Unincorporated Weber County building permits

Verified

Unincorporated Weber County, Utah — as published 2026-07-17.

Verified 2026-07-16 · Source

Codes adopted

2024 International Building Code (IBC) — Utah Code § 15A-2-103(1)(a); effective July 1, 2026 (replaces 2021 IBC). Weber County Code § 12-3-1 adopts the specific editions as adopted and amended by the State of Utah per Title 15A.2021 International Residential Code (IRC) — Utah Code § 15A-2-103(1)(b); continues in force after July 1, 20262024 International Plumbing Code (IPC) — Utah Code § 15A-2-103(1)(d); effective July 1, 2026 (replaces 2021 IPC)2024 International Mechanical Code (IMC) — Utah Code § 15A-2-103(1)(e); effective July 1, 2026 (replaces 2021 IMC)2024 International Fuel Gas Code (IFGC) — Utah Code § 15A-2-103(1)(f); effective July 1, 2026 (replaces 2021 IFGC)2023 National Electrical Code (NEC) — Utah Code § 15A-2-103(1)(g), current version effective 7/1/2026, superseded 1/1/2027, re-read live 2026-07-16 at le.utah.gov. Weber County Code § 12-3-1 (weber.municipalcodeonline.com, re-read live 2026-07-16) adopts codes by reference to Utah Code Title 15A generally and does not itself name a specific NEC edition; no '2020 NEC' reference could be found in the current codified text.2024 International Energy Conservation Code (IECC) — Utah Code § 15A-2-103(1)(h); effective July 1, 2026 (replaces 2021 IECC). Note: Utah statewide residential energy provisions effectively follow 2015 IECC residential per § 15A-2-104.2024 International Existing Building Code (IEBC) — Utah Code § 15A-2-103(1)(i); effective July 1, 2026 (replaces 2021 IEBC)2024 International Swimming Pool and Spa Code (ISPSC) — Utah Code § 15A-2-103(1)(n); effective July 1, 2026 (replaces 2021 ISPSC)

Permit types & fees

Residential Building Permit

Verified

Required for new residential construction, additions, structural alterations, and other work requiring plan review in Unincorporated Weber County, per Weber County Code Title 12 and the state-adopted International Building Code / International Residential Code.

Verified 2026-07-16 · Source

Requirements

  • New single-family or multi-family residential construction
  • Additions or structural alterations to existing structures
  • Conversion of non-habitable space to habitable space
  • Any work for which a building permit is required under the adopted codes

Required documents

  • RequiredOnline Building Permit ApplicationSubmit at countyofweberut.portal.opengov.com. All items must be complete before plans are accepted for review.
  • RequiredConstruction PlansComplete drawings to scale: floor plans, elevations, sections, and structural details. Submitted electronically through the OpenGov portal.
  • RequiredSite PlanProperty survey showing setbacks from property lines and footprint of structure.
  • RequiredEnergy Compliance (REScheck or equivalent)Required on-site for the insulation inspection per the Required Inspections List (Revised 1/7/21).
  • OptionalEngineered Truss PlansSealed truss layouts required for new construction with factory-built trusses.

Fee schedule

Fee typeAmountNotes
Building Permit — valuation $1.00–$2,000.00$69.25Weber County Code § 12-3-6 (Ord. 2020-25, 12/22/2020)
Building Permit — valuation $2,001.00–$25,000.00$69.25 for the first $2,000, plus $14.00 for each additional $1,000 or fraction thereof, to and including $25,000Weber County Code § 12-3-6 (Ord. 2020-25, 12/22/2020)
Building Permit — valuation $25,001.00–$50,000.00$391.75 for the first $25,000, plus $10.10 for each additional $1,000 or fraction thereof, to and including $50,000Weber County Code § 12-3-6 (Ord. 2020-25, 12/22/2020)
Building Permit — valuation $50,001.00–$100,000.00$643.75 for the first $50,000, plus $7.00 for each additional $1,000 or fraction thereof, to and including $100,000Weber County Code § 12-3-6 (Ord. 2020-25, 12/22/2020)
Building Permit — valuation $100,001.00–$500,000.00$993.75 for the first $100,000, plus $5.60 for each additional $1,000 or fraction thereof, to and including $500,000Weber County Code § 12-3-6 (Ord. 2020-25, 12/22/2020)
Building Permit — valuation $500,001.00–$1,000,000.00$3,233.75 for the first $500,000, plus $4.75 for each additional $1,000 or fraction thereof, to and including $1,000,000Weber County Code § 12-3-6 (Ord. 2020-25, 12/22/2020)
Building Permit — valuation over $1,000,000.00$5,608.75 for the first $1,000,000, plus $3.65 for each additional $1,000 or fraction thereofWeber County Code § 12-3-6 (Ord. 2020-25, 12/22/2020)
Plan Review — Single-Family Dwelling35% of the building permit feeWeber County Code § 12-3-8(2)(a) (Ord. 2020-25, 12/22/2020)
Plan Review — Commercial65% of the building permit feeWeber County Code § 12-3-8(2)(b) (Ord. 2020-25, 12/22/2020)
Plan Review — Over-Counter / Other$25.00 minimum, plus $55.00 per hour for review time in excess of 30 minutesWeber County Code § 12-3-8(2)(c) (Ord. 2020-25, 12/22/2020)
State Surcharge1% of the building permit fee (excludes plan review fees)Weber County Code § 12-3-8(1) (Ord. 2020-25, 12/22/2020)
Re-inspection Fee$115.00Weber County Code § 12-3-8(3) (Ord. 2020-25, 12/22/2020)
After-Hours Inspection$125.00 per hour (must be requested and approved by County Building Official)Weber County Code § 12-3-8(7) (Ord. 2020-25, 12/22/2020)
Permit Update Fee (permit inactive >180 days without inspection)$100.00 per year or any portion thereof, not to exceed $500.00Weber County Code § 12-3-8(4) (Ord. 2020-25, 12/22/2020)
Work-without-permit penaltyAdditional fee equal to the permit feeWeber County Code § 12-3-8(6) (Ord. 2020-25, 12/22/2020)

