This is PermitBase’s published record for Provo as of 2026-06-30. It has since been superseded — see the current record. A historical record reflects what PermitBase had verified at that time; it may not capture a real-world change the jurisdiction had made but PermitBase had not yet verified, and it includes any errors we later corrected. Snapshots are never edited retroactively.
Provo building permits
VerifiedProvo, Utah — as published 2026-06-30.
Verified 2026-06-29 · Source
Codes adopted
Permit types & fees
Residential Building Permit
VerifiedRequired for new residential construction, additions, structural alterations, and any work regulated by the adopted 2021 IRC or 2021 IBC. The permit covers plumbing, electrical, and mechanical (MEP) for residential structures with four or fewer dwelling units — no separate MEP permits are required for those projects.
Verified 2026-06-29 · Source
Requirements
- New single-family or multi-family residential construction (up to 4 units)
- Additions or enlargements to existing residential structures
- Structural modifications — load-bearing wall removal, foundation alterations, beam additions
- Conversion of non-habitable space to habitable space
- Any work regulated by the 2021 IRC, per IRC § R105.1 as cited in Provo Building FAQ
Required documents
- RequiredBuilding PlansComplete construction drawings to scale — lot lines with property dimensions, setbacks, four elevations showing height from top back of curb to top of foundation and peak of roof (max 35 ft combined), floor plans with all rooms labeled, wall sections (continuous footing to roof), and grading plan indicating minimum 2% slope from house. Submit as PDF via provo.org/portal.
- RequiredSite PlanRecorded lot dimensions, building setback measurements, all hard surface drives and parking, grading profiles in two directions. Must match recorded lot dimensions.
- RequiredEnergy Code Compliance (REScheck or equivalent)Required per Provo residential plan review checklist (Doc 820, updated 10/2024). Demonstrates compliance with the adopted IECC.
- OptionalEngineered Truss PlansSealed truss layouts for new construction using engineered trusses.
- OptionalStructural/Engineering CalculationsRequired for large homes or homes with extensive beams. Soils report required for all homes on the east side of Provo (hillside/fault zone). All calculations must be transferred to and detailed on plans.
- OptionalOwner/Builder CertificationRequired if work is performed by the owner rather than a licensed contractor. Utah DOPL form filed with Provo City Building Division.
Fee schedule
| Fee type | Amount | Notes |
|---|---|---|
| Building Permit Fee — valuation-based (1997 UBC Fee Chart) | Building permit fee is 'Based on the 1997 UBC Fee Chart' with building valuation 'Based upon International Code Council Building Valuation Data' (Provo City Consolidated Fee Schedule, Inspection Fees). The 1997 UBC Table 1-A brackets: $23.50 for the first $500; $3.05 per additional $100 to $2,000; $69.25 + $14 per additional $1,000 to $25,000; $391.75 + $10.10 per additional $1,000 to $50,000; $643.75 + $7 per additional $1,000 to $100,000; $993.75 + $5.60 per additional $1,000 to $500,000; $3,233.75 + $4.75 per additional $1,000 to $1,000,000; $5,608.75 + $3.65 per additional $1,000 above $1,000,000. | Provo City Consolidated Fee Schedule (provo.municipal.codes/Code/CFS, current through Ordinance 2026-13 passed April 28, 2026), Inspection Fees: 'For residential structures with not more than 4 units the building permit fee includes the plumbing, electrical, and mechanical permit fees.' — no separate MEP permits required for those structures. |
| Plan Review Fee | 65% of the building permit fee | Provo City Consolidated Fee Schedule (provo.municipal.codes/Code/CFS), Inspection Fees: 'Plan review — 65% of the Building Permit Fee.' Nonprofit organizations: 100%. |
| Reinspection Fee | $100.00 per system | Provo City Consolidated Fee Schedule (provo.municipal.codes/Code/CFS), Inspection Fees: 'Reinspection fee — $100.00 per system.' |
Electrical Permit
VerifiedRequired for electrical work in Provo. For residential structures with four or fewer dwelling units, electrical is included in the building permit fee — a separate electrical permit is not required when pulled alongside a building permit for those structures. Standalone electrical permits (e.g., panel upgrades, service changes, EV charger circuits on existing structures) require a separate permit with valuation-based fees per the 1997 UBC table.
