Residential Addition / Remodel / Accessory Structure Permit in Quartzsite, Arizona

Required for room additions, remodels, and accessory structures/buildings greater than 120 sq ft in the Town of Quartzsite, reviewed against the 2018 IRC as adopted and amended by the Town.

Verified 2026-07-07 · Source

When you need this permit

  • Building permit required for any commercial or residential improvement, addition, renovation, or accessory structure/building GREATER THAN 120 square feet, or not otherwise exempted under Chapter 150 (§ 150.02)
  • Accessory structures/buildings of 120 sq ft or less do not require a Town building permit under this threshold, though other Town Code provisions (e.g., zoning/setbacks) may still apply
  • Submittal via the Town's iWorq Citizen Portal
  • Fee calculated from the same Table 1-A valuation-based schedule as new construction — the Town does not publish a separate discounted valuation table for additions/remodels/accessory structures distinct from new construction

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 1 required documents checked.

This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29

Fee schedule

Building Permit Fee — Per Table 1-A (calculated via iWorq)Town of Quartzsite Schedule of Fees - Rates (2024), Schedule 2, Section 2-1
Calculated dynamically through iWorq per Table 1-A of the currently adopted International Building Code

Review timeline

Plan review
Not published — contact the department

How long did your Residential Addition / Remodel / Accessory Structure Permit permit actually take in Quartzsite?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    Foundation/Footing

    Required before concrete pour for additions/accessory structures over the 120 sq ft threshold

  2. 2

    Framing

    Structural connections to existing structure or new accessory-structure framing

  3. 3

    Final

    Completed work verified against approved plans

See the full Quartzsite inspection guide — scheduling & re-inspection fees →

Tips

  • The 120-sq-ft exemption threshold (§ 150.02) is the Town's own specific published cutoff for accessory structures/additions — smaller than some other AZ cities in this dataset (e.g., Buckeye's 200 sq ft). Confirm exact structure square footage against this threshold before assuming no permit is needed.
  • CONFIRMED GAP: as with new construction, no numeric review-timeframe is published by the Town for this permit type — see the new-construction entry's tips for the full exhaustive-chase trail (Town Code, Development Procedures Handbook, Fee Schedule, iWorq portal, and A.R.S. § 9-835 all checked directly, none publish a figure).

Frequently asked questions

Only if it is greater than 120 square feet, or not otherwise exempted under Town Code Chapter 150. Structures of 120 sq ft or less do not require a Town of Quartzsite building permit under this threshold, per § 150.02, though other zoning requirements may still apply.

In Quartzsite, the published Building Permit Fee — Per Table 1-A (calculated via iWorq) is: Calculated dynamically through iWorq per Table 1-A of the currently adopted International Building Code. These are the jurisdiction's own published figures — see the fee schedule table and source citations on this page.

Quartzsite does not publish a plan-review timeline for this permit. Contact Town of Quartzsite Community Development Department — Building Safety Division at 928-927-4333 ext. 601 for current turnaround.

You'll need: Building Permit Application (iWorq Citizen Portal). Depending on your project, Quartzsite may also ask for: Site Plan. See the required-documents checklist on this page for details on each.

Quartzsite requires 3 inspection(s) for a residential addition / remodel / accessory structure permit, in order: Foundation/Footing, Framing, Final. Schedule each through Town of Quartzsite Community Development Department — Building Safety Division (928-927-4333 ext. 601).

Apply through Town of Quartzsite Community Development Department — Building Safety Division at 465 N. Plymouth Ave. / PO Box 2812, Quartzsite, AZ 85346. Phone: 928-927-4333 ext. 601, email: thess@quartzsiteaz.org. Office hours: Monday - Thursday, 7:00 a.m. - 6:00 p.m. (closed Fridays); Fax 928-927-4400. All building, electrical, plumbing, mechanical, demolition, grading, sign, and manufactured/mobile home permit applications are submitted through the Town's iWorq Citizen Portal (quartzsite.portal.iworq.net/portalhome/quartzsite) — there is no separate PDF/paper Building Permit Application form published outside the portal. The portal's own instructions direct applicants to 'submit the application and wait for the City to contact you,' with no stated numeric response time.. Official information: https://www.ci.quartzsite.az.us/government/departments/community_development/index.php.