Electrical Permit

Verified

Required for electrical work in Unincorporated Weber County including new circuits, panel upgrades, service changes, and new construction wiring. Governed by the 2023 National Electrical Code (NEC) as adopted statewide by Utah Code § 15A-2-103(1)(g). EV charger/EVSE installation is electrical work and falls under this general Electrical Permit; the County's Code § 12-3-8 fee schedule (flat $150, excluding solar) does not publish an EV-specific line item.

Verified 2026-07-16 · Source

Requirements

  • New electrical circuits or wiring installations
  • Electrical panel upgrades or replacements
  • Service entrance changes
  • Adding or relocating outlets, switches, or fixtures
  • Generator or solar panel electrical connections (excluding solar installations, which have a separate fee)

Required documents

  • RequiredOnline Building Permit ApplicationSubmit at countyofweberut.portal.opengov.com
  • OptionalElectrical Plan / Single-Line DiagramPanel schedule and circuit layout for service upgrades and new construction
  • OptionalContractor LicenseValid Utah electrical contractor license (DOPL) for work not performed by the homeowner

Fee schedule

Fee typeAmountNotes
Electrical Permit (excluding solar installations)$150.00Weber County Code § 12-3-8(1) (Ord. 2020-25, 12/22/2020)
State Surcharge1% of the permit feeWeber County Code § 12-3-8(1) (Ord. 2020-25, 12/22/2020)
Re-inspection Fee$115.00Weber County Code § 12-3-8(3) (Ord. 2020-25, 12/22/2020)

EV Charger / EVSE Permit

Verified

Weber County does not publish a distinct EV charger / EVSE permit type or fee line item. EV charger/EVSE installation is electrical work and falls under the county's general Electrical Permit — Weber County Code § 12-3-8(1) (Ord. 2020-25, 12/22/2020) sets a flat $150.00 fee for electrical permits and explicitly excludes only solar installations (which are separately valuation-based) from that flat rate; no EV-specific carve-out or line item exists in the codified fee schedule.

Verified 2026-07-20 · Source

Requirements

  • Installation of a Level 2 or DC fast EV charger (EVSE) at a residential or commercial property in unincorporated Weber County — falls under the county's general Electrical Permit
  • Online Building Permit Application submitted at countyofweberut.portal.opengov.com
  • Compliance with the 2023 NEC, adopted statewide per Utah Code § 15A-2-103(1)(g)

Required documents

  • RequiredOnline Building Permit ApplicationSubmit at countyofweberut.portal.opengov.com; no distinct EV-charger application category exists.
  • OptionalElectrical Plan / Single-Line DiagramPanel schedule and circuit layout for the charger installation.
  • OptionalContractor LicenseValid Utah electrical contractor license (DOPL) for work not performed by the homeowner

Fee schedule

Fee typeAmountNotes
Electrical Permit (applies to EV charger/EVSE installation)$150.00Weber County Code § 12-3-8(1) (Ord. 2020-25, 12/22/2020). This flat electrical permit fee explicitly excludes only solar installations (valuation-based per § 12-3-6); no EV-charger carve-out or separate line item exists, so a standard EV/EVSE installation is billed under this general electrical rate.
State Surcharge1% of the permit feeWeber County Code § 12-3-8(1) (Ord. 2020-25, 12/22/2020).
Re-inspection Fee$115.00Weber County Code § 12-3-8(3) (Ord. 2020-25, 12/22/2020).