Verified 2026-06-29 · Source
Requirements
- New electrical circuits or wiring installations (standalone, not part of a building permit for ≤4-unit residential)
- Electrical panel upgrades or service entrance changes
- EV charger circuit installation on existing structure
- Solar PV electrical connections
- Generator connections
Required documents
- RequiredPermit ApplicationSubmit via provo.org/portal. Include panel amp size and location, smoke detector locations, and GFCI locations per Provo building requirements.
- OptionalElectrical Plan or Single-Line DiagramRequired for service upgrades and new construction — panel schedule and circuit layout.
- OptionalContractor License or Owner/Builder CertificationUtah DOPL electrical contractor license for work by a contractor; Utah allows homeowners to perform electrical work on their own primary residence with a permit.
Fee schedule
| Fee type | Amount | Notes |
|---|---|---|
| Electrical Inspection / Permit Fee | $75.00 (residential standalone). Commercial Electrical: $175.00. Electrical service charge: $75.00. Inspection fee: $0.02 per sq. ft. ($75.00 minimum). | Provo City Consolidated Fee Schedule (provo.municipal.codes/Code/CFS, current through Ordinance 2026-13 passed April 28, 2026), Inspection Fees: 'Electrical Inspection — $75.00; Commercial Electrical — $175.00; Service charge — $75.00; Inspection fee — $0.02 per sq. ft., $75.00 minimum.' |
| Included with building permit (residential ≤4 units) | No separate charge | Provo City Consolidated Fee Schedule, Inspection Fees: 'For residential structures with not more than 4 units the building permit fee includes the plumbing, electrical, and mechanical permit fees.' A standalone electrical permit applies only to work not covered by a residential building permit. |
Plumbing Permit
VerifiedRequired for plumbing installations, alterations, and repairs in Provo. For residential structures with four or fewer dwelling units, plumbing is included in the building permit fee. Standalone plumbing permits (e.g., water heater replacement, re-pipe on existing structure) require a separate permit with valuation-based fees.
Verified 2026-06-29 · Source
Requirements
- New plumbing fixture installations (sinks, toilets, showers) — standalone on existing structure
- Water heater installation or replacement
- Water line or sewer line replacement or extension
- Gas line installation or modification
- Backflow prevention device installation
Required documents
- RequiredPermit ApplicationSubmit via provo.org/portal. Include water heater type, size, and fuel source for water heater permits.
- OptionalPlumbing PlanGas piping schematics required for new construction — sizing, lengths, and BTU at service outlets from meter per Provo residential plan review checklist.
- OptionalContractor License or Owner/Builder CertificationUtah DOPL plumbing contractor license; Utah allows homeowners to perform plumbing work on their own primary residence.
Fee schedule
| Fee type | Amount | Notes |
|---|---|---|
| Plumbing Inspection / Permit Fee | $75.00 minimum (including issuance of permit) + $20.00 first fixture + $6.00 each additional fixture + $6.00 each water heater. | Provo City Consolidated Fee Schedule (provo.municipal.codes/Code/CFS, current through Ordinance 2026-13 passed April 28, 2026), Inspection Fees: 'Plumbing Inspection — Minimum fee, including issuance of permit $75.00; First fixture $20.00; Each additional fixture $6.00; Each water heater $6.00.' |
| Included with building permit (residential ≤4 units) | No separate charge | Provo City Consolidated Fee Schedule, Inspection Fees: building permit for residential structures with not more than 4 units includes the plumbing permit fee. |
Mechanical / HVAC Permit
VerifiedRequired for heating, ventilation, and air conditioning installations, replacements, and ductwork modifications in Provo. For residential structures with four or fewer dwelling units, mechanical is included in the building permit. Standalone mechanical permits require separate application.
