Electrical Permit — Unincorporated Apache County, Arizona · Requirements sheet
Reviewed 2026-07-07 · Source: https://www.apachecountyaz.gov/building-safety
PermitBase is an independent reference and is not affiliated with any government agency. Requirements change and vary by project — confirm current details with the building department before you submit.
Electrical Permit in Unincorporated Apache County, Arizona
Required for electrical service installations, upgrades, and repairs in unincorporated Apache County, including service replacement and new-service energizing. Issued by the Building Safety Division; applicants must meet minimum service requirements before the county will issue a 'green tag' clearance to energize.
Reviewed 2026-07-07 · Source
When you need this permit
- An electrical permit MUST be issued by Apache County before energizing a new or replacement service
- Over-current protection devices must be properly sized for the conductors
- Conductors must be landed and secured in the proper locations; correctly sized feeder conductors must be in place
- Permanent labeling of circuits must be completed
- Permanent physical address must be posted on the service entrance system
- System grounding electrode conductor(s) must be installed
- Minor listed work (temporary decorative lighting, reinstalling attachment-plug receptacles, replacing branch-circuit overcurrent devices of the same capacity in the same location, low-voltage <25V/50W equipment, and minor repairs/lamp replacement) is exempt from permit per adopted 2015 IRC §R105.2
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 2 required documents checked.
This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29 →
Fee schedule
Review timeline
Inspection process
- 1
Rough-In / Service Inspection
Wiring installed before wall cover, or service equipment installed before energizing; verifies conductor sizing, landing, labeling, address posting, and grounding electrode per the county's minimum service requirements
- 2
Final / Green Tag
Apache County issues a 'green tag' clearance to energize once all minimum service requirements are verified; failure to meet requirements results in inspection failure and denial of the request
See the full Unincorporated Apache County inspection guide — scheduling & re-inspection fees →
Tips
- Apache County calls its energize-clearance a 'green tag' — any minimum requirement not met at inspection results in a failed inspection and the request to energize is denied outright, not just delayed.
- Permanent physical address must be visibly posted on the service entrance system itself, not just at the property entrance, before the county will clear the service to energize.
Frequently asked questions
Sources & verification
Key facts verified against official sources. Last reviewed 2026-07-07.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Unincorporated Apache County building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Other permits in Unincorporated Apache County
Electrical Permit in other cities
Compare electrical permit fees across Arizona →
Look up this fee in a different city →
Related guides
Now live
Build your Unincorporated Apache County project checklist
Describe your project once and get every permit, document, and fee it triggers in Unincorporated Apache County — in one checklist. Sign up and pay once to generate it, or go unlimited with Pro.
Get started →