Plumbing Permit

Verified

Required for plumbing installations, alterations, and repairs in Unincorporated Weber County including water heaters, fixture additions, and drain or supply line work. Governed by the 2024 International Plumbing Code (IPC) as adopted by Utah Code § 15A-2-103 (effective July 1, 2026).

Verified 2026-07-16 · Source

Requirements

  • New plumbing fixture installations (sinks, toilets, showers)
  • Water heater installation or replacement
  • Water line or sewer line replacement or extension
  • Gas line installation or modification
  • Backflow prevention device installation

Required documents

  • RequiredOnline Building Permit ApplicationSubmit at countyofweberut.portal.opengov.com
  • OptionalPlumbing PlanRequired for larger projects — isometric or plan showing fixture locations, pipe sizes, and drainage
  • OptionalContractor LicenseValid Utah plumbing contractor license (DOPL) for work not performed by the homeowner

Fee schedule

Fee typeAmountNotes
Plumbing Permit$100.00Weber County Code § 12-3-8(1) (Ord. 2020-25, 12/22/2020)
State Surcharge1% of the permit feeWeber County Code § 12-3-8(1) (Ord. 2020-25, 12/22/2020)
Re-inspection Fee$115.00Weber County Code § 12-3-8(3) (Ord. 2020-25, 12/22/2020)

Mechanical / HVAC Permit

Verified

Required for heating, ventilation, and air conditioning installations, replacements, and ductwork modifications in Unincorporated Weber County. Governed by the 2024 International Mechanical Code (IMC) as adopted by Utah Code § 15A-2-103 (effective July 1, 2026).

Verified 2026-07-16 · Source

Requirements

  • Furnace or boiler installation or replacement
  • Air conditioning system installation or replacement
  • Ductwork installation or major modification
  • Evaporative cooler installation
  • Fireplace or wood-burning stove installation

Required documents

  • RequiredOnline Building Permit ApplicationSubmit at countyofweberut.portal.opengov.com
  • OptionalEquipment SpecificationsManufacturer data sheets for furnace, AC, heat pump, or evaporative cooler
  • OptionalMechanical PlanRequired for larger projects — equipment location, duct layout, sizing calculations

Fee schedule

Fee typeAmountNotes
Mechanical Permit$100.00Weber County Code § 12-3-8(1) (Ord. 2020-25, 12/22/2020)
State Surcharge1% of the permit feeWeber County Code § 12-3-8(1) (Ord. 2020-25, 12/22/2020)
Re-inspection Fee$115.00Weber County Code § 12-3-8(3) (Ord. 2020-25, 12/22/2020)

Roofing Permit

Verified

Required for roof replacement, re-roofing, and structural roof repairs in Unincorporated Weber County. Permit fees are valuation-based per the Weber County building permit fee schedule (Code § 12-3-6).

Verified 2026-07-16 · Source

Requirements

  • Complete roof replacement (tear-off and re-roof)
  • Overlay of new roofing over existing (where code allows)
  • Structural roof repairs or modifications
  • Changes to roofing material type

Required documents

  • RequiredOnline Building Permit ApplicationSubmit at countyofweberut.portal.opengov.com; include scope of work, square footage, and material specifications
  • OptionalContractor LicenseValid Utah roofing contractor license (DOPL) if not performed by the homeowner

Fee schedule

Fee typeAmountNotes
Roofing PermitValuation-based per Weber County Code § 12-3-6 (Ord. 2020-25, 12/22/2020) — same tier table as Residential Building Permit above. Valuation based on total contract value of roofing work.Weber County Code § 12-3-6 (Ord. 2020-25, 12/22/2020)
Plan Review (if required)35% of the building permit fee (SFD); 65% (commercial)Weber County Code § 12-3-8(2) (Ord. 2020-25, 12/22/2020)
State Surcharge1% of the permit feeWeber County Code § 12-3-8(1) (Ord. 2020-25, 12/22/2020)
Re-inspection Fee$115.00Weber County Code § 12-3-8(3) (Ord. 2020-25, 12/22/2020)

Solar Panel Permit

Verified

Required for installation of rooftop or ground-mounted solar photovoltaic systems in Unincorporated Weber County. Note: Weber County Code § 12-3-8(1) explicitly excludes solar installations from the standard $150 electrical permit fee — the applicable fee mechanism for solar is valuation-based per § 12-3-6.