Verified 2026-06-29 · Source
Requirements
- Furnace or boiler installation or replacement (standalone on existing structure)
- Air conditioning system installation or replacement
- Ductwork installation or major modification
- Evaporative cooler installation
- Fireplace or wood-burning stove installation (may also require a gas permit)
Required documents
- RequiredPermit ApplicationSubmit via provo.org/portal. Include equipment type, BTU rating, and location.
- OptionalEquipment SpecificationsManufacturer data sheets for furnace, AC, heat pump, or evaporative cooler.
Fee schedule
| Fee type | Amount | Notes |
|---|---|---|
| Mechanical Inspection / Permit Fee | $75.00 minimum fee (residential). Commercial Mechanical: $175.00. | Provo City Consolidated Fee Schedule (provo.municipal.codes/Code/CFS, current through Ordinance 2026-13 passed April 28, 2026), Inspection Fees: 'Mechanical Inspection — Minimum fee $75.00; Commercial Mechanical $175.00.' |
| Included with building permit (residential ≤4 units) | No separate charge | Provo City Consolidated Fee Schedule, Inspection Fees: building permit for residential structures with not more than 4 units includes the mechanical permit fee. |
Roofing Permit
VerifiedRequired for roof replacement, re-roofing, and structural roof repairs in Provo. Permit fees are valuation-based per the 1997 UBC table.
Verified 2026-07-01 · Source
Requirements
- Complete roof replacement (tear-off and re-roof)
- Overlay of new roofing over existing (where allowed by code)
- Structural roof repairs or modifications
- Changes to roofing material type
Required documents
- RequiredPermit ApplicationScope of work, square footage, and material specifications. Submit via provo.org/portal.
- OptionalContractor License or Owner/Builder CertificationUtah DOPL contractor license or owner-builder form.
Fee schedule
| Fee type | Amount | Notes |
|---|---|---|
| Roofing Permit Fee (building permit, valuation-based) | Charged as a building permit per the 1997 UBC Fee Chart (no separate roofing line item in the fee schedule). Example: a $15,000 roofing job falls in the 1997 UBC $2,000–$25,000 bracket: $69.25 + (13 × $14) = $251.25. | Provo City Consolidated Fee Schedule (provo.municipal.codes/Code/CFS, current through Ordinance 2026-15 passed May 26, 2026; confirmed live 2026-07-01), Inspection Fees: building permit 'Based on the 1997 UBC Fee Chart,' Building Valuation 'Based upon International Code Council Building Valuation Data.' Fee schedule was checked directly (page rendered via browser after Cloudflare challenge) and contains no distinct 'Roofing' line item — roofing is confirmed permitted and charged solely as a valuation-based building permit, which is a grounded fee. |
| Plan Review Fee | 65% of the building permit fee | Provo City Consolidated Fee Schedule (confirmed live 2026-07-01), Inspection Fees: 'Plan review — 65% of the Building Permit Fee.' |
Solar Panel Permit
VerifiedRequired for installation of rooftop or ground-mounted solar photovoltaic (PV) systems in Provo. Provo City Power is the local utility — not Rocky Mountain Power. Net metering applications go to Provo City Power.
Verified 2026-06-29 · Source
Requirements
- Rooftop solar panel installation
- Ground-mounted solar array installation
- Battery storage system installation
- Electrical service upgrade for solar interconnection
Required documents
- RequiredSolar Site PlanDetailed site plan showing the home location, 3-foot clearance around all solar panels (required by Fire Code per Provo Solar PV Checklist), electrical meter panel, production meter/net meter, any backfed sub-panels, and all PV system components on the property.
- RequiredElectrical One-Line DiagramRequired per Provo Solar PV System Checklist (Doc 824, updated 08/2025). Must show: type of PV system (single inverter or micro-inverter), exact number and layout of modules and connections, all wire types and sizes, conduit types and sizes, detailed grounding wiring and connections, locations of all circuits and components, and ratings of all fuses or breakers.
