Evanston building inspections

Verified

Inspection sequence, scheduling, and re-inspection fees for building permits in Evanston, Wyoming.

Verified 2026-07-01 · Source

How to schedule

Inspections are requested through the building department below.

Address
33 Allegiance Circle, Evanston, WY 82930
Phone
(307) 783-6470
Office hours
Monday through Thursday 7:30 am–5 pm; Friday 7:30 am–1:30 pm (City Hall hours; contact Building Department directly for its own hours)

Inspection sequence

Applies to: Residential Building Permit (New Construction)

  1. 1

    Sewer/Water Service Lines

    Line connections inspected prior to backfilling trenches

  2. 2

    Footings

    Property lines identified and setbacks checked; footing forms in place

  3. 3

    Foundation Reinforcing Steel (Rebar)

    All rebar (including ufer ground) in place and tied before concrete pour

  4. 4

    Foundation Wall

    After all forms and rebar in place, prior to pouring concrete

  5. 5

    Underground Plumbing

    After underground plumbing installed, prior to covering/concrete

  6. 6

    Rough Plumbing

    After all waste, vent, and water piping installed

  7. 7

    Rough Mechanical

    After venting and ductwork installed

  8. 8

    Electrical (State)

    Contact the State of Wyoming Electrical Inspector directly — not performed by the City

  9. 9

    Rough Framing

    After rough plumbing/mechanical approved and after roofing, framing, and fire blocking complete and structure weather-proofed

  10. 10

    Sheetrock

    After all sheetrock installed and fastened at required spacing

  11. 11

    Final Construction

    Building complete and ready for occupancy, including grading, sidewalks, driveways, curb box, and sewer clean-out to finished grade

  12. 12

    Certificate of Occupancy

    Required prior to moving furnishings into the building

Applies to: Plumbing Permit

  1. 1

    Underground Plumbing

    After underground plumbing installed and prior to covering/concrete

  2. 2

    Rough Plumbing

    After all waste, vent, and water piping installed

  3. 3

    Sewer/Water Service Lines

    Line connections inspected prior to backfilling trenches

  4. 4

    Final

    Fixtures connected, no leaks, water turned on only after meter installed and inspected

Applies to: Mechanical / HVAC Permit

  1. 1

    Rough Mechanical

    After all venting and ductwork installed

  2. 2

    Gas

    Contact local gas provider (Enbridge Gas) for gas line inspection — not performed by the City

  3. 3

    Final

    Equipment operational and inspected per approved plans

Applies to: Residential Addition / Remodel Permit

  1. 1

    Footing (if applicable)

    Property lines and setbacks checked; forms in place before concrete pour

  2. 2

    Rough Framing

    After rough plumbing/mechanical approved and roofing/framing/fire blocking complete

  3. 3

    Final Construction

    Work complete per approved plans

Applies to: Change of Use Permit

  1. 1

    Standard Building Permit Inspections (for the new use)

    Same inspection sequence as the underlying permit type matching the new use, culminating in a Certificate of Occupancy

  2. 2

    Certificate of Occupancy

    Issued once inspections for the new use are approved; required prior to occupying/using the space for the new use

Applies to: Fire Sprinkler / Fire Alarm Permit

  1. 1

    State Fire Protection Systems Inspection

    Performed by the Wyoming State Fire Marshal's Office regional fire inspector assigned to Uinta County/Bear River (Travis Mayer, per WSFM's Personnel and Inspectors listing)

  2. 2

    Local Fire Code Final Inspection

    Performed by the Uinta County Fire Protection and Emergency Services Joint Powers Board, acting as the City's designated IFC 'Chief'/'Fire Marshal' authority

Applies to: Solar PV Permit

  1. 1

    City Structural/Racking Inspection

    Roof penetration, racking attachment, and structural connections — performed by the City

  2. 2

    State Electrical Inspection

    PV interconnection wiring inspected by the Wyoming State Fire Marshal's electrical program, not the City

Sources & verification

Verified against official sources. Last reviewed 2026-07-01.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Evanston building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.

Evanston building permits

Get alerts for Evanston

We'll email you when Evanston's fees, documents, or codes change — not often.

We only use your email to send permit updates. No spam, unsubscribe anytime. Privacy.