Verified 2026-07-16 · Source

Requirements

  • Rooftop solar panel installation
  • Ground-mounted solar array installation
  • Battery storage system installation
  • Electrical service upgrade for solar interconnection

Required documents

  • RequiredOnline Building Permit ApplicationSubmit at countyofweberut.portal.opengov.com
  • RequiredSolar Site Plan / Roof PlanShowing panel placement, setbacks, and fire access pathways on the roof
  • RequiredElectrical Single-Line DiagramSystem wiring from panels to inverter to main panel and utility meter
  • RequiredStructural AnalysisRoof load calculation confirming structure can support the panels
  • RequiredEquipment SpecificationsData sheets for panels, inverter, and racking system
  • OptionalInterconnection AgreementRocky Mountain Power approval required before energizing grid-tied systems

Fee schedule

Fee typeAmountNotes
Solar Permit (building/structural component)Valuation-based per Weber County Code § 12-3-6 (Ord. 2020-25, 12/22/2020), using Building Valuation Data per § 12-3-7. The flat $150 electrical fee explicitly excludes solar installations per § 12-3-8(1); Title 12 publishes no separate flat solar fee, so the structural/installation permit is assessed on project valuation per the standard building-permit fee schedule.Grounded directly against the live Weber County Code text (weber.municipalcodeonline.com, Title 12, Sec 12-3-1 through 12-3-8, fetched 2026-07-01): § 12-3-1 places all building-permit-requiring work (including electrical/solar interconnection structural work) under the adopted Building Code fee schedule; § 12-3-8(1) excludes solar from the flat $150 electrical fee without publishing a substitute flat figure; § 12-3-6/12-3-7 (valuation-based, ICC Building Valuation Data) is therefore the applicable published fee mechanism. Valuation-based fee is a grounded fee per sweep criteria.
State Surcharge1% of the permit feeWeber County Code § 12-3-8(1) (Ord. 2020-25, 12/22/2020)
Re-inspection Fee$115.00Weber County Code § 12-3-8(3) (Ord. 2020-25, 12/22/2020)

Deck Permit

Verified

Required for new deck construction or structural modifications to existing decks in Unincorporated Weber County. Permit fees are valuation-based per County Code § 12-3-6.

Verified 2026-07-16 · Source

Requirements

  • New deck construction attached to the house
  • Decks higher than 30 inches above grade
  • Structural modifications to existing decks
  • Adding or replacing a deck ledger

Required documents

  • RequiredOnline Building Permit ApplicationSubmit at countyofweberut.portal.opengov.com
  • RequiredConstruction DrawingsFraming plan, footing details, ledger attachment method, and railing specifications
  • RequiredSite PlanShowing deck location, setbacks from property lines, and relationship to existing structure

Fee schedule

Fee typeAmountNotes
Deck PermitValuation-based per Weber County Code § 12-3-6 (Ord. 2020-25, 12/22/2020) — same tier table as Residential Building Permit above. Valuation based on ICC Building Valuation Data per § 12-3-7.Grounded directly against the live Weber County Code text (weber.municipalcodeonline.com, Title 12, fetched 2026-07-01). § 12-3-1 places all permit-requiring construction/alteration/addition work under the adopted Building Code; Title 12 publishes no separate flat deck fee, so § 12-3-6/12-3-7's valuation-based schedule is the applicable published fee mechanism, assessed on the project's contract valuation.
Plan Review — Single-Family Dwelling35% of the building permit feeWeber County Code § 12-3-8(2)(a) (Ord. 2020-25, 12/22/2020)
State Surcharge1% of the permit feeWeber County Code § 12-3-8(1) (Ord. 2020-25, 12/22/2020)
Re-inspection Fee$115.00Weber County Code § 12-3-8(3) (Ord. 2020-25, 12/22/2020)

Basement Finish Permit

Verified

Required for finishing or remodeling an unfinished basement in Unincorporated Weber County. Valuation is calculated at 50% of the ICC Building Valuation Data square-foot cost per Weber County Code § 12-3-7.

Verified 2026-07-16 · Source

Requirements

  • Framing walls in an unfinished basement
  • Adding a bedroom (requires egress window per IRC)
  • Adding a bathroom (requires plumbing permit)
  • Electrical wiring for new rooms
  • Any structural modifications

Required documents

  • RequiredOnline Building Permit ApplicationSubmit at countyofweberut.portal.opengov.com
  • RequiredFloor PlanLayout showing room sizes, egress windows, and door locations
  • OptionalElectrical PlanCircuit layout, panel capacity, smoke/CO detector locations

