Unincorporated Apache County building inspections
Inspection sequence, scheduling, and re-inspection fees for building permits in Unincorporated Apache County, Arizona.
Reviewed 2026-07-07 · Source
How to schedule
Inspections are requested through the building department below.
- Address
- 75 West Cleveland Street, PO Box 238, St. Johns, AZ 85936
- Phone
- 928-337-7527
- Office hours
- Mon–Fri (hours not published on county site; call 928-337-7527 to confirm)
- Website
- Official site
Inspection sequence
Applies to: Residential Building Permit (New Construction, One- and Two-Family Dwelling)
- 1
Foundation / Footing
Approved before ordering concrete; verify setbacks, trench depth, reinforcement, and Ufer ground per county Schedule of Inspections
- 2
Stem Wall / Foundation Wall
Approved before grouting — block/poured wall completion, reinforcement, anchors and straps
- 3
Under-Slab or Floor Framing
Under-slab piping/compaction approved before concrete pour; OR floor framing (sill plate, joists, girders) approved before floor sheathing
- 4
Roof Sheathing, Shear Walls and Anchorage
Approved before building wrap, window flashing, air barrier, and roof covering installation
- 5
Building Wrap / Window Flashing
Approved before pre-drywall/rough trades begin
- 6
Rough Combo (Framing, Plumbing, Electrical, Mechanical)
Approved before insulation installation and before drywall covering
- 7
Insulation
Approved before drywall covering — roof/ceiling R-38, floor R-30, walls R-15 minimum per county schedule
- 8
Drywall Nailing
Approved before tape and texture
- 9
Final
All trades complete (building, plumbing, electrical, mechanical, exterior site); Certificate of Occupancy issued on approval — no occupancy permitted prior to approved completion
Applies to: Commercial / Multi-Family Building Permit
- 1
Foundation / Footing
Approved before ordering concrete
- 2
Stem Wall
Approved before grouting
- 3
Framing, Electrical, Plumbing Rough-In
Combined rough-in inspection
- 4
Final
All work complete; Certificate of Occupancy issued on approval
Applies to: Change of Use / Change of Occupancy Permit
- 1
Plan Review
Building Safety reviews the submitted plans, including the code-analysis legend (occupancy, building type, allowable area, occupant load and plumbing fixture counts) that drives a change-of-occupancy determination. Plan review is charged at $50.00 per hour with a one-hour minimum; additional review required by changes or revisions is charged at the same rate.
- 2
Construction Inspections (if alteration work is performed)
Inspections are required for all phases of construction. The county's commercial requirements list foundation, footing, stem wall (before grouting), floor framing, framing/electrical/plumbing rough-in, and final. At least two (2) working days' notice is required for commercial inspections; call 928-337-7527. Per IBC Section 114, failure to request and complete required inspections can result in a stop work order or revocation of the building permit.
- 3
Final Inspection / Certificate of Occupancy
On approved completion a Certificate of Occupancy is issued; the county states plainly that no occupancy is allowed prior to approved completion. The validated permit card itself becomes the Certificate of Occupancy/Completion, signed by the Building Official.
Applies to: Electrical Permit
- 1
Rough-In / Service Inspection
Wiring installed before wall cover, or service equipment installed before energizing; verifies conductor sizing, landing, labeling, address posting, and grounding electrode per the county's minimum service requirements
- 2
Final / Green Tag
Apache County issues a 'green tag' clearance to energize once all minimum service requirements are verified; failure to meet requirements results in inspection failure and denial of the request
Applies to: EV Charger / EVSE Permit
- 1
Rough-In / Service Inspection
Required if the EV charger installation involves a new circuit or service equipment; verifies conductor sizing, landing, labeling, and grounding electrode per the county's minimum service requirements
- 2
Final / Green Tag
Apache County issues a 'green tag' clearance to energize once all minimum service requirements are verified
Applies to: Manufactured Home Installation Permit
- 1
First Safety Inspection (Installation Start)
Called in at the start of installation; building inspections 928-337-7527, septic inspections 928-337-7607
- 2
Final / Certificate of Occupancy
After all safety inspections pass, obtain the Certificate of Occupancy for the home and the Discharge Authorization for the septic system
Applies to: Sign Permit
- 1
Sign Identification Plate Verification
Each sign requiring a permit that is erected or remodeled must bear, in a permanent position, an identification plate stating the date the sign was erected and the name of the person, firm or entity responsible for its construction and erection (Zoning Ordinance Section 705.9)
- 2
Zoning Compliance / Enforcement Check
The Community Development Director enforces sign standards, may require the removal or repair of any sign in a dangerous or defective condition, and may cause immediate removal where a defective sign poses immediate danger, assessing costs against the property owner (Section 710.1). Signs on property that becomes vacant and unoccupied for thirty days or more are treated as abandoned and must be removed (Section 710.2).
Final inspection only: Solar PV Permit
Re-inspection fees
Sources & verification
Key facts verified against official sources. Last reviewed 2026-07-07.
Fee schedules
Applications & forms
Checklists & handouts
Online permit portal
Codes & ordinances
Department & other records
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Unincorporated Apache County building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Unincorporated Apache County building permits
Get alerts for Unincorporated Apache County
We'll email you when Unincorporated Apache County's fees, documents, or codes change — not often.
We only use your email to send permit updates. No spam, unsubscribe anytime. Privacy.