Solar PV Permit in Quartzsite, Arizona

Required for installation of rooftop or ground-mounted solar photovoltaic systems within Quartzsite town limits. There is no dedicated solar/photovoltaic permit type, application, or fee line published by the Town — a solar installation is submitted through the same single iWorq Citizen Portal 'Building Permit Application' used for all trades, with Building and Electrical scope checked, billed under the general Table 1-A valuation-based fee mechanism.

Verified 2026-07-19 · Source

When you need this permit

  • Submit via the Town's iWorq Citizen Portal (quartzsite.portal.iworq.net/portalhome/quartzsite) — no separate solar-specific application exists
  • Structural/roof-mounting scope reviewed against the 2018 IBC/IRC as adopted by the Town (§§ 150.15, 150.21)
  • Electrical-connection scope reviewed against the 2017 NEC as adopted by the Town (§ 150.16)
  • Exempt only if the installation qualifies under the Town's 120-sq-ft general permit-exemption threshold (§ 150.02) or another Chapter 150 exemption — in practice this rarely applies to a functional PV array's supporting structure/equipment
  • Fee calculated dynamically through iWorq per Table 1-A of the currently adopted International Code, the same mechanism used for all Building/Electrical/Plumbing permits in Quartzsite

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 1 required documents checked.

This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29

Fee schedule

Solar PV Permit Fee — Per Table 1-A (calculated via iWorq)Town of Quartzsite Schedule of Fees - Rates (2024), Schedule 2 — confirmed absence: Sections 2-1 through 2-9 itemize Building, Electrical, Plumbing, Grading, Encroachment, Manufactured Home, Re-Roofing default valuations, and Factory Built Building fees, but no separate 'Solar' or 'Photovoltaic' line exists anywhere in the schedule. Solar installations are billed under the general Building/Electrical Table 1-A mechanism like any other valuation-based improvement.
Calculated dynamically through iWorq per Table 1-A of the currently adopted International Code; no dedicated solar/photovoltaic line item exists in the Town's published 2024 Schedule of Fees - Rates

Review timeline

Plan review
Not published — contact the department

How long did your Solar PV Permit permit actually take in Quartzsite?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    Rough-In

    Structural mounting and electrical wiring/box placement before covering or energizing

  2. 2

    Final

    Completed installation verified against approved plans and the 2017 NEC as adopted by the Town

See the full Quartzsite inspection guide — scheduling & re-inspection fees →

Tips

  • There is no distinct Solar permit type in Quartzsite — apply through the same iWorq Citizen Portal Building Permit Application used for all other construction, checking both Building and Electrical scope.
  • Because fees are calculated dynamically inside iWorq per Table 1-A rather than published as a static table, you cannot precompute an exact solar permit fee without submitting through the portal.
  • CONFIRMED GAP: no numeric review-timeframe is published for any permit type in Quartzsite, including solar — budget informally and contact the Building Safety Division (928-927-4333 ext. 601) for a current estimate.

Frequently asked questions

Quartzsite requires a solar pv permit for: Submit via the Town's iWorq Citizen Portal (quartzsite.portal.iworq.net/portalhome/quartzsite) — no separate solar-specific application exists; Structural/roof-mounting scope reviewed against the 2018 IBC/IRC as adopted by the Town (§§ 150.15, 150.21); Electrical-connection scope reviewed against the 2017 NEC as adopted by the Town (§ 150.16); Exempt only if the installation qualifies under the Town's 120-sq-ft general permit-exemption threshold (§ 150.02) or another Chapter 150 exemption — in practice this rarely applies to a functional PV array's supporting structure/equipment; Fee calculated dynamically through iWorq per Table 1-A of the currently adopted International Code, the same mechanism used for all Building/Electrical/Plumbing permits in Quartzsite. If your project isn't listed, confirm with Town of Quartzsite Community Development Department — Building Safety Division at 928-927-4333 ext. 601 before starting work.

In Quartzsite, the published Solar PV Permit Fee — Per Table 1-A (calculated via iWorq) is: Calculated dynamically through iWorq per Table 1-A of the currently adopted International Code; no dedicated solar/photovoltaic line item exists in the Town's published 2024 Schedule of Fees - Rates. These are the jurisdiction's own published figures — see the fee schedule table and source citations on this page.

Quartzsite does not publish a plan-review timeline for this permit. Contact Town of Quartzsite Community Development Department — Building Safety Division at 928-927-4333 ext. 601 for current turnaround.

You'll need: Building Permit Application (iWorq Citizen Portal). See the required-documents checklist on this page for details on each.

Quartzsite requires 2 inspection(s) for a solar pv permit, in order: Rough-In, Final. Schedule each through Town of Quartzsite Community Development Department — Building Safety Division (928-927-4333 ext. 601).

Apply through Town of Quartzsite Community Development Department — Building Safety Division at 465 N. Plymouth Ave. / PO Box 2812, Quartzsite, AZ 85346. Phone: 928-927-4333 ext. 601, email: thess@quartzsiteaz.org. Office hours: Monday - Thursday, 7:00 a.m. - 6:00 p.m. (closed Fridays); Fax 928-927-4400. All building, electrical, plumbing, mechanical, demolition, grading, sign, and manufactured/mobile home permit applications are submitted through the Town's iWorq Citizen Portal (quartzsite.portal.iworq.net/portalhome/quartzsite) — there is no separate PDF/paper Building Permit Application form published outside the portal. The portal's own instructions direct applicants to 'submit the application and wait for the City to contact you,' with no stated numeric response time.. Official information: https://www.ci.quartzsite.az.us/government/departments/community_development/index.php.

