Fountain Hills building inspections

Verified

Inspection sequence, scheduling, and re-inspection fees for building permits in Fountain Hills, Arizona.

Verified 2026-07-06 · Source

How to schedule

Inspections are requested through the building department below.

Address
Town Hall, 16705 E. Avenue of the Fountains, Fountain Hills, AZ 85268
Phone
480-816-5123
Office hours
Building Safety office hours for plan review, phone calls, front counter assistance and building code questions: Monday - Thursday, 7 a.m. - 6 p.m. Inspections are conducted 7 a.m. - 4 p.m. Monday through Friday. The Town of Fountain Hills only accepts permit applications online through T.O.P.P.S. (Town's Online Permitting and Planning System), a Citizenserve-hosted portal; there is no walk-in/paper submittal option. Source: Town of Fountain Hills Building Safety page (fountainhillsaz.gov/204/Building-Safety) and Building Permit Forms & Checklists page (fountainhillsaz.gov/502/Building-Permit-Forms-Checklists).

Inspection sequence

Applies to: Residential Building Permit (New Construction / Additions)

  1. 1

    Stormwater / Limits Fence

    Prior to permit issuance — BMPs, inlets, trackout pad and site limits fence per copy of site plan

  2. 2

    Footing

    Prior to placing concrete — copies of compaction tests required

  3. 3

    Foundation

    Prior to placing concrete or grout — required hold-downs installed, all steel tied, elevation set

  4. 4

    Under-Slab Plumbing/Heating/Electric

    Before fill placement; all piping under test

  5. 5

    Pre-Slab

    Before concrete is placed — pipes sleeved, footings formed

  6. 6

    Roof Diaphragm Nailing / Wall Shear Nailing

    Prior to dry-in — stamped truss calcs and ladder on site; windows installed, flashed, NFRC-labeled

  7. 7

    Rough Framing / Plumbing / Electrical / Mechanical

    Before top-out — gas/DWV/water under test, boxes/panel/service made up, gas appliance venting installed

  8. 8

    Insulation

    Before drywall — per approved plans

  9. 9

    Drywall

    After all insulation approved, before taping

  10. 10

    Final Grade & Site Improvements / Landscaping

    Before building final — site plan on site, landscape plan complete

  11. 11

    Final Building

    Gas/electric meters set, appliances operational, blower door test results provided

Applies to: Plumbing Permit (Water Heater / Minor)

  1. 1

    Under-Slab Plumbing

    Before fill placement — all piping under test, sticker on cleanout for tie-in

  2. 2

    Rough Plumbing

    Gas, DWV and water under test, before walls closed

  3. 3

    Sewer Final

    Before building final — sticker in panel

  4. 4

    Final Building

    Fixtures connected, water heater and gas connections verified

Applies to: Swimming Pool & Spa Permit

  1. 1

    Limits Fence

    Prior to permit issuance — provide copy of site plan showing temporary construction barrier

  2. 2

    Pre-Slab / Plumbing

    Pipes sleeved before concrete; pool plumbing under test

  3. 3

    Permanent Power / Electrical

    Pool electrical panel, bonding, and GFCI protection verified

  4. 4

    Final Building

    Barrier compliance, VGBA anti-entrapment devices, and equipment verified

Applies to: Electrical Permit (Minor / One-Discipline)

  1. 1

    Rough Electrical

    Boxes, panel and service made up, before walls are closed

  2. 2

    Permanent Power

    When top-out is approved; 2-20 amp GFCI receptacles installed

  3. 3

    Final Building

    Gas/electric meters set, appliances operational

Applies to: Residential Remodel Permit

  1. 1

    Rough Framing/Plumbing/Electrical/Mechanical

    Structural connections to existing structure, per the Town's 2024 Required Inspections list

  2. 2

    Insulation / Drywall

    Before and after drywall per approved plans

  3. 3

    Final Building

    Completed work verified against approved plans

Applies to: EV Charger / EVSE Permit

  1. 1

    Rough Electrical

    Conduit runs, wire sizing, disconnect placement before cover, per the Town's standard electrical rough-in inspection practice

  2. 2

    Final Electrical

    EVSE unit connections, breaker/disconnect, and grounding verified before energizing

Applies to: Fence and Retaining Wall Permit

  1. 1

    Retaining Wall Footings

    Prior to placing concrete or grout — reinforcement, forms, and shoring in place

  2. 2

    Final Building

    Completed fence/wall verified against approved plans

Applies to: Fire Sprinkler and Fire Alarm System Permit

  1. 1

    Rough Inspection

    All system components in place and secured, connected to the permanent water supply, approved 24x36 fire sprinkler plans on-site, and a cold-water test at a minimum of 200 psi for 2 hours showing no visible leakage or pressure reduction (residential/NFPA 13D systems); witnessed by the Fountain Hills Fire Department

  2. 2

    Final Inspection

    System flowed to verify activation of the flow switch and alarm bell; hydraulic design placard in place at the riser; spare sprinklers present in the riser compartment

Applies to: Mechanical / HVAC Permit (Minor Replacement)

  1. 1

    Rough Mechanical

    All gas appliance venting installed; installation manual and duct leakage report provided if required

  2. 2

    Final Building

    Equipment operational, clearances and combustion air verified

Applies to: Solar Photovoltaic & Energy Storage Permit

  1. 1

    Rough Electrical

    Conduit runs, wire sizing, disconnect placement before energizing

  2. 2

    Final Building

    Panel mounting, racking attachment, roof penetration sealing, electrical connections, interconnection point, and rapid-shutdown labeling verified

Re-inspection fees

Electrical Permit (Minor / One-Discipline)Reinspection Fee · Town of Fountain Hills Comprehensive Fee Schedule FY2026-2027.
$170.00 per inspection
Plumbing Permit (Water Heater / Minor)Reinspection Fee · Town of Fountain Hills Comprehensive Fee Schedule FY2026-2027.
$170.00 per inspection
Mechanical / HVAC Permit (Minor Replacement)Reinspection Fee · Town of Fountain Hills Comprehensive Fee Schedule FY2026-2027.
$170.00 per inspection
EV Charger / EVSE PermitReinspection Fee · Town of Fountain Hills Comprehensive Fee Schedule FY2026-2027.
$170.00 per inspection
Sign PermitReinspection Fee · Town of Fountain Hills Comprehensive Fee Schedule FY2026-2027, Building Fees — Commercial section (general reinspection fee applied to commercial permit types including signs).
$170.00 per inspection
Fire Sprinkler and Fire Alarm System PermitReinspection Fee (beyond one re-check) · Town of Fountain Hills Comprehensive Fee Schedule FY2026-2027, Fire Fees section. Assessed for, among other triggers, approved plans without an FHFD approval stamp on-site, incomplete installation, uncorrected prior deficiencies, or late/repeated inspection cancellations (per the Town's NFPA 13D interpretations, § 11.1.5).
$150.00 per request

Sources & verification

Verified against official sources. Last reviewed 2026-07-06.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Fountain Hills building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.

Fountain Hills building permits

Get alerts for Fountain Hills

We'll email you when Fountain Hills's fees, documents, or codes change — not often.

We only use your email to send permit updates. No spam, unsubscribe anytime. Privacy.