Quartzsite, Arizona has adopted: Arizona has NO statewide mandatory building code for general construction — code adoption is a per-jurisdiction (town/city/county) authority under state enabling statutes (A.R.S. Title 9 for municipalities). The Town of Quartzsite independently adopts and administers its own construction codes through its Community Development Department / Building Safety Division; it does NOT defer to La Paz County for permitting within incorporated town limits. La Paz County separately runs its own Building, Safety & Permits Department for unincorporated areas of the county (lapaz.gov/589) — a distinct code-administration regime from the Town's own department. Despite Quartzsite's small year-round population and famously seasonal RV/gem-show tourist economy, its Building Safety Division independently adopts, amends, and enforces its own full suite of ICC technical codes (confirmed via Town Code Chapter 150 and the Development Procedures Handbook) — it is a genuinely independent building department, not a pass-through to the County. Source: Town of Quartzsite Code of Ordinances, Chapter 150 (Building Regulations; Construction), via American Legal Publishing code library (codelibrary.amlegal.com/codes/quartzsiteaz); La Paz County Building, Safety & Permits page (lapaz.gov/589).; International Building Code (IBC), 2018 edition, including Appendices C, I, and J, adopted by reference (Town Code § 150.15), as published by the International Code Council. Source: Town of Quartzsite Code of Ordinances § 150.15 (amlegal.com), most recently amended by Ord. 23-06, passed 10-10-2023.; International Residential Code (IRC), 2018 edition, including Appendices G, H, P, and Q, adopted by reference (§ 150.21), for regulating detached one- and two-family dwellings and townhouses (multiple single-family dwellings) not more than three stories in height with separate means of egress. Source: Town of Quartzsite Code of Ordinances § 150.21 (amlegal.com).; National Electrical Code (NEC), 2017 edition, adopted by reference (§ 150.16), published by the National Fire Protection Association, governing electrical work in public and private buildings, mobile homes, recreational vehicles, floating buildings, yards/lots, industrial substations, and optical fiber cable. Source: Town of Quartzsite Code of Ordinances § 150.16 (amlegal.com).; International Mechanical Code (IMC), 2018 edition, including Appendix A, adopted by reference (§ 150.17). Source: Town of Quartzsite Code of Ordinances § 150.17 (amlegal.com), amended by Ord. 23-06, passed 10-10-2023.; International Plumbing Code (IPC), 2018 edition, including Appendices C and E, adopted by reference (§ 150.18), with locally added Chapter 10 grease-trap/interceptor maintenance (§ 1005) and enforcement (§ 1006) provisions. Source: Town of Quartzsite Code of Ordinances § 150.18 (amlegal.com), amended by Ord. 23-06, passed 10-10-2023.; International Fire Code (IFC), 2018 edition, including Appendices B, C, D, E, F, G, and I, adopted by reference (§ 150.19). Source: Town of Quartzsite Code of Ordinances § 150.19 (amlegal.com), amended by Ord. 23-06, passed 10-10-2023.; International Existing Building Code (IEBC), 2018 edition, adopted by reference (§ 150.20) as the town's code for the abatement of dangerous buildings, applicable to buildings/structures that endanger life, limb, health, morals, property, safety, or public welfare. Source: Town of Quartzsite Code of Ordinances § 150.20 (amlegal.com), amended by Ord. 23-06, passed 10-10-2023.; International Fuel Gas Code (IFGC), 2018 edition, including Appendices A and B, adopted by reference (§ 150.22). Source: Town of Quartzsite Code of Ordinances § 150.22 (amlegal.com), adopted/amended by Ord. 23-06.; International Property Maintenance Code, 2018 edition, including Appendix A, adopted by reference (§ 150.23). Source: Town of Quartzsite Code of Ordinances § 150.23 (amlegal.com), Ord. 23-06, passed 10-10-2023.; International Swimming Pool and Spa Code, 2018 edition, adopted by reference (§ 150.24). Source: Town of Quartzsite Code of Ordinances § 150.24 (amlegal.com), Ord. 23-06, passed 10-10-2023.; Manufactured homes, mobile homes, and park models are subject to a Town of Quartzsite Manufactured Home / Mobile Home / Park Model Set / Office Trailer Installation fee ($360.00 flat) for placement within town limits, per the Town's Schedule of Fees - Rates (2024), Schedule 2, Section 2-7; manufactured homes are additionally subject to State of Arizona regulation for the factory-built unit itself (Arizona Department of Housing, Office of Manufactured Housing, A.R.S. § 41-4001 et seq.). Source: Town of Quartzsite Schedule of Fees - Rates (2024).. Local amendments apply — see the Quartzsite overview page for the full list.

Sources & verification

Verified against official sources. Last reviewed 2026-07-07.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Quartzsite building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.