Quartzsite, Arizona has adopted: Arizona has NO statewide mandatory building code for general construction — code adoption is a per-jurisdiction (town/city/county) authority under state enabling statutes (A.R.S. Title 9 for municipalities). The Town of Quartzsite independently adopts and administers its own construction codes through its Community Development Department / Building Safety Division; it does NOT defer to La Paz County for permitting within incorporated town limits. La Paz County separately runs its own Building, Safety & Permits Department for unincorporated areas of the county (lapaz.gov/589) — a distinct code-administration regime from the Town's own department. Despite Quartzsite's small year-round population and famously seasonal RV/gem-show tourist economy, its Building Safety Division independently adopts, amends, and enforces its own full suite of ICC technical codes (confirmed via Town Code Chapter 150 and the Development Procedures Handbook) — it is a genuinely independent building department, not a pass-through to the County. Source: Town of Quartzsite Code of Ordinances, Chapter 150 (Building Regulations; Construction), via American Legal Publishing code library (codelibrary.amlegal.com/codes/quartzsiteaz); La Paz County Building, Safety & Permits page (lapaz.gov/589).; International Building Code (IBC), 2018 edition, including Appendices C, I, and J, adopted by reference (Town Code § 150.15), as published by the International Code Council. Source: Town of Quartzsite Code of Ordinances § 150.15 (amlegal.com), most recently amended by Ord. 23-06, passed 10-10-2023.; International Residential Code (IRC), 2018 edition, including Appendices G, H, P, and Q, adopted by reference (§ 150.21), for regulating detached one- and two-family dwellings and townhouses (multiple single-family dwellings) not more than three stories in height with separate means of egress. Source: Town of Quartzsite Code of Ordinances § 150.21 (amlegal.com).; National Electrical Code (NEC), 2017 edition, adopted by reference (§ 150.16), published by the National Fire Protection Association, governing electrical work in public and private buildings, mobile homes, recreational vehicles, floating buildings, yards/lots, industrial substations, and optical fiber cable. Source: Town of Quartzsite Code of Ordinances § 150.16 (amlegal.com).; International Mechanical Code (IMC), 2018 edition, including Appendix A, adopted by reference (§ 150.17). Source: Town of Quartzsite Code of Ordinances § 150.17 (amlegal.com), amended by Ord. 23-06, passed 10-10-2023.; International Plumbing Code (IPC), 2018 edition, including Appendices C and E, adopted by reference (§ 150.18), with locally added Chapter 10 grease-trap/interceptor maintenance (§ 1005) and enforcement (§ 1006) provisions. Source: Town of Quartzsite Code of Ordinances § 150.18 (amlegal.com), amended by Ord. 23-06, passed 10-10-2023.; International Fire Code (IFC), 2018 edition, including Appendices B, C, D, E, F, G, and I, adopted by reference (§ 150.19). Source: Town of Quartzsite Code of Ordinances § 150.19 (amlegal.com), amended by Ord. 23-06, passed 10-10-2023.; International Existing Building Code (IEBC), 2018 edition, adopted by reference (§ 150.20) as the town's code for the abatement of dangerous buildings, applicable to buildings/structures that endanger life, limb, health, morals, property, safety, or public welfare. Source: Town of Quartzsite Code of Ordinances § 150.20 (amlegal.com), amended by Ord. 23-06, passed 10-10-2023.; International Fuel Gas Code (IFGC), 2018 edition, including Appendices A and B, adopted by reference (§ 150.22). Source: Town of Quartzsite Code of Ordinances § 150.22 (amlegal.com), adopted/amended by Ord. 23-06.; International Property Maintenance Code, 2018 edition, including Appendix A, adopted by reference (§ 150.23). Source: Town of Quartzsite Code of Ordinances § 150.23 (amlegal.com), Ord. 23-06, passed 10-10-2023.; International Swimming Pool and Spa Code, 2018 edition, adopted by reference (§ 150.24). Source: Town of Quartzsite Code of Ordinances § 150.24 (amlegal.com), Ord. 23-06, passed 10-10-2023.; Manufactured homes, mobile homes, and park models are subject to a Town of Quartzsite Manufactured Home / Mobile Home / Park Model Set / Office Trailer Installation fee ($360.00 flat) for placement within town limits, per the Town's Schedule of Fees - Rates (2024), Schedule 2, Section 2-7; manufactured homes are additionally subject to State of Arizona regulation for the factory-built unit itself (Arizona Department of Housing, Office of Manufactured Housing, A.R.S. § 41-4001 et seq.). Source: Town of Quartzsite Schedule of Fees - Rates (2024).. Local amendments apply — see the Quartzsite overview page for the full list.

No. Solar photovoltaic installations are submitted through the same iWorq Citizen Portal Building Permit Application used for all trades in Quartzsite, with Building and Electrical scope checked. Fees are calculated dynamically per Table 1-A of the currently adopted International Code — the Town's published 2024 Schedule of Fees - Rates has no dedicated solar/photovoltaic fee line.

Sources & verification

Verified against official sources. Last reviewed 2026-07-19.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Quartzsite building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.