Fee schedule

Fee typeAmountNotes
Building Permit — Basement FinishValuation-based per Code § 12-3-6 (Ord. 2020-25, 12/22/2020). Finished basements are valued at 50% of the ICC Building Valuation Data square-foot cost per § 12-3-7 — then apply the permit fee tier table.Grounded directly against the live Weber County Code text (weber.municipalcodeonline.com, Title 12, fetched 2026-07-01) — § 12-3-7 confirmed verbatim: "Finished basements will be valued at 50 percent of the square foot construction cost table in the latest edition of the Building Valuation Data published by the International Code Council." Valuation-based fee against this published, cited standard is a grounded fee per sweep criteria.
Plan Review — Single-Family Dwelling35% of the building permit feeWeber County Code § 12-3-8(2)(a) (Ord. 2020-25, 12/22/2020)
State Surcharge1% of the permit feeWeber County Code § 12-3-8(1) (Ord. 2020-25, 12/22/2020)
Re-inspection Fee$115.00Weber County Code § 12-3-8(3) (Ord. 2020-25, 12/22/2020)

Water Heater Permit

Verified

Required for water heater installation, replacement, or conversion in Unincorporated Weber County. Pulled as a plumbing permit — the flat $100 plumbing fee applies per Weber County Code § 12-3-8(1).

Verified 2026-07-16 · Source

Requirements

  • Water heater replacement (including like-for-like swaps)
  • New water heater installation
  • Conversion from tank to tankless water heater
  • Gas line modification for water heater

Required documents

  • RequiredOnline Building Permit ApplicationSubmit at countyofweberut.portal.opengov.com
  • OptionalContractor LicenseValid Utah plumbing contractor license (DOPL) if not performed by the homeowner

Fee schedule

Fee typeAmountNotes
Water Heater (Plumbing Permit)$100.00Weber County Code § 12-3-8(1) (Ord. 2020-25, 12/22/2020) — water heater replacement is covered by the flat plumbing permit fee
State Surcharge1% of the permit feeWeber County Code § 12-3-8(1) (Ord. 2020-25, 12/22/2020)
Re-inspection Fee$115.00Weber County Code § 12-3-8(3) (Ord. 2020-25, 12/22/2020)

Demolition Permit

Verified

Required for partial or complete demolition of structures in Unincorporated Weber County. Permit fees are valuation-based per County Code § 12-3-6.

Verified 2026-07-16 · Source

Requirements

  • Complete demolition of any structure
  • Partial demolition involving structural elements
  • Removal of load-bearing walls
  • Demolition of structures with potential asbestos or lead paint (pre-1980 construction)

Required documents

  • RequiredOnline Building Permit Application / Demolition ApplicationSubmit at countyofweberut.portal.opengov.com; include scope of demolition, structure details, and disposal plan
  • OptionalAsbestos SurveyFederal NESHAP regulations require an asbestos inspection before demolition of structures that may contain asbestos-containing materials (typically pre-1980 construction)
  • RequiredUtility Disconnect ConfirmationProof that gas, electric, water, and sewer are disconnected prior to demolition — Weber County Code § 12-3-5 requires utility disconnection

Fee schedule

Fee typeAmountNotes
Demolition PermitValuation-based per Weber County Code § 12-3-6 (Ord. 2020-25, 12/22/2020). Per § 12-3-7, if a valuation is not otherwise specified for the work, the building official determines and assigns the per-square-foot valuation.Grounded directly against the live Weber County Code text (weber.municipalcodeonline.com, Title 12, fetched 2026-07-01). § 12-3-1 explicitly lists "demolition" among the regulated activities under the adopted Building Code fee schedule; Title 12 publishes no separate flat demolition fee. § 12-3-7 confirms that when a valuation is not specified, "the building official will determine and assign the per square foot valuation" — this is the published, cited fee mechanism, i.e., valuation-based per § 12-3-6/12-3-7.
State Surcharge1% of the permit feeWeber County Code § 12-3-8(1) (Ord. 2020-25, 12/22/2020)
Re-inspection Fee$115.00Weber County Code § 12-3-8(3) (Ord. 2020-25, 12/22/2020)

Commercial Building Permit

Verified

Required for new commercial construction in Unincorporated Weber County, per Weber County Code Title 12 and the state-adopted 2024 International Building Code. Uses the same valuation-based Building Permit fee table as residential permits (§ 12-3-6), plus a Commercial Plan Review fee of 65% of the building permit fee under § 12-3-8(2)(b).

Verified 2026-07-19 · Source

Requirements

  • New commercial construction
  • Any work regulated by the state-adopted 2024 IBC (Utah Code § 15A-2-103(1)(a), effective July 1, 2026)
  • Site plan review coordinated with the applicable zoning/land-use requirements for the parcel
  • Any work for which a building permit is required under the adopted codes, per Weber County Code § 12-3-1

Required documents

  • RequiredOnline Building Permit ApplicationSubmit at countyofweberut.portal.opengov.com. All items must be complete before plans are accepted for review.
  • RequiredConstruction PlansComplete drawings to scale: floor plans, elevations, sections, and structural details, stamped by a licensed engineer/architect as required for the occupancy classification. Submitted electronically through the OpenGov portal.
  • RequiredSite PlanProperty survey showing setbacks from property lines and footprint of structure.
  • RequiredEnergy Compliance DocumentationCompliance with the state-adopted IECC (commercial provisions).