- RequiredMounting System DetailsDetailed information on module mounting system and weight of all components on the roof. Support manufacturer specs must specify required support spacing based on Provo local wind and snow loads (31 lbs/sqft snow, 115 mph wind). Note if trusses are engineered, type and size of roof rafters, and type of roof covering.
- RequiredModule and Inverter Spec SheetsPV module spec sheets showing STC rated watts (Pmp), Vmp, Imp, Voc, and Isc — modules must be UL 1703 listed. Inverter spec sheets showing rated output; utility-tied inverters must meet UL 1741 and have ground fault protection.
- RequiredNet Metering Agreement (Provo City Power)A Net Metering Agreement must be submitted concurrently to Provo City Power per Provo Solar PV System Checklist (Doc 824).
Fee schedule
| Fee type | Amount | Notes |
|---|---|---|
| Net Metering / Solar Interconnection Fee (Provo City Power) | $375.00 (100–200 Amp residential); $825.00 (200–400 Amp commercial/residential). | Provo City Consolidated Fee Schedule (provo.municipal.codes/Code/CFS, current through Ordinance 2026-13 passed April 28, 2026), Energy/Utilities: 'Net Metering/Solar 100-200 Amp Residential $375.00; Net Metering/Solar 200-400 Amp Commercial/Residential $825.00.' Paid to Provo City Power (the municipal electric utility). |
| Building / Electrical Permit Fee | Building permit per the 1997 UBC Fee Chart; electrical inspection $75.00 if charged separately. Plan review 65% of the building permit fee. | Provo City Consolidated Fee Schedule, Inspection Fees: building permit 'Based on the 1997 UBC Fee Chart'; 'Electrical Inspection — $75.00'; 'Plan review — 65% of the Building Permit Fee.' |
Accessory Dwelling Unit (ADU) Permit
VerifiedRequired for construction of accessory dwelling units (basement apartments, detached ADUs) in Provo. ADU regulations are enforced strictly in this college-town jurisdiction.
Verified 2026-06-29 · Source
Requirements
- Property must be zoned for ADU use — confirm with Provo Planning Division
- ADU must meet building code and fire separation requirements
- Basement bedrooms require compliant egress windows (minimum 5.7 sq ft net clear opening, sill no higher than 44 inches above floor)
- Off-street parking must meet zone requirements
Required documents
- RequiredBuilding PlansComplete construction drawings showing unit layout, egress, fire separation, and all rooms labeled. Submit via provo.org/portal.
- RequiredSite PlanADU location, setbacks, and parking — must match recorded lot dimensions.
- RequiredEnergy Code Compliance (REScheck)Required per Provo residential plan review standards.
- OptionalOwner/Builder Certification or Contractor LicenseUtah DOPL licensed contractor or owner-builder form.
Fee schedule
| Fee type | Amount | Notes |
|---|---|---|
| Accessory Dwelling Unit Development Fee | $100.00 (single ADU); $500.00 (multiple ADUs). | Provo City Consolidated Fee Schedule (provo.municipal.codes/Code/CFS, current through Ordinance 2026-13 passed April 28, 2026), Development Fees: 'Accessory Dwelling Unit (Single) $100.00; Accessory Dwelling Unit (Multiple) $500.00.' |
| Building Permit Fee (includes MEP for ≤4 units) | Building permit per the 1997 UBC Fee Chart — includes plumbing, electrical, and mechanical for residential structures with 4 or fewer units. Plan review 65% of the building permit fee. | Provo City Consolidated Fee Schedule, Inspection Fees: building permit 'Based on the 1997 UBC Fee Chart'; MEP included for ≤4-unit residential; 'Plan review — 65% of the Building Permit Fee.' |
Deck Permit
VerifiedRequired for new deck construction, replacement, or structural modifications to existing decks in Provo. Fees are valuation-based per the 1997 UBC table.
Verified 2026-07-01 · Source
Requirements
- New deck construction attached to or detached from the house
- Decks more than 30 inches above grade
- Structural modifications to existing decks
- Adding or replacing a deck ledger
Required documents
- RequiredPermit Application and PlansFraming plan with beam/joist sizes, post locations, and footing details; site plan showing deck setbacks. Submit via provo.org/portal.
