Electrical Permit in Unincorporated Apache County, Arizona

Required for electrical service installations, upgrades, and repairs in unincorporated Apache County, including service replacement and new-service energizing. Issued by the Building Safety Division; applicants must meet minimum service requirements before the county will issue a 'green tag' clearance to energize.

Reviewed 2026-07-07 · Source

When you need this permit

  • An electrical permit MUST be issued by Apache County before energizing a new or replacement service
  • Over-current protection devices must be properly sized for the conductors
  • Conductors must be landed and secured in the proper locations; correctly sized feeder conductors must be in place
  • Permanent labeling of circuits must be completed
  • Permanent physical address must be posted on the service entrance system
  • System grounding electrode conductor(s) must be installed
  • Minor listed work (temporary decorative lighting, reinstalling attachment-plug receptacles, replacing branch-circuit overcurrent devices of the same capacity in the same location, low-voltage <25V/50W equipment, and minor repairs/lamp replacement) is exempt from permit per adopted 2015 IRC §R105.2

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 2 required documents checked.

This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29

Fee schedule

Electrical PermitBuilding Safety Schedule of Fees and Valuations, Resolution 2019-1
$62
Reinspection FeeBuilding Safety Schedule of Fees and Valuations, Resolution 2019-1
$50 per hour

Review timeline

Plan review
Not published — contact the department

How long did your Electrical Permit permit actually take in Unincorporated Apache County?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    Rough-In / Service Inspection

    Wiring installed before wall cover, or service equipment installed before energizing; verifies conductor sizing, landing, labeling, address posting, and grounding electrode per the county's minimum service requirements

  2. 2

    Final / Green Tag

    Apache County issues a 'green tag' clearance to energize once all minimum service requirements are verified; failure to meet requirements results in inspection failure and denial of the request

See the full Unincorporated Apache County inspection guide — scheduling & re-inspection fees →

Tips

  • Apache County calls its energize-clearance a 'green tag' — any minimum requirement not met at inspection results in a failed inspection and the request to energize is denied outright, not just delayed.
  • Permanent physical address must be visibly posted on the service entrance system itself, not just at the property entrance, before the county will clear the service to energize.

Frequently asked questions

Unincorporated Apache County requires an electrical permit for: An electrical permit MUST be issued by Apache County before energizing a new or replacement service; Over-current protection devices must be properly sized for the conductors; Conductors must be landed and secured in the proper locations; correctly sized feeder conductors must be in place; Permanent labeling of circuits must be completed; Permanent physical address must be posted on the service entrance system; System grounding electrode conductor(s) must be installed; Minor listed work (temporary decorative lighting, reinstalling attachment-plug receptacles, replacing branch-circuit overcurrent devices of the same capacity in the same location, low-voltage <25V/50W equipment, and minor repairs/lamp replacement) is exempt from permit per adopted 2015 IRC §R105.2. If your project isn't listed, confirm with Apache County Community Development Department — Building Safety Division at 928-337-7527 before starting work.

In Unincorporated Apache County, the published Electrical Permit is: $62. Additional published fees: Reinspection Fee — $50 per hour. These are the jurisdiction's own published figures — see the fee schedule table and source citations on this page.

Unincorporated Apache County does not publish a plan-review timeline for this permit. Contact Apache County Community Development Department — Building Safety Division at 928-337-7527 for current turnaround.

You'll need: Building Permit Application; Minimum Requirements for Electrical Service Replacement and New Service Energizing. See the required-documents checklist on this page for details on each.

Unincorporated Apache County requires 2 inspection(s) for an electrical permit, in order: Rough-In / Service Inspection, Final / Green Tag. Schedule each through Apache County Community Development Department — Building Safety Division (928-337-7527).

Apply through Apache County Community Development Department — Building Safety Division at 75 West Cleveland Street, PO Box 238, St. Johns, AZ 85936. Phone: 928-337-7527. Office hours: Mon–Fri (hours not published on county site; call 928-337-7527 to confirm). Official information: https://www.apachecountyaz.gov/building-safety.

Unincorporated Apache County, Arizona has adopted: 2015 International Residential Code (IRC) — adopted by Apache County; governs all residential (one- and two-family dwelling) construction per the county's Building Safety Ordinances page and Requirements for One- and Two-Family Dwellings sheet; 2015 International Building Code (IBC) — adopted by Apache County; governs commercial, multi-family, and non-residential construction; 2015 International Plumbing Code (IPC) — adopted by Apache County for all plumbing work; 2015 International Fire Code (IFC) — adopted by Apache County; 2015 International Fuel Gas Code (IFGC) — adopted by Apache County; National Electrical Code (NEC) — adopted by Apache County; the county's published Building Safety Ordinances list names it '2014 International Electric Code' but the county's own Building Safety FAQ (question 11) states the applicable edition is the 2011 NEC for all non-residential/general construction electrical work. Both sources are county-published; this discrepancy is disclosed rather than resolved by guessing — treat 2011 NEC as the FAQ's more specific statement pending direct confirmation from the Building Safety Division at 928-337-7527.. Local amendments apply — see the Unincorporated Apache County overview page for the full list.

Yes, but it must be installed according to the safety standards of the adopted electrical code and requires an electrical/solar permit and inspection. Source: Apache County Building Safety FAQ, Question 4 (https://www.apachecountyaz.gov/building-safety)

Sources & verification

Key facts verified against official sources. Last reviewed 2026-07-07.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Unincorporated Apache County building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.