Fee schedule

Fee typeAmountNotes
Building Permit — valuation-based (same tier table as Residential Building Permit)$69.25 for the first $2,000, scaling through published brackets to $5,608.75 for the first $1,000,000 plus $3.65 for each additional $1,000 or fraction thereofWeber County Code § 12-3-6 (Ord. 2020-25, 12/22/2020). No separate commercial-only valuation table is published; the same bracket table applies to residential and commercial permits.
Plan Review — Commercial65% of the building permit feeWeber County Code § 12-3-8(2)(b) (Ord. 2020-25, 12/22/2020).
State Surcharge1% of the building permit fee (excludes plan review fees)Weber County Code § 12-3-8(1) (Ord. 2020-25, 12/22/2020).
Re-inspection Fee$115.00Weber County Code § 12-3-8(3) (Ord. 2020-25, 12/22/2020).
After-Hours Inspection$125.00 per hour (must be requested and approved by County Building Official)Weber County Code § 12-3-8(7) (Ord. 2020-25, 12/22/2020).

Commercial Tenant Improvement / Tenant Finish Permit

Verified

Required for tenant improvement, remodel, or interior finish work in existing commercial space in Unincorporated Weber County. Weber County Code Title 12 does not publish a separate TI-specific fee line — TI/remodel work is billed under the same valuation-based Building Permit fee table (§ 12-3-6) and the same 65% Commercial Plan Review fee (§ 12-3-8(2)(b)) as new commercial construction.

Verified 2026-07-19 · Source

Requirements

  • Commercial tenant improvement, remodel, or interior finish scope in an existing commercial building
  • Any work regulated by the state-adopted 2024 IBC
  • Any work for which a building permit is required under Weber County Code § 12-3-1

Required documents

  • RequiredOnline Building Permit ApplicationSubmit at countyofweberut.portal.opengov.com
  • RequiredTenant Improvement / Remodel PlansFloor plan showing scope of work, and stamped structural plans where structural modifications are involved. Weber County does not publish a distinct TI-specific document checklist as of 2026-07-19; the general commercial plan-submittal requirements apply.

Fee schedule

Fee typeAmountNotes
Building Permit — valuation-based (same tier table as Residential/Commercial Building Permit)$69.25 for the first $2,000, scaling through published brackets to $5,608.75 for the first $1,000,000 plus $3.65 for each additional $1,000 or fraction thereofWeber County Code § 12-3-6 (Ord. 2020-25, 12/22/2020). No separate TI-specific valuation table is published.
Plan Review — Commercial65% of the building permit feeWeber County Code § 12-3-8(2)(b) (Ord. 2020-25, 12/22/2020). The same rate applies to TI/remodel work as to new commercial construction; no distinct TI line item exists in Title 12.
State Surcharge1% of the building permit feeWeber County Code § 12-3-8(1) (Ord. 2020-25, 12/22/2020).
Re-inspection Fee$115.00Weber County Code § 12-3-8(3) (Ord. 2020-25, 12/22/2020).

Fire Sprinkler System Permit

Verified

Required for installation of a fire suppression (sprinkler) system anywhere within Weber Fire District's service area, which covers all unincorporated areas of Weber County plus the incorporated cities of Farr West, Hooper, Huntsville, Marriott-Slaterville, Ogden Valley City, West Haven, and Uintah. Weber Fire District is a special service district separate from the Weber County Building Inspection Department (which handles the general building permit) — it maintains its own plan-review process and published Fee Schedule (effective January 1, 2026) tiered by sprinkler-head count.

Verified 2026-07-20 · Source

Requirements

  • Installation of a new fire suppression (sprinkler) system, per Weber Fire District's adopted current edition of NFPA 13, 13R, and 13D and the International Fire Code
  • Plans submitted electronically to the Fire Marshal's Office (prevention@weberfiredistrict.gov)
  • Approved plans and permits are not released until all applicable fees are paid
  • Allow up to 14 business days for the plan review process

Required documents

  • RequiredPlan Submittal ApplicationCompleted and submitted with each set of plans, per Weber Fire District's Plan Reviews & Permits page.
  • RequiredFire Suppression System PlansElectronic (PDF) plan set showing sprinkler head layout, submitted to prevention@weberfiredistrict.gov.

