Building Permit — Burien, Washington · Requirements sheet
Reviewed 2026-09-16 · Source: https://www.codepublishing.com/WA/Burien/html/Burien15/Burien1510.html
PermitBase is an independent reference and is not affiliated with any government agency. Requirements change and vary by project — confirm current details with the building department before you submit.
Building Permit in Burien, Washington
Required for construction in Burien. The city adopts the 2021 IBC, runs administration through its own Construction Administrative Code, and imposes aircraft noise envelope requirements near Seattle-Tacoma International Airport.
Reviewed 2026-09-16 · Source
When you need this permit
- Built to the 2021 IBC with Appendix Chapters E, H and J, and ICC A117.1 2017
- IBC Chapter 1 is replaced by BMC Chapter 15.05, the Construction Administrative Code
- If the site is in a Sea-Tac noise reduction area, BMC 15.12 envelope criteria apply
- Construction noise is prohibited 7:00 p.m. to 7:00 a.m. weekdays and 5:00 p.m. to 9:00 a.m. weekends
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 1 required documents checked.
This checker covers one permit. A full project usually triggers several — our checklist will assemble all of them, free →
Fee schedule
NO FEE AMOUNT IS STATED IN THIS ENTRY. Burien replaces IBC Chapter 1 with its own Construction Administrative Code at BMC Chapter 15.05 - "The Construction Administrative Code, as provided in Chapter… Show full citationHide
NO FEE AMOUNT IS STATED IN THIS ENTRY. Burien replaces IBC Chapter 1 with its own Construction Administrative Code at BMC Chapter 15.05 - "The Construction Administrative Code, as provided in Chapter 15.05 BMC, shall be used in place of IBC Chapter 1, Administration." - and that chapter, which is where permits, inspections and fees live, was NOT opened for this entry. A figure is declined rather than invented, and the reader is pointed at the chapter that holds it. WHAT THIS ENTRY CAN TELL YOU ABOUT COST IS NOT A FEE AT ALL: if the site is inside a Seattle-Tacoma International Airport noise reduction area, the envelope requirements in BMC 15.12 drive materially more expensive wall, window, door and roof assemblies and force a mechanical ventilation system. That will dwarf the permit fee.Review timeline
Inspection process
Tips
- CHECK WHICH AIRCRAFT NOISE ZONE THE SITE IS IN BEFORE DESIGNING - 35, 30 and 25 dB areas have different envelope criteria
- In a noise area the ventilation system must work without opening windows, so mechanical ventilation is effectively required
- A sub-500-square-foot addition loses its noise-chapter exemption if it contains a sleeping room
- Permits, inspections and fees are in BMC 15.05, not in the model code's Chapter 1
Frequently asked questions
Sources & verification
Key facts verified against official sources. Last reviewed 2026-09-16.
Codes & ordinances
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Burien building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Burien's permit history isn't searchable here yet
This page covers what the permit requires. What we don't have for Burien yet is the record of permits actually issued — the history you'd search by street address. That is a gap in our coverage, not a statement about any particular property.
Your email, and the place — never an address. We only use it to tell you when Burien lands. Privacy.
Other permits in Burien
Building Permit in other cities
Compare building permit fees across Washington →