- OptionalLedger DetailConnection detail for attached decks per adopted IRC.
Fee schedule
| Fee type | Amount | Notes |
|---|---|---|
| Deck Permit Fee (building permit, valuation-based) | Charged as a building permit per the 1997 UBC Fee Chart (no separate deck line item in the fee schedule). Plan review 65% of the building permit fee. | Provo City Consolidated Fee Schedule (provo.municipal.codes/Code/CFS, current through Ordinance 2026-15 passed May 26, 2026; confirmed live 2026-07-01), Inspection Fees: building permit 'Based on the 1997 UBC Fee Chart,' Building Valuation 'Based upon International Code Council Building Valuation Data'; 'Plan review — 65% of the Building Permit Fee.' Fee schedule was checked directly and contains no distinct 'Deck' line item — decks are confirmed permitted and charged solely as a valuation-based building permit, which is a grounded fee. |
Basement Finish Permit
VerifiedRequired for finishing or remodeling an unfinished basement in Provo, including framing, electrical, plumbing, and mechanical work.
Verified 2026-07-01 · Source
Requirements
- Framing walls in an unfinished basement
- Adding a bedroom (requires egress window)
- Adding a bathroom or wet bar (requires plumbing permit if standalone)
- Electrical wiring for new rooms
- Structural modifications
Required documents
- RequiredFloor PlanLayout showing room sizes, all rooms labeled, egress windows, and door locations. Submit via provo.org/portal.
- OptionalElectrical, Mechanical, Plumbing PlansCircuit layout, panel capacity, smoke/CO detector locations, HVAC supply/return for new rooms, combustion air provisions for furnace room. Plumbing plan required if adding bathroom.
Fee schedule
| Fee type | Amount | Notes |
|---|---|---|
| Building Permit Fee (includes MEP for ≤4 units) | Building permit per the 1997 UBC Fee Chart — includes plumbing, electrical, and mechanical for residential structures with 4 or fewer units. Plan review 65% of the building permit fee. | Provo City Consolidated Fee Schedule (provo.municipal.codes/Code/CFS, current through Ordinance 2026-15 passed May 26, 2026; confirmed live 2026-07-01), Inspection Fees: building permit 'Based on the 1997 UBC Fee Chart,' Building Valuation 'Based upon International Code Council Building Valuation Data'; MEP included for ≤4-unit residential; 'Plan review — 65% of the Building Permit Fee.' Fee schedule was checked directly and contains no distinct 'Basement Finish' line item — basement finishes are confirmed permitted and charged solely as a valuation-based building permit, which is a grounded fee. |
Demolition Permit
VerifiedRequired for partial or complete demolition of structures in Provo. Federal NESHAP requirements apply for pre-1980 structures. Utah DEQ Air Quality must be contacted prior to any demolition (asbestos removal).
Verified 2026-06-29 · Source
Requirements
- Complete demolition of any structure
- Partial demolition involving structural elements
- Removal of load-bearing walls
- Structures built before approximately 1980 require NESHAP asbestos inspection
Required documents
- RequiredDemolition ApplicationScope of demolition, structure details, and disposal plan. Submit via provo.org/portal.
- OptionalAsbestos / NESHAP DocumentationContact Utah Division of Air Quality at (801) 535-4000 or airquality.utah.gov prior to demolition per Provo Residential Remodel Checklist (Doc 821, updated 08/2025). Required for structures that may contain asbestos-containing materials.
- RequiredUtility Disconnect ConfirmationProof that gas, electric, water, and sewer are disconnected prior to demolition.
Fee schedule
| Fee type | Amount | Notes |
|---|---|---|
| Demolition Permit Fee | $100.00 | Provo City Consolidated Fee Schedule (provo.municipal.codes/Code/CFS, current through Ordinance 2026-13 passed April 28, 2026), Development Fees: 'Demolition Permit $100.00.' (Relocation of a Building is likewise $100.00.) |
Sources & verification
Verified against official sources. Last reviewed 2026-06-29.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Provo building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.