Fee schedule

Fee typeAmountNotes
Third Party Plan Review$50.00Weber Fire District Fee Schedule (effective 1/1/2026), Fire Protection Systems — Fire Sprinkler Systems.
Plan Review / Re-Review — 1-100 Sprinkler Heads$100.00Weber Fire District Fee Schedule (effective 1/1/2026).
Plan Review / Re-Review — 101-400 Sprinkler Heads$350.00Weber Fire District Fee Schedule (effective 1/1/2026).
Plan Review / Re-Review — 401+ Sprinkler Heads$500.00Weber Fire District Fee Schedule (effective 1/1/2026).
Permit (Includes 2 Inspections) — 1-100 Sprinkler Heads$175.00Weber Fire District Fee Schedule (effective 1/1/2026).
Permit (Includes 2 Inspections) — 101-300 Sprinkler Heads$325.00Weber Fire District Fee Schedule (effective 1/1/2026).
Permit (Includes 2 Inspections) — 301-500 Sprinkler Heads$500.00Weber Fire District Fee Schedule (effective 1/1/2026).
Permit (Includes 2 Inspections) — 501+ Sprinkler Heads$675.00Weber Fire District Fee Schedule (effective 1/1/2026).

Fire Alarm System Permit

Verified

Required for installation of a fire alarm system anywhere within Weber Fire District's service area, which covers all unincorporated areas of Weber County plus the incorporated cities of Farr West, Hooper, Huntsville, Marriott-Slaterville, Ogden Valley City, West Haven, and Uintah. Issued by Weber Fire District (a special service district separate from the Weber County Building Inspection Department) under its adopted current edition of NFPA 72 and the International Fire Code, tiered by building square footage.

Verified 2026-07-20 · Source

Requirements

  • Installation of a new fire alarm system, per Weber Fire District's adopted current edition of NFPA 72 and the International Fire Code
  • Plans submitted electronically to the Fire Marshal's Office (prevention@weberfiredistrict.gov)
  • Approved plans and permits are not released until all applicable fees are paid
  • Allow up to 14 business days for the plan review process

Required documents

  • RequiredPlan Submittal ApplicationCompleted and submitted with each set of plans, per Weber Fire District's Plan Reviews & Permits page.
  • RequiredFire Alarm System PlansElectronic (PDF) plan set, submitted to prevention@weberfiredistrict.gov.

Fee schedule

Fee typeAmountNotes
Third Party Plan Review$50.00Weber Fire District Fee Schedule (effective 1/1/2026), Fire Protection Systems — Fire Alarm System.
Plan Review / Re-Review — 1-50,000 Sq Ft$200.00Weber Fire District Fee Schedule (effective 1/1/2026).
Plan Review / Re-Review — 50,001+ Sq Ft$300.00Weber Fire District Fee Schedule (effective 1/1/2026).
Permit (Includes 2 Inspections) — 1-20,000 Sq Ft$250.00Weber Fire District Fee Schedule (effective 1/1/2026).
Permit (Includes 2 Inspections) — 20,001-50,000 Sq Ft$350.00Weber Fire District Fee Schedule (effective 1/1/2026).
Permit (Includes 2 Inspections) — 50,001+ Sq Ft$500.00Weber Fire District Fee Schedule (effective 1/1/2026).

Land Use Permit (Zoning / Change-of-Use Verification)

Verified

Weber County's Planning Division requires a Land Use Permit as a zoning-compliance verification step whenever a new business license is issued in unincorporated Weber County or Ogden Valley City — including when an existing building or tenant space is put to a new business use without any new construction. Per the Planning Division's own FAQ page: 'A Land Use Permit is a verification of zoning standards for building permit, business licenses etc. The Land Use Permit indicates zoning setback requirements and conditions that may be associated with the use.' It is distinct from, and required in addition to, any building permit or the business license fee itself.

Verified 2026-07-20 · Source

Requirements

  • Applies automatically to every new business license application (any Business, Home Occupation, or Short Term Rental license) in unincorporated Weber County or Ogden Valley City, per the County's Business License Portal
  • Verification that the proposed use meets zoning standards, setback requirements, and any conditions associated with that use for the parcel, per the Planning Division FAQ
  • Required prior to issuance of the business license and prior to issuance of any building permit, per the Planning Division FAQ ('A Land Use Permit is required prior to a Building Permit being issued')
  • Submitted through the Business License Portal (for business-use verification) or the Frontier development-project portal (frontier.co.weber.ut.us) for other Land Use Permit applications

Required documents

  • RequiredNew Business License ApplicationSubmitted online at the Weber County Business License Portal; the Land Use Permit fee is billed alongside the business license fee as part of this application.

