new one- and two-family dwellings and townhomes built or moved within NTFD boundaries if ANY of the following apply, per NTFD Ordinance No. 2015-001: (A) the structure is in an urban-wildland interface area and does not meet Utah Code 65A-8-203(3)(a) / Utah Administrative Code R652-122-200 minimum wildland fire standards; (B) the structure is in an area without a public water distribution system with fire hydrants per Utah Administrative Code R309-550-5; (C) the only fire apparatus access road has a grade greater than 10% for more than 500 continual feet; (D) the water supply does not provide at least 750 gallons per minute for 30 minutes where living space exceeds 5,000 but is at or under 10,000 square feet; or (E) the water supply does not provide at least 1,000 gallons per minute for 30 minutes where living space exceeds 10,000 square feet
- Outside the NTFD boundary (i.e., directly under Tooele County Fire), automatic fire sprinkler systems are mandatory under Tooele County Code § 6-17-10 if ANY of the following apply: (A) the structure is in a wildland-urban interface area and does not meet Utah Code § 65A-8-203(4)(a) / Utah Administrative Code R652-122-1300 minimum wildland fire standards; (B) the area lacks a public water distribution system with fire hydrants per Utah Administrative Code R309-550-5; (C) the only fire apparatus access road has a grade greater than 10% for more than 500 continual feet; (D) the dwelling unit's total floor area exceeds 10,000 square feet; or (E) the dwelling unit's total floor area is double the average of unsprinklered homes (10,000 sq ft or under) in the same subdivision -- with a narrow exception for single-lot subdivisions outside the wildland-urban interface with 50 feet of defensible space on all sides
- Fire sprinkler and fire alarm plan review and permitting is a separate process and fee from the Tooele County building permit -- coordinate both in parallel
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 2 required documents checked.
This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29 →
Fee schedule
Review timeline
Inspection process
- 1
Fire Alarm System Inspection
Included in the $200.00 Fire Alarm System Permit fee per NTFD's fee schedule.
- 2
Fire Sprinkler System Flow, Hydrostatic, and Final Inspections
3 inspections (flow, hydro, final) are included in the $300.00 Fire Sprinkler System Permit fee; each additional inspection beyond those 3 is billed at $100.00, per NTFD's fee schedule.
See the full Unincorporated Tooele County inspection guide — scheduling & re-inspection fees →
Tips
- Fire sprinkler and fire alarm permitting is NOT part of the Tooele County building permit fee (which already separately bundles Parks, Public Safety, Fire, and Transportation impact fees per this jurisdiction's commercial-building-permit entry) -- it is a distinct process and fee charged directly by whichever fire authority has jurisdiction, in addition to the County building permit and its bundled impact fees.
- Whether North Tooele Fire District's fee schedule applies depends on the property's location: NTFD covers Erda, Lake Point, Pine Canyon, and Stansbury Park. Properties in unincorporated Tooele County outside the NTFD boundary fall under the Tooele County Fire Department (Fire Marshal Anthony Bott, (435) 833-8125). Re-chased 2026-07-20 against the county's current consolidated Fee Schedule (effective 5-19-26): no standalone fire sprinkler/alarm plan-review or permit fee line exists for the County Fire Department -- only per-unit/per-square-foot 'Tooele County Fire' impact fees (a separate one-time development charge, not a sprinkler/alarm permit fee). Sprinkler/alarm review outside NTFD is folded into the standard valuation-based County building permit fee with no separate dollar figure; confirm specifics with the Fire Marshal's office before applying.
- NTFD's fee schedule prices the Fire Sprinkler System Permit (which includes flow, hydrostatic, and final inspections) at a flat $300.00 regardless of the 0-3,000 / 3,001-10,000 / 10,001+ square-foot tier -- only the separate Plan Review fee scales with square footage.
- Under NTFD Ordinance No. 2015-001, a residential automatic fire sprinkler system is not universally required -- it becomes mandatory only when specific conditions are met (wildland-urban interface without minimum wildfire standards, no hydrant-served public water system, a sole fire-apparatus access road graded over 10% for more than 500 feet, or inadequate fire flow relative to the home's living-space square footage).
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-07-20.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Unincorporated Tooele County building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Other permits in Unincorporated Tooele County
Fire Sprinkler & Fire Alarm System Permit in other cities
Compare fire sprinkler & fire alarm system permit fees across Utah →
Look up this fee in a different city →