Change of Use / Certificate of Occupancy Permit in Unincorporated Tooele County, Utah

Unincorporated Tooele County has no standalone Change of Use or Certificate of Occupancy application, checkbox, or fee category distinct from the general Building Permit process. The county's own Building Permits page states that state and county law require a permit for anyone who wants to 'construct, enlarge, alter, repair, move, demolish or change the use of any building or structure,' and the combined Building Permit Application and General Instructions form (building-permit-012225.pdf) lists 'Occupancy' among the permit types it covers (Building, Electrical, HVAC, Plumbing, Energy, Occupancy, Sign Permit, Construction and Demolition), but no dedicated occupancy-only checkbox, form, or fee line was found on the form itself, in the county's Applications & Forms index, or in its adopted Fee Schedule. A Certificate of Occupancy is issued following the Final inspection under the standard building-permit process, consistent with the 'Final / Certificate of Occupancy' inspection already documented in this file's residential-building-permit entry.

Reviewed 2026-07-22 · Source

When you need this permit

  • Change of use of any existing building or structure requires a permit, per Tooele County's own Building Permits page: 'State and County laws require that anyone who wants to construct, enlarge, alter, repair, move, demolish or change the use of any building or structure must first get a permit.'
  • Submit the same combined Building Permit Application and General Instructions form (building-permit-012225.pdf) used for all other permit types; its own instructions list 'Occupancy' among the permit categories it covers, alongside Building, Electrical, HVAC, Plumbing, Energy, Sign Permit, Construction, and Demolition.
  • Complete application with proof of ownership and all supporting documents submitted at time of submittal — incomplete applications are not accepted.
  • Where a new use is established, curb, gutter, and sidewalk improvements may be required as a condition of a 'building permit or a use permit approval,' per Tooele County Land Use Ordinance Chapter 4, Section 4-17.
  • A Certificate of Occupancy is issued following the Final inspection under the standard building-permit process (see this file's residential-building-permit entry).

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 2 required documents checked.

This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29

Fee schedule

Building Permit Fee (change of use / occupancy)Tooele County adopted Fee Schedule (effective 5-19-26), Building Permit Fees section, uses the same ICC Building Valuation Data-based mechanism for all building permit types; checked specifically for a distinct 'change of use' or 'certificate of occupancy' line item and found none as of 2026-07-22. Omitted rather than estimated.
Valuation-based, per Uniform Building Code fee-calculation provisions
State SurchargeTooele County adopted Fee Schedule (effective 5-19-26): 'Tooele County shall assess and collect a surcharge equal to one percent of the building permit fee in compliance with Utah state law... shall remit eighty percent of the amount of the surcharge to have been assessed to said Division [DOPL].'
1% of the building permit fee

Review timeline

Plan review
Not published — contact the department

How long did your Change of Use / Certificate of Occupancy Permit permit actually take in Unincorporated Tooele County?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    Final / Certificate of Occupancy Inspection

    Final inspection confirming compliance for the new use or occupancy classification before a Certificate of Occupancy is issued, per the standard building-permit inspection sequence documented in this file's residential-building-permit entry.

See the full Unincorporated Tooele County inspection guide — scheduling & re-inspection fees →

Tips

  • Tooele County does not publish a standalone Change of Use or Certificate of Occupancy application form, checkbox, or fee — a genuine gap confirmed by checking the Building Permit Application form, the county's Applications & Forms index, and its adopted Fee Schedule as of 2026-07-22. Use the same combined Building Permit Application and General Instructions form used for all other permit types.
  • Contact Building & Zoning at (435) 843-3160 to confirm whether a specific change of use triggers full plan review (e.g., an occupancy-classification change under the adopted IBC) or only a re-inspection for the new use.
  • Tooele County Land Use Ordinance Chapter 4, Section 4-17 references a 'use permit approval' distinct in name from a building permit, tied to curb/gutter/sidewalk requirements when 'a new use is to be established' — the ordinance does not elaborate this into a separate standalone application process from the Building Permit Application.

Frequently asked questions

Yes. Tooele County's Building Permits page states that state and county law require a permit for anyone who wants to 'construct, enlarge, alter, repair, move, demolish or change the use of any building or structure.' Use the same combined Building Permit Application and General Instructions form used for new construction and demolition.

In Unincorporated Tooele County, the published Building Permit Fee (change of use / occupancy) is: Valuation-based, per Uniform Building Code fee-calculation provisions. Additional published fees: State Surcharge — 1% of the building permit fee. These are the jurisdiction's own published figures — see the fee schedule table and source citations on this page.

Unincorporated Tooele County does not publish a plan-review timeline for this permit. Contact Tooele County Development Department — Building Inspection and Code Compliance at (435) 843-4737 for current turnaround.

You'll need: Building Permit Application and General Instructions; Proof of Ownership. Depending on your project, Unincorporated Tooele County may also ask for: Construction Plans / Site Plan. See the required-documents checklist on this page for details on each.