Fee schedule

Fee typeAmountNotes
Land Use Permit issued with a new Business License$60.00 one-time feeWeber County Business License Portal (webercountyutah.gov/businesslicense): 'All new licenses will be issued a Land Use Permit which is a one time fee of $60.00, in addition to the business license fee which is based on your business type.' Matches the 'General Land Use Permit or Approval (not otherwise listed) Fee' line item of $60.00 on the Planning Division's official Fee Chart PDF.
General Land Use Permit or Approval (not otherwise listed)$60.00Weber County Planning Division Fee Chart PDF (webercountyutah.gov/planning/documents/Fee_Chart.pdf), General Permitting Fees section.
Land Use Permit Re-review Fee$30.00Weber County Planning Division Fee Chart PDF, General Permitting Fees section — charged if the initial Land Use Permit submittal requires a re-review.
Exempt Building Land Use Permit Fee$30.00Weber County Planning Division Fee Chart PDF, General Permitting Fees section — reduced-fee tier for exempt building types; listed separately from the standard Land Use Permit fee.

Sign Permit (Land Use Permit)

Verified

Required to erect, alter, or relocate any sign in Unincorporated Weber County. Weber County Land Use Code § 110-2-2 states: 'No person shall erect, alter or relocate any sign without first obtaining a land use permit.' Signage is governed by Land Use Code Title 110, Chapter 110-2 (Signs), which sets zone-specific standards, prohibits certain sign types, and requires sign structures to meet wind/seismic standards under the adopted Building Code. This is the same 'Land Use Permit' process documented for change-of-use verification elsewhere in this file — signs are one of the structure types (along with sheds, decks, and sports courts) that require it before a building permit is issued.

Verified 2026-07-22 · Source

Requirements

  • Erecting, altering, or relocating any sign not specifically exempted under Land Use Code § 110-2 (sign maintenance/repainting, qualifying flags, qualifying window signs, and certain government signs are exempt)
  • Compliance with the zone-specific sign standards in § 110-2 (Commercial & Manufacturing, Residential/Agricultural/Forest, or Recreation Resort zone standards)
  • A Master Signage Plan, reviewed through the Title 108 design-review process, where a site or building has multiple tenants or multiple signs allowed
  • A separate building permit for the sign structure itself where structural sufficiency (wind/seismic load) is at issue, per § 110-2's construction and safety standards

Required documents

  • RequiredLand Use Permit ApplicationSubmitted through the Planning Division's development project portal at frontier.co.weber.ut.us.
  • RequiredSign Plans / SpecificationsPlans, designs, specifications, dimensions, lighting details, colors, and installation information for the proposed sign, per § 110-2-2's application requirements.
  • OptionalMaster Signage PlanRequired only when a site or building has multiple tenants or multiple signs allowed; shows location, size, illumination, type, and dimensions for each sign.
  • OptionalStructural Engineer's CertificateMay be required where structural sufficiency of the sign (wind/seismic load) is in question, per § 110-2's construction and safety standards.

Fee schedule

Fee typeAmountNotes
Land Use Permit for Building Permit Fee$60.00 (Planning Division) + $40.00 (Engineering Division) = $100.00 totalWeber County Planning Division Fee Chart (PDF), General Permitting Fees section, read directly from the source PDF 2026-07-22. This is the same fee line this file's change-of-use-permit entry cites for signs: 'A Land Use Permit is also required before any building permit is issued for structures (sheds, decks, sports courts, signs, etc.)' Note: a separately-fetched rendering of the codified ordinance (weber.municipalcodeonline.com) suggested a different figure for a generic 'Land Use Permit' line ($150+$100=$250); that figure could not be independently confirmed against a primary document (unlike this PDF, which was read directly) and is NOT used here to avoid citing an unverified number.
Land Use Permit Re-review Fee$30.00Weber County Planning Division Fee Chart (PDF), General Permitting Fees section — charged if the initial Land Use Permit submittal requires re-review.
Building Permit for Sign Structure (where structural review applies)Valuation-based per Weber County Code § 12-3-6 — same tier table as this file's Residential Building Permit entryLand Use Code § 110-2 requires signs to meet wind/seismic load standards under the adopted Building Code and states a building permit is required for sign structures; Title 110 does not set a separate structural-permit fee, so the county's standard valuation-based Building Permit schedule (§ 12-3-6) is the applicable published mechanism.

Sources & verification

Verified against official sources. Last reviewed 2026-07-16.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Unincorporated Weber County building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.

← Earlier version (2026-07-01)View current record →All versions →

Permalink: /utah/weber-county/unincorporated-weber/as-of/2026-07-17/

Snapshot date: 2026-07-17

Commit: 0fd24e8

Reproducible from PermitBase’s version-controlled dataset, commit 0fd24e8.