Roofing Permit (Reroof) in Evanston, Wyoming

Same-type-for-same-type roof replacement does NOT require a permit in Evanston. A building permit IS required when changing roofing materials or structural elements.

Verified 2026-07-01 · Source

When you need this permit

  • Replacing roofing with the SAME type of material does not require a permit
  • Changing roofing materials or altering structural roof elements DOES require a building permit
  • New construction roofing is covered under the residential-building-permit or commercial-tenant-improvement-permit type

Required documents

Check off what you have — your progress is saved on this device.

    Fee schedule

    Building Permit Fee (when a permit is required — material/structural change)City of Evanston Engineering & Building Rate Sheet; no separate flat reroof fee line
    $0.010 × project cost (minimum charge $30.00)

    Review timeline

    Plan reviewTypical estimate — confirm current times with the Evanston building department
    ~1–10 business days

    How long did your Roofing Permit (Reroof) permit actually take in Evanston?

    Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

    Inspection process

    1. 1

      Final

      Completed roof inspected when a permit was required (material or structural change)

    See the full Evanston inspection guide — scheduling & re-inspection fees →

    Tips

    • Confirm with the Building Department whether your specific reroof project qualifies as 'same type for same type' before skipping the permit — this exemption is narrowly defined in the City's Repairs & Replacements guidance.

    Frequently asked questions

    Not if you are replacing the roofing with the same type of material. Changing materials or any structural roof elements requires a building permit from the City of Evanston Building Department.

    In Evanston, the published Building Permit Fee (when a permit is required — material/structural change) is: $0.010 × project cost (minimum charge $30.00). These are the jurisdiction's own published figures — see the fee schedule table and source citations on this page.

    Plan review for a roofing permit (reroof) in Evanston typically runs 1–10 business days. This is an estimate, not a published figure — confirm current review times with City of Evanston Engineering & Planning Department — Building Department at (307) 783-6470.

    Evanston requires 1 inspection(s) for a roofing permit (reroof), in order: Final. Schedule each through City of Evanston Engineering & Planning Department — Building Department ((307) 783-6470).

    Apply through City of Evanston Engineering & Planning Department — Building Department at 33 Allegiance Circle, Evanston, WY 82930. Phone: (307) 783-6470, email: jhergert@evanstonwy.org. Office hours: Monday through Thursday 7:30 am–5 pm; Friday 7:30 am–1:30 pm (City Hall hours; contact Building Department directly for its own hours). Official information: https://engineering-planning-evanstonwy.hub.arcgis.com/pages/5d3f1221a8a94c8d9d12e0c6e6d8bea9.

    Evanston, Wyoming has adopted: 2024 International Building Code (IBC) — current edition per City of Evanston Building Permit Legal Requirements; 2024 International Residential Code (IRC) — residential construction incorporates current IRC requirements per Evanston City Code § 7-52.1; 2021 Uniform Plumbing Code (UPC) provision cited for irrigation backflow prevention (UPC 608.17.5); confirm current adopted plumbing code edition with the Building Department; Evanston local design load values (wind, seismic, snow, frost depth) apply IN ADDITION TO the International codes — see localAmendments; IMPORTANT: Electrical work in Evanston is NOT governed by a City-adopted electrical code — electrical permitting and inspection is performed by the Wyoming State Fire Marshal's Office (Chief Electrical Inspector) under the state's default statewide electrical program (W.S. § 35-9-119), per the WSFM 'LOCAL AND STATE JURISDICTIONS' chart (Evanston = ELEC INSP/PR: S/S) and confirmed directly by the City's own Building Inspection Information sheet ('Electrical: Contact State of Wyoming Electrical Inspector'); IMPORTANT: Building PLAN REVIEW in Evanston has a state-law overlay — per W.S. § 35-9-108, the Wyoming State Fire Marshal must review and approve plans (in addition to city review) for: buildings/structures owned or leased by state/local government; buildings for general public access exceeding 5,000 sq ft total floor area; buildings over one story (incl. apartments/condos); childcare centers for more than 10 children; public bars/lounges/restaurants/night clubs/lodge halls/theatres/churches/public meeting places regardless of size; aboveground fuel dispensing facilities; alternate energy generation feeding the utility (incl. solar); Type I commercial kitchen exhaust hoods; spray finish applications; and buildings changing occupancy type — this matches the WSFM jurisdictions chart classification of Evanston building plan review as having a State component (STATE BLDG INSP/PR designation) alongside the City's own local building permit issuance and inspection program. Local amendments apply — see the Evanston overview page for the full list.

    Sources & verification

    Verified against official sources. Last reviewed 2026-07-01.

    Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Evanston building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.