Unincorporated Tooele County requires 1 inspection(s) for a change of use / certificate of occupancy permit, in order: Final / Certificate of Occupancy Inspection. Schedule each through Tooele County Development Department — Building Inspection and Code Compliance ((435) 843-4737).

Apply through Tooele County Development Department — Building Inspection and Code Compliance at 47 South Main Street, Room 208, Tooele, UT 84074. Phone: (435) 843-4737, email: building@tooeleco.gov. Office hours: Not published on tooeleco.gov as of 2026-07-04 — the Building Inspection page and Building Permits page list contact info (phone, fax, email) but no posted office hours. General county offices are listed at 47 S. Main St., Tooele, UT 84074, main line (435) 843-3100. A separate Building & Zoning Questions line, (435) 843-3160, and a Fire Department Questions line, (435) 833-8125, appear on the county's own Building Permit Application Instructions form (building-permit-012225.pdf).. Official information: https://www.tooeleco.gov/departments/development/building_inspection.php.

Unincorporated Tooele County, Utah has adopted: 2024 International Building Code (IBC), including Appendices C and J — governs per Utah Code §15A-2-103(1)(a) (https://le.utah.gov/xcode/Title15A/Chapter2/15A-2-S103.html), in force statewide since 7/1/2026 and binding on counties under §15A-1-204. Tooele County's own Building Permits page still lists the 2021 IBC (no appendices specified) — live-checked 2026-07-16, the county's own page has not been updated to the current statewide edition.; 2021 International Residential Code (IRC), including Appendix AQ — governs per Utah Code §15A-2-103(1)(b)/(c); this edition is UNCHANGED from the prior code cycle. Tooele County's own Building Permits page lists the 2021 IRC — live-checked 2026-07-16, consistent with the current statute on the base edition.; 2024 International Mechanical Code (IMC) — governs per Utah Code §15A-2-103(1)(e). Tooele County's own Building Permits page still lists the 2021 IMC — live-checked 2026-07-16, lags the current statewide edition.; 2024 International Plumbing Code (IPC) — governs per Utah Code §15A-2-103(1)(d). Tooele County's own Building Permits page still lists the 2021 IPC — live-checked 2026-07-16, lags the current statewide edition.; 2024 International Fuel Gas Code (IFGC) — governs per Utah Code §15A-2-103(1)(f). Tooele County's own Building Permits page still lists the 2021 IFGC — live-checked 2026-07-16, lags the current statewide edition.; 2024 International Energy Conservation Code (IECC) — one code, no residential/commercial split, per Utah Code §15A-2-103(1)(h). Tooele County's own Building Permits page still lists the 2021 IECC — live-checked 2026-07-16, lags the current statewide edition.; 2021 International Fire Code (IFC) — per Tooele County's own Building Permits page, live-checked 2026-07-16 and unchanged. Utah Code §15A-2-103 does NOT adopt the IFC (fire codes are addressed separately under Title 15A, Chapter 5, the State Fire Code Act) — this edition is left as the county's own published figure rather than reconciled to §15A-2-103, since that statute does not govern it. NOTE: Tooele County's own list includes the IFC explicitly (cited directly in its Fire Protection Criteria for Unincorporated Tooele County, referencing IFC 503.1.1 and Appendix D); Tooele City's own sheet does not list a standalone IFC edition. This is a genuine difference between the two jurisdictions' own published code lists, reported as each jurisdiction states it.; 2023 National Electrical Code (NEC) — governs per Utah Code §15A-2-103(1)(g); this edition is UNCHANGED from the prior code cycle, and Tooele County's own Building Permits page already correctly lists the 2023 NEC — live-checked 2026-07-16, no lag on this edition.; 2024 International Existing Building Code (IEBC) — governs statewide per Utah Code §15A-2-103(1)(i). Tooele County's own Building Permits page does NOT list the IEBC at all — live-checked 2026-07-16; added here per the statute, not omitted from this file.; Residential provisions of the 2024 International Swimming Pool and Spa Code (ISPSC) — governs statewide per Utah Code §15A-2-103(1)(n). Tooele County's own Building Permits page does NOT list the ISPSC at all — live-checked 2026-07-16; added here per the statute, not omitted from this file.; Modular Building Institute (MBI) Standards 1200 and 1205 — governs statewide per Utah Code §15A-2-103(1)(o). Not listed on Tooele County's own Building Permits page — live-checked 2026-07-16.; Utah State Amendments to the Building Codes (Utah Code Title 15A, Chapter 3) — per Tooele County's own Building Permits page, linking directly to le.utah.gov Title 15A Chapter 3.. Local amendments apply — see the Unincorporated Tooele County overview page for the full list.

No distinct application, checkbox, or fee line for a Change of Use or Certificate of Occupancy permit is published by Tooele County as of 2026-07-22. Change of use is processed through the same combined Building Permit Application and General Instructions form used for all other permit types, and a Certificate of Occupancy is issued following